Message ID: 2581     Entry time: Thursday, May 02, 2024, 18:48
Author: Carla Babcock 
Category: ITW 
Type: Standard Operation 
Module:  
Target/Number:  
Subject: ITW cage setup 

ITW gas lines pumped down to 2e-3Torr on leak detector with leak rate in the low e-7 atm-cc/s. Gas bottles opened at 3psi and labels in epics changed to reflect correct setup. switch box set to cathode mode, checked that anode wire was at HV common.

note ballast is removed from ITW now to be used in ITE so that line is blanked off.