Entry  Wednesday, March 13, 2013, 15:26, Bevan Moss, Conditioning Station, Development, TM4, CS Test Target #1, Roughing Started 
 Roughing pumps were turned on at 15:23 13/03/2013.
Entry  Wednesday, March 13, 2013, 14:31, Bevan Moss, Conditioning Station, Standard Operation, TM4, CS Test Target #1, Module Move 
 TM4 with CS Test Target #1 was moved from the SHC to the Conditioning Station. All went well. The welding cables came a little close to the cage,
David will bend them in more in the future.
Entry  Wednesday, March 13, 2013, 14:30, Bevan Moss, Conditioning Station, Development, , , Faraday Cup 
 Dave Morris and I investigated the Faraday Cup today. It was found to be plumed in the wrong direction (fails in). This is not an issue for the
conditioning station as there is nothing down stream from the cup. Dave will change the controls to reflect this.
Entry  Wednesday, March 13, 2013, 11:23, chad fisher, South Hot-Cell, Repair, TM4, , Ground Electrode Leak 
The containment box has been re-installed and the window waterlines reconnected and leak checked.
The window lines did pass the leak check, however the leak dectoctor did not pump down past 5.8 x 10-9.
The front cover has also been reinstalled.
Entry  Wednesday, March 13, 2013, 07:22, chad fisher, South Hot-Cell, Repair, TM4, , Ground Electrode Leak / Inspection Results IMG_3449.JPGIMG_3450.JPGIMG_3451.JPGIMG_3452.JPGIMG_3454.JPG
Further attempts to localize the leak were unsucessful. The circuit was pressurized with 60 psi air and snoop solution was applied to both the braze
joints and the mating surface between the two halfs of the water blocks. Unfortunately, no visible bubbles could be dectected.
This was reported to Grant and Pierre and it was decided to continue with removing one of the vcr gaskets from the optics cooling lines (on the
Entry  Tuesday, March 12, 2013, 09:18, chad fisher, South Hot-Cell, Repair, TM4, , Ground Electrode Leak 
On Monday, March 11 the containment box was removed from TM4 and a vacuum leak check preformed in an attempt to locate the leak in the ground electrode
circuit.
Following Pierre's work plain helium was sprayed was the highest joint accessible towards the lowest.
Entry  Friday, March 08, 2013, 15:50, Bevan Moss, ITE, Standard Operation, TM4, CS Test Target #1, Module Move from ITE to SHC 
 Today David and I moved the module from ITE to the SHC. Move went very smoothly, David operated the cameras and has had basic training in how to
manually lock out the controls.
Entry  Wednesday, March 06, 2013, 14:12, David Wang, ITW, Repair, , , ITW EXIT1 tank to module o-ring replacement 
 ITW EXIT1  o-ring replacement is fininshed today. The ITW EXIT 1 is back to ITW.
The old o-ring lost most its elastic property and changed  to stiff sqaure shape inside the slot.The flange surface around the o-ring slot  was dirty.
I cleaned the o-ring surface completely before putting the new o-ring  . Everything should be fine now. There will be a leak check late
Entry  Wednesday, March 06, 2013, 12:50, Travis Cave, South Hot-Cell, Maintenance, , , module move 
ITW EX1 have been moved back to the west target station from the south hot cell.
Entry  Wednesday, March 06, 2013, 10:09, Travis Cave, ITW, Maintenance, , , module move 
ITW EX1 has been moved from the west target station to the south hot cell for the seal replacement on the west station.
Entry  Friday, March 01, 2013, 11:35, David Wang, ITE, Maintenance, TM4, , Leak check on ITE and TM4. 
 The leak  check on TM4 and ITE is done. All primary vacuum vessel , secondary vacuum
 vessel  on TM4 and ITE are leak tight. There is no any response had been found on leak detector(leak detector base LR 0.0xE-9 arm.cc/sec). All water
lines had been pressurized to  70 psi helium for 3 minutes. They are all perfect leak tight( I cant find even a  tiny response on leak detector) except
Entry  Tuesday, February 26, 2013, 13:53, David Wang, Conditioning Station, Repair, TM4, , Replaced TM4 TP1 
Bevan and I replaced TM4 TP1 today at conditioning station .The pump will be started this week when I do ITE and TM4 leak check .
Entry  Tuesday, February 26, 2013, 13:24, Travis Cave, Conditioning Station, Standard Operation, TM4, CS Test Target #1, module move 
TM#4 with CS Test Target #1 (dummy target) moved from the conditioning station to the east target station. Move went well.
Entry  Tuesday, February 26, 2013, 10:26, Travis Cave, ITW, Standard Operation, TM1, , module move 
TM1 moved from the west station to the southwest silo. Move went well.
Entry  Friday, February 22, 2013, 13:13, Bevan Moss, Conditioning Station, Development, TM4, CS Test Target #1, Broken Turbo Pump IMG_0528.JPG
 Today while putting the cover on the cord that goes to the controller was bumped. This bent the connector down and caused a vacuum leak. I tried
to tighten the bolts in the hope the leak would go away but it did not and I sheared one of the bolts off. David is inquiring with Edi if the pump can
be repaired or if it needs to be replaced. The good news is that the interlocks work exactly as planned. Upon detecting a leak they shut the turbos down
Entry  Friday, February 22, 2013, 13:02, Bevan Moss, Conditioning Station, Development, TM4, CS Test Target #1, HV test with Water vacuum_for_40k.JPG
 Hello Ray and Yi
Completed a HV test with the water flowing today.
8.96 Mohm
Entry  Thursday, February 21, 2013, 14:05, David Wang, ITW, Repair, TM1, , Disconnected EXIT1 in ITW. 
Disconnected EXIT1 in ITW. All cables , wires and air lines are label marked.
Entry  Thursday, February 14, 2013, 09:31, David Wang, ITW, Repair, , , ITH MP1 is replaced. 
Edi and I replaced the broken ITH MP1 in target hall with a new pump. The old pump was leak on oil. There were no oil had been left in the old pump by
checking the sight glass.Thats the reason of  the pump  failure.The tray which the old pump sat on was full of leaking oil ( highly contaminated
). The old pump was bagged in 3 thick plastic bags ,and the tray was cleaned before the new pump was installed. The working area had been cleaned up and
Entry  Friday, February 08, 2013, 11:42, Grant Minor, ITE, Maintenance, , , TAPC 477 resolved - ISAC elec. room gas cylinder TAPC-477_resolved_8Feb2013.pdf
See attached TAPC 477 documentation.
Entry  Wednesday, February 06, 2013, 14:34, Bevan Moss, Conditioning Station, Development, TM4, CS Test Target #1, 40kV All Common w/o Water Test 40kV_no_water_HV_test.JPG
 Today the module was biased to 40kV in the conditioning station. The current draw was 0uA. Sparking started at 27 kV. I have attached the recording
from the strip tool of the vacuum while we were testing. After consulting Pierre if we should take the module to a higher voltage it was decided not to.
The purpose of this test we to check the interaction between the module, cover, new cooling line, EE and EINZEL cables. This test was considered a success