Entry  Tuesday, March 23, 2021, 09:47, David Wang, South Hot-Cell, Standard Operation, TM3, , TM3 has been moved from TCS to SHC. 
Frank and I removed Tm3 from TCS to SHC. The move is successful. 
Entry  Thursday, March 25, 2021, 08:55, Anders Mjos, Conditioning Station, Maintenance, , , Filters inspected and cleaned on water circuit 
By Curtis. See Work Permit I2021-03-24-1 for details.
Entry  Friday, March 26, 2021, 12:22, Adam Newsome, Crane, Development, , , Aux Hoist Pendant Upgrade 
The crane pendant for the auxiliary hoist was upgraded to a FLEX EX2 style  pendant by Canco Cranes. The installation work was performed by  Canco, supervised
by Tom Kauss and David Wang.  Installation work was performed in one day (I2021-03-26-1).
Items installed include: new pendant (2 motion, 2 speed) 
Entry  Monday, April 12, 2021, 13:45, Anders Mjos, Cooling, Maintenance, , , New T installed for instrumentation loop on HALCW system MicrosoftTeams-image_(9).png
Adrian and co installed a new T to be able to add an instrument loop for O2 and pH monitoring on the low conductivity water systtem (photo). See WP I2021-04-09-4
Entry  Monday, April 12, 2021, 13:47, Anders Mjos, Assembly/Bench Test, Repair, TM4, , Steerer wiring TM4_Steerers_electric_check.pdf
Travis assembled and tested the steerer wires March 31st (see attached)
Entry  Wednesday, April 21, 2021, 10:32, David Wang, South Hot-Cell, Standard Operation, TM3, , Remotely remove TM3 from SHC to silo 
On 2021-04-19, Frank and I remotely removed Tm3 from SHC to silo . The moving is successful. 
Entry  Wednesday, April 21, 2021, 10:34, David Wang, South Hot-Cell, Standard Operation, TM4, , Remtely remove TM4 from Silo to SHC.  
On 2021- 04-20,  Tm4 is removed from Silo to SHC. The moving is smooth. 
Entry  Wednesday, April 21, 2021, 11:18, David Wang, Cooling, Maintenance, , , Refilling high active wtaer system and starting HA water pumps.  
High active water system is refilled. Air are drained out of  system before pump to be started. Following sequence are used to bring the whole system
back to operation:
1. close ITE , open ITW. Switch on the pump. Only 2A beam line related 5 water circuits are in loop in ITW.  Switch off pump when system pressure
Entry  Thursday, April 22, 2021, 08:41, David Wang, South Hot-Cell, Repair, TM4, , TM4 steerer electical check at SHC and TH. 
Using SHC electrical test cables routed to to TH,  We tested TM4 steerer  4 polarities. At 100v megga test, left, right , up and down to ground
are all OL. TM4 steerer has no short. 
Entry  Monday, April 26, 2021, 13:02, David Wang, South Hot-Cell, Repair, TM4, , TM4 new steerer cable installation. 
New steerer cables are installed in TM4. Cables are properly routed in containment box and service cap top. After job, TP2 is installed back onto module
top. 
Entry  Friday, April 30, 2021, 14:09, Luca Egoriti, ITE/ITW, Development, TM4, , TM4 resistance measurements for P2N 
 Friday, April 30, 2021, 14:06
Anders and Luca
Resistance measurements on each electrical feedthroughs (A,B,C,D,E,I,P,Q,R,U,60kV,ground) taken with no target or no short attached to the module.
Entry  Monday, May 03, 2021, 15:14, Frank Song, ITE, Maintenance, , , High voltage test in ITE 
 Anders and I prepared ITE high voltage test in April 30 ( Friday morning), The MAA is locked for this.
Entry  Friday, May 14, 2021, 11:29, David Wang, Spent Target Vault, Standard Operation, , , Repack of 4 spent targets. 
Repack of 4 spent targets in TH and SHC.  SiC#37 to new pail249#. SiC#36 to new pail 250#. Nb#8 to new pail 247#, SiC#33 to new pail 248#. 
They are all in mini storage. Also, UCx 31 are transferred to mini storage.  There are 5 spent targets in mini storage now.  
2021-05-20: 5 spent targets have been loaded into F308's. We transferred two more spent targets into mini storage this morning for next week loading.
Entry  Tuesday, May 25, 2021, 15:59, Matthew Gareau, North Hot-Cell, Development, , , Removed boot from left hot manipulator 7x
 Myself and Isaac removed the boot from the left hot manipulator.
- opened the hatch in the TH to get access to the top of the boot
- released the latch on the boot and loosened the boot from above
Entry  Tuesday, May 25, 2021, 16:20, Anders Mjos, Conditioning Station, Maintenance, , , Chiller maintenance 
A contractor on site today for chiller maintenance. CP2 and CP3 circuit is leaking and shall not be used. CP1 can still be used. The contractor will
contact Plant Group with a quote for repair and upgrades.
Entry  Tuesday, May 25, 2021, 16:20, Anders Mjos, Conditioning Station, Maintenance, , , TK2 refilled 
Tank refilled from 12 in to 25 in using the new valve.
Entry  Monday, May 31, 2021, 11:28, David Wang, ITE, Standard Operation, TM4, , Remotely remove TM4 from silo to shc 
Remotely remove tm4 from silo to shc. The moving is smooth.
Entry  Thursday, June 03, 2021, 08:20, David Wang, South Hot-Cell, Standard Operation, TM2, , Remotely remove TM2 from silo to shc 
Remotely removed Tm2 from silo to SHC. The moving is smooth. 
Entry  Wednesday, June 09, 2021, 10:48, David Wang, South Hot-Cell, Standard Operation, TM2, , TM2 containment box leak check.  
Chad installed containment box back to TM2 yesterday. We leak checked VCR joints on window line.    No leak. 
Entry  Wednesday, June 30, 2021, 14:11, Matthew Gareau, North Hot-Cell, Standard Operation, , , North Hot Cell Commemorative Opening 
 Yesterday a bottle of Cava (sparkling wine) was place, opened, and poured in the NHC, to commemorate its new operational status.
The NHC is now a functional hot cell and is ready for many years of target exchanges to come.