274
|
Saturday, March 23, 2013, 18:14 |
Aurelia Laxdal | Conditioning Station | Development | TM4 | FEBIAD HP with Dummy Target | Commissioning TCS - Part 2 Completed | After few hickups the TCS was successfuly
commissioned.
In the morning, in the middle of |
|
1095
|
Tuesday, October 06, 2015, 21:12 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | TM3 service cap inspection in target hall | David Wang and I did the service cap inspection
in target hall: see WP I2015-10-06-10.<br>
Signs of sparking were seen underneath |
|
1250
|
Thursday, June 02, 2016, 18:04 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
|
|
1252
|
Friday, June 03, 2016, 16:04 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
|
|
1289
|
Tuesday, July 19, 2016, 14:35 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | | TM3 leak checked at TCS |
|
|
1414
|
Monday, December 05, 2016, 10:04 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | | TM3 vacuum system have been connected at TCS. |
|
|
1417
|
Friday, December 09, 2016, 18:05 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | | TM3 vacuum system have been connected at TCS. |
|
|
1493
|
Wednesday, April 12, 2017, 16:39 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | no target | TM3 Inspection at the South Hot Cell | Found spark signs on TM3's containment
on the side of the water blocks. They may
be OLD or/and NEW sparking signs, but this |
|
1508
|
Wednesday, April 26, 2017, 16:52 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | TM3 Lower Service Tray Video Inspection |
|
|
1509
|
Wednesday, April 26, 2017, 17:37 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | no target | TM3 HV tests at atmosphere Pictures from April 19-21, 2017 |
Please see the first two pictures
of the HV test at atmosphere done on April |
|
1510
|
Wednesday, April 26, 2017, 17:55 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | no target | TM3 Schedule updates at the South Hot Cell and CS | Please see TM3's Updated Schedule (the
current schedule) at the SHC and TCS.
For the record I am uploading TM3's |
|
1512
|
Thursday, April 27, 2017, 19:59 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | no target | TM3 HV tests at atmosphere for Each Line(s) April 27, 2017 | Today a HV test at atmosphere was performed
for Each Line(s), while floating the other
lines. |
|
1514
|
Sunday, April 30, 2017, 20:57 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | no target | TM3 May 1-15, 2017 Tentative Schedule at the SHC and TCS | Please see attachment for TM3 May 1-15,
2017 Tentative Schedule at the SHC and TCS. |
|
1520
|
Tuesday, May 02, 2017, 18:33 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | no target | TM3 HV tests at atmosphere for Each Line(s) after the Fiber Glass removal May 2, 2017 | Today a HV test at atmosphere was performed
for Each Line(s), while floating the other
lines. THIS TEST AT ATMOSPHERE IS THE FIRST |
|
1522
|
Thursday, May 04, 2017, 19:10 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | no target | TM3 HV test at TCS up to 50kV | Today TM3 was conditioned up to 50kV. At
50kV sparking started and to go higher in
voltage it needs more conditioning time. |
|
1525
|
Friday, May 05, 2017, 19:36 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | no target | TM3 HV test at TCS up to 65kV | Today TM3 HV conditioning went up to 65kV.
I'll leave it here over night. ISAC OPS have
instructions to keep an alarm on the HV, |
|
1526
|
Saturday, May 06, 2017, 13:30 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | no target | TM3 current limiting | Today the voltage was raised from 65kV
to 65.7kV. After about 10min at this level
TM3 started current limiting. TM3 was not |
|
1585
|
Monday, July 17, 2017, 17:50 |
Aurelia Laxdal | Conditioning Station | Development | TM3 | No target | Conditioning TM3 |
|
|
2452
|
Tuesday, June 06, 2023, 15:10 |
Antoniette Yap | Spent Target Vault | Maintenance | | | Annual Inspection of Main and Mini Storage Vaults | The annual inspection of the mini-storage
vault and main storage vault was completed
June 23, 2023. The following items were checked: |
|
78
|
Tuesday, March 13, 2012, 12:24 |
Anders Mjos | South Hot-Cell | Standard Operation | TM1 | UCx#3 | UCx#3 Autopsy |
|
|