  275   Monday, March 25, 2013, 09:35 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Cooling Package and Vacuum Stopped The cooling package and vacuum was
stopped today at 9:26 so the module can be
move.
  
  276   Monday, March 25, 2013, 10:59 Bevan MossConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 2 Completed

    

       
            
 IRH1511.pdfISK4574D-rev7.pdf 
  288   Thursday, April 04, 2013, 12:07 Bevan MossConditioning StationStandard OperationTM1Ta #39Roughing started Roughing started at 12:06. It was
believed there was a problem with the compressed
air but there was none, TM1 doesn't leak
  
  289   Thursday, April 04, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM1Ta #39Roughing started

    

       
            
  
  292   Monday, April 08, 2013, 16:16 Bevan MossConditioning StationStandard OperationTM1Ta #39Venting with Argon TM1 started venting at 4:15 pm with
Argon. I will leave the valve open over night.
  
  304   Wednesday, April 17, 2013, 15:17 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Failed Both Turbo pumps on TM3 have failed.
They were both attempted to start in soft
mode. TP2 could only achieve ~19kpm and TP1
  
  305   Friday, April 19, 2013, 10:48 Bevan MossConditioning StationMaintenanceTM3N/ATurbo Pump 2 replaced Turbo Pump 2 has been replaced on
TM3. I got a count of 350 on the sleeve of
my tank suit.
  
  306   Friday, April 19, 2013, 10:48 Bevan MossConditioning StationMaintenanceTM3N/ATurbo Pump 2 replaced Turbo Pump 2 has been replaced on
TM3. I got a count of 350 on the sleeve of
my tank suit.
  
  307   Friday, April 19, 2013, 10:51 Bevan MossConditioning StationStandard OperationTM3N/ARoughing Started 10:48With the Turbo pump replaced I have started
roughing at 10:48
  
  308   Friday, April 19, 2013, 13:32 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Started Both Turbo Pumps are now operational.   
  309   Friday, April 19, 2013, 15:25 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Started

    

       
            
  
  311   Monday, April 22, 2013, 11:31 Bevan MossConditioning StationStandard OperationTM3N/ACooling Package Started Cooling Package was started at 9:25
this morning inlet conductivity is 0.08 Mohm
at 22.9C. Resistance reached 5.33 Mohm by
  
  312   Monday, April 22, 2013, 11:35 Bevan MossConditioning StationRepairTM3N/ATCS:DIF2 broken The flow meter on the primary side
(TCS:DIF2) of the conditioning station is
broken. I investigated and there is flow,
  
  313   Tuesday, April 23, 2013, 11:19 Bevan MossConditioning StationStandard OperationTM3N/AHV Test All common A HV test was conducted yesterday
on TM3. There was no target and all items
were tied to common or ground. The conductivity
 TM3_40kV_22042013.txt22042013_TM3_40kV_Archiver.csvRGA_files.zip 
  314   Tuesday, April 23, 2013, 13:48 Bevan MossConditioning StationStandard OperationTM3N/AEL testingThis morning the Einzel Lens was tested
on TM3 as the intention is to reuse this
piece of equipment. The EL was able to achieve
 23042013_TM3_EL_RGA.zip23042013_TM3_EL_39.csv 
  315   Tuesday, April 23, 2013, 15:52 Bevan MossConditioning StationStandard OperationTM3N/AFurther HV Testing Further HV testing was completed
today from ~2:00 until 3:00. The resistivity
of the water was 11.7 - 12.7 Mohm. The EE
 TM3_BIAS_EE_CB_23042013.xlsxTM3_BIA_EE_CD_23042013_RGA_files.zip 
  316   Tuesday, April 23, 2013, 15:59 Bevan MossConditioning StationStandard OperationTM3N/ASystems off Both the Cooling Package and
Vacuum have been turned off in preparation
for the module move tomorrow
  
  317   Tuesday, April 23, 2013, 16:11 Bevan MossConditioning StationMaintenanceTM3N/AChiller Fault 2 During Testing it was noticed that
Fault 2 was indicated and one of the compressors
would not run. Fault 2 does not indicate
  
  318   Wednesday, April 24, 2013, 09:00 Bevan MossConditioning StationDevelopment  New user testing Controls has created a new user group
that can operate the conditioning station
but cannot use any of the bypasses or forces.
  
  325   Monday, April 29, 2013, 15:58 Bevan MossSouth Hot-CellRepairTM3 Source Tray RemovalChad removed the source tray from TM3  today,
see attached picture (video was also taken).
There was some interference between the window
 20130429_TM3_SOURCE_TRAY_REMOVAL_IMG_0620.JPG 