  260   Wednesday, March 13, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Module Move TM4 with CS Test Target #1 was moved
from the SHC to the Conditioning Station.
All went well. The welding cables came a
  
  261   Wednesday, March 13, 2013, 15:26 Bevan MossConditioning StationDevelopmentTM4CS Test Target #1Roughing Started Roughing pumps were turned on at
15:23 13/03/2013.
  
  264   Thursday, March 14, 2013, 10:04 Bevan MossConditioning StationStandard OperationTM4CS Test Target 1Cooling Package Started The cooling package was started at
10:00 today. See attached picture. There
is another snap shot at 10:03.
 Cooling_system_start.JPGCooling_System_start_3_min.JPG 
  265   Thursday, March 14, 2013, 11:25 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Turbos Started Turbos started at 11:14. TP1S achieved
full speed in less than 2 minutes. TP1 and
2 tripped at 9 minutes. Restarted and reached
 turbo_started_1115.JPGvacuum_running_1124.JPG 
  266   Thursday, March 14, 2013, 11:56 Bevan MossConditioning StationStandard OperationTM4CS Test Target 1Cooling Package Started

    

       
            
 Cooling_package_1155.JPG 
  267   Monday, March 18, 2013, 12:03 Bevan MossConditioning StationRepairTM4CS Test Target #1Turbo Pump 1 Failure and Venting Over the weekend Turbo pump one failed.
It was attempted to restart the turbo in
soft start but that also failed. Although
  
  268   Monday, March 18, 2013, 12:39 Bevan MossConditioning StationRepairTM4CS Test Target #1TGHT PS FailureThe Model of the Power
Supply (PS) is TSQLG 480-20/1500 and serial
number is 2755.02.01.01.09. 
 IMG_0529.JPG 
  269   Monday, March 18, 2013, 15:28 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Vented With Argon The conditioning station has been
vented with argon. Time taken is not known
but it is less than 3 hours. See attached
 Vented_with_Argon.JPG 
  270   Tuesday, March 19, 2013, 09:55 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Turbo pump 1 replaced roughing started David replaced the broken turbo pump
this morning and I have started roughing
at 9:54.
  
  271   Tuesday, March 19, 2013, 13:49 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Tubros Started Turbo Pumps have been started and
are in normal operation. TP1 which has recently
been replaced was started in soft start and
  
  275   Monday, March 25, 2013, 09:35 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Cooling Package and Vacuum Stopped The cooling package and vacuum was
stopped today at 9:26 so the module can be
move.
  
  276   Monday, March 25, 2013, 10:59 Bevan MossConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 2 Completed

    

       
            
 IRH1511.pdfISK4574D-rev7.pdf 
  288   Thursday, April 04, 2013, 12:07 Bevan MossConditioning StationStandard OperationTM1Ta #39Roughing started Roughing started at 12:06. It was
believed there was a problem with the compressed
air but there was none, TM1 doesn't leak
  
  289   Thursday, April 04, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM1Ta #39Roughing started

    

       
            
  
  292   Monday, April 08, 2013, 16:16 Bevan MossConditioning StationStandard OperationTM1Ta #39Venting with Argon TM1 started venting at 4:15 pm with
Argon. I will leave the valve open over night.
  
  304   Wednesday, April 17, 2013, 15:17 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Failed Both Turbo pumps on TM3 have failed.
They were both attempted to start in soft
mode. TP2 could only achieve ~19kpm and TP1
  
  305   Friday, April 19, 2013, 10:48 Bevan MossConditioning StationMaintenanceTM3N/ATurbo Pump 2 replaced Turbo Pump 2 has been replaced on
TM3. I got a count of 350 on the sleeve of
my tank suit.
  
  306   Friday, April 19, 2013, 10:48 Bevan MossConditioning StationMaintenanceTM3N/ATurbo Pump 2 replaced Turbo Pump 2 has been replaced on
TM3. I got a count of 350 on the sleeve of
my tank suit.
  
  307   Friday, April 19, 2013, 10:51 Bevan MossConditioning StationStandard OperationTM3N/ARoughing Started 10:48With the Turbo pump replaced I have started
roughing at 10:48
  
  308   Friday, April 19, 2013, 13:32 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Started Both Turbo Pumps are now operational.   