  RH-ISAC, Page 127 of 140  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  2199   Friday, March 12, 2021, 11:36 Travis CaveSouth Hot-CellMaintenance East Entrance ModuleEntrance module move The East Entrance Module has been
moved from the East Target Station to the
South Hot Cell.
  
  2200   Monday, March 15, 2021, 13:01 Isaac EarleCraneDevelopment  Plate & pin lift assembly load testing (ITA6550)In mid-2020 design analysis was completed
on the steel plate & pin assemblies (ITA6550)
used to connect the ISAC target hall crane
 11x 
  2201   Wednesday, March 17, 2021, 09:10 Travis CaveITEStandard Operation  Entrance module move The east entrance module is now back
at the east target station.
  
  2202   Wednesday, March 17, 2021, 11:43 Frank SongITERepair  Re-connect Entrance Module in ITE  David and I re-connect Entrance module
at ITE after the monitor been replaced at
SHC. 
 job_done_by_following_#190510.pdf 
  2204   Thursday, March 25, 2021, 08:55 Anders MjosConditioning StationMaintenance  Filters inspected and cleaned on water circuitBy Curtis. See Work Permit I2021-03-24-1
for details.
  
  2205   Thursday, March 25, 2021, 10:38 David WangSpent Target VaultStandard Operation C#1Remove pail 237 spent target C#1 from storage vault to mini storage. Pail 237 only has 200u sv/hr field at 0.5
meter. On contact measurement: 0.9 to 1.6
m sv/hr.and less than 80 count contamination
  
  2206   Friday, March 26, 2021, 12:22 Adam NewsomeCraneDevelopment  Aux Hoist Pendant UpgradeThe crane pendant for the auxiliary hoist
was upgraded to a FLEX EX2 style  pendant
by Canco Cranes. The installation work was
  
  2207   Monday, April 12, 2021, 13:45 Anders MjosCoolingMaintenance  New T installed for instrumentation loop on HALCW systemAdrian and co installed a new T to be able
to add an instrument loop for O2 and pH monitoring
on the low conductivity water systtem (photo).
 MicrosoftTeams-image_(9).png 
  2211   Wednesday, April 21, 2021, 11:18 David WangCoolingMaintenance  Refilling high active wtaer system and starting HA water pumps. High active water system is refilled. Air
are drained out of  system before pump
to be started. Following sequence are used
  
  2215   Monday, May 03, 2021, 15:14 Frank SongITEMaintenance  High voltage test in ITE Anders and I prepared ITE high voltage
test in April 30 ( Friday morning), The MAA
is locked for this.
  
  2216   Friday, May 14, 2021, 11:29 David WangSpent Target VaultStandard Operation  Repack of 4 spent targets.Repack of 4 spent targets in TH and SHC. 
SiC#37 to new pail249#. SiC#36 to new pail
250#. Nb#8 to new pail 247#, SiC#33 to new
  
  2217   Tuesday, May 25, 2021, 15:59 Matthew GareauNorth Hot-CellDevelopment  Removed boot from left hot manipulator Myself and Isaac removed the boot
from the left hot manipulator.
- opened the hatch in the TH to get
 7x 
  2218   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  Chiller maintenanceA contractor on site today for chiller
maintenance. CP2 and CP3 circuit is leaking
and shall not be used. CP1 can still be used.
  
  2219   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  TK2 refilledTank refilled from 12 in to 25 in using
the new valve.
  
  2230   Wednesday, June 30, 2021, 14:11 Matthew GareauNorth Hot-CellStandard Operation  North Hot Cell Commemorative Opening Yesterday a bottle of Cava (sparkling
wine) was place, opened, and poured in the
NHC, to commemorate its new operational status.
  
  2231   Wednesday, July 07, 2021, 11:59 Adam NewsomeSafe Module ParkingMaintenance  Annual Electrical and Mechanical InspectionAn annual electrical and mechanical inspection
was performed on the SMP today by Adam Newsome,
Dan McDonald, and Jason Zhang as per Work
 Capture.PNGPXL_20210707_162143876.jpgPXL_20210707_162918257.jpg 
  2234   Thursday, July 15, 2021, 09:02 Adam NewsomeSpent Target VaultStandard Operation  Emergency Close Mechanism TestThe emergency close mechanism for the Storage
Vault door was tested  by Adam Newsome and
Travis Cave. The door was opened to its fully
  
  2237   Friday, July 30, 2021, 16:31 Carla BabcockITERepair  ITE re-wireSee the attached for the way ITE has been
re-wired for the Ta62 run. Note also that
the copper block in the schematic on TBHT
 ISK4425D-rev9._APshortmitigationsvg_july27update.png 
  2239   Friday, August 06, 2021, 11:52 Travis CaveNorth Hot-CellStandard Operation UC#33Spent Target MoveUC#33 has been packed and moved from the north
hot cell to the spent target vault. See attached
PDF for 
 Target_Index_2021-08-06.pdf 
  2240   Tuesday, August 10, 2021, 10:16 Adam NewsomeSouth Hot-CellRepair  West Entrance Module Move to South Hot CellThe West Entrance Module has been moved
to the South Hot Cell for repair. 
  