ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  2214   Friday, April 30, 2021, 14:09 Luca EgoritiITE/ITWDevelopmentTM4 TM4 resistance measurements for P2N Friday, April 30, 2021, 14:06
Anders and Luca
Resistance measurements on each electrical
  
  2215   Monday, May 03, 2021, 15:14 Frank SongITEMaintenance  High voltage test in ITE Anders and I prepared ITE high voltage
test in April 30 ( Friday morning), The MAA
is locked for this.
  
  2216   Friday, May 14, 2021, 11:29 David WangSpent Target VaultStandard Operation  Repack of 4 spent targets.Repack of 4 spent targets in TH and SHC. 
SiC#37 to new pail249#. SiC#36 to new pail
250#. Nb#8 to new pail 247#, SiC#33 to new
  
  2217   Tuesday, May 25, 2021, 15:59 Matthew GareauNorth Hot-CellDevelopment  Removed boot from left hot manipulator Myself and Isaac removed the boot
from the left hot manipulator.
- opened the hatch in the TH to get
 7x 
  2218   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  Chiller maintenanceA contractor on site today for chiller
maintenance. CP2 and CP3 circuit is leaking
and shall not be used. CP1 can still be used.
  
  2219   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  TK2 refilledTank refilled from 12 in to 25 in using
the new valve.
  
  2220   Monday, May 31, 2021, 11:28 David WangITEStandard OperationTM4 Remotely remove TM4 from silo to shcRemotely remove tm4 from silo to shc. The
moving is smooth.
  
  2222   Thursday, June 03, 2021, 08:20 David WangSouth Hot-CellStandard OperationTM2 Remotely remove TM2 from silo to shcRemotely removed Tm2 from silo to SHC.
The moving is smooth. 
  
  2226   Wednesday, June 09, 2021, 10:48 David WangSouth Hot-CellStandard OperationTM2 TM2 containment box leak check. Chad installed containment box back to
TM2 yesterday. We leak checked VCR joints
on window line.    No leak.
  
  2230   Wednesday, June 30, 2021, 14:11 Matthew GareauNorth Hot-CellStandard Operation  North Hot Cell Commemorative Opening Yesterday a bottle of Cava (sparkling
wine) was place, opened, and poured in the
NHC, to commemorate its new operational status.
  
  2231   Wednesday, July 07, 2021, 11:59 Adam NewsomeSafe Module ParkingMaintenance  Annual Electrical and Mechanical InspectionAn annual electrical and mechanical inspection
was performed on the SMP today by Adam Newsome,
Dan McDonald, and Jason Zhang as per Work
 Capture.PNGPXL_20210707_162143876.jpgPXL_20210707_162918257.jpg 
  2234   Thursday, July 15, 2021, 09:02 Adam NewsomeSpent Target VaultStandard Operation  Emergency Close Mechanism TestThe emergency close mechanism for the Storage
Vault door was tested  by Adam Newsome and
Travis Cave. The door was opened to its fully
  
  2235   Tuesday, July 20, 2021, 09:46 Adam NewsomeITEStandard OperationTM4 Remotely moved TM4 from TCS to ITETM4 was moved from the conditioning station
to the East target station. 
  
  2237   Friday, July 30, 2021, 16:31 Carla BabcockITERepair  ITE re-wireSee the attached for the way ITE has been
re-wired for the Ta62 run. Note also that
the copper block in the schematic on TBHT
 ISK4425D-rev9._APshortmitigationsvg_july27update.png 
  2240   Tuesday, August 10, 2021, 10:16 Adam NewsomeSouth Hot-CellRepair  West Entrance Module Move to South Hot CellThe West Entrance Module has been moved
to the South Hot Cell for repair. 
  
  2241   Wednesday, August 11, 2021, 11:15 Adam NewsomeSpent Target VaultDevelopment  Mini-Storage: Cable track for e-chain installedA cable track was installed between the
mini-storage vault and the silos, for the
purpose of implementing a retractable cable
 PXL_20210811_165201449.jpg 
  2242   Thursday, August 12, 2021, 14:13 Adam NewsomeITWRepair  West Entrance Module Move to ITWThe West Entrance Module has been moved
from the South Hot Cell to the West Target
Station.
  
  2250   Thursday, September 23, 2021, 19:04 Adam NewsomeSpent Target VaultDevelopment  Mini-Storage: Remote CapabilityRemote capability was added for the mini-storage
door control. The control signals originate
from the Opto 22 Module box that is used
  
  2256   Wednesday, October 06, 2021, 10:42 David WangITERepair  ITE IG1S cable end connector replacementITE IG1S cable end connector replacement
has been finished by Roy Huang. 
  
  2268   Monday, November 15, 2021, 12:15 Adam NewsomeSouth Hot-CellRepair  Squeaking noise during turntable rotation - chain misalignment and improper tensionIt was noted on Nov. 9 that a squeaking
noise was present when the turntable was
rotated CCW with a module present.
 PXL_20211119_190640081.jpg 