Entry  Thursday, July 09, 2015, 14:02, David Wang, Conditioning Station, Development, TM1, , TM1 is pumping down at CS 

TM1 and CS  vacuum system are connected. All turbo-pumps are started. The new TP1S works fine also. The pumping down looks good so far. During the TM1 and CS roughing down time, Joe .M noticed a Rn-220 level surge up in TH . Then,the Rn220  level slowly dropped back. Anders suspected this Rn-220 surging is related to the TM1 roughing down at CS. We decided we will stop the pumps , vent the CS , and roughing  again tomorrow. During the same time Joe will monitor  Rn-220 level in TH to see if the surging is repeatable. We want to learn more on this TH Rn-220 issue.

Entry  Friday, July 10, 2015, 14:41, Anders Mjos, Conditioning Station, Maintenance, TM1, , Replaced roughing pump 

 The roughing pump was replaced with a more leak tight pump due to the discovery of Rn-220 migration while roughing on TM1 in TCS

Entry  Monday, July 13, 2015, 11:31, Travis Cave, Conditioning Station, Standard Operation, TM1, no target, Module moved 

TM#1 has been moved back to the south west silo from the conditioning station.

Entry  Monday, July 27, 2015, 17:03, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, UCx13 and TM4 under vacuum at CS. 

I connected the CS  vacuum system  to TM4. The CS and TM4 turbo pumps are started. Everything is good so far. The HS line will be pressured with helium tomorrow for leak checking. The CS and TM4 will be vented with Argon on Wednesday morning as planned before moved to ITE.

Entry  Tuesday, July 28, 2015, 10:12, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Helium pressure test on TM4 HS line at CS 

I did the helium pressure test on TM4 HS line at CS. Applied 70 psi helium  2 minutes. base leak rate0.0x E-9 atm.cc/sec.  No response during the test. No leak.

Entry  Tuesday, July 28, 2015, 14:31, Travis Cave, Conditioning Station, Standard Operation, TM4, UC#13, Electrical Check TM4UC13IGLISelecchkCS.PDF

TM#4 with UC#13 electrical check at the conditioning station under vacuum. See attached PDF.

Entry  Wednesday, July 29, 2015, 06:24, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Stopped the CS and TM4 pumps and vent with argon. 

Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target.

Entry  Thursday, August 13, 2015, 14:36, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Module moved 

TM#2 with the dummy target has been moved to the conditioning station.

Entry  Thursday, August 13, 2015, 17:17, David Wang, Conditioning Station, Repair, TM2, Dummy target, TM2 at CS 

TM2 has been moved to CS. All turbo-pumps have been started. The pumping down is good so far.  I connected the leak detector to service cap, and finished the leak check today.  The LD base LR:0.0Xe-9atm.cc/sec. 80psi helium were applied to coil1, coil 2. HS and window circuits, each for 2minutes. No any response has been found on LD. So all water lines are leak tight now. I also sprayed   helium to top service cap checking all air to   vacuum seals. They are all good either. But, The new installed PGN1 does not work. Other thing need to mention is The TP2 is running at 2.45A which is 1A higher comparing to TP1. It need to be monitored to see if we have to replace it or not. The high current cables and water lines will be connected tomorrow morning.

Entry  Friday, August 14, 2015, 10:00, David Wang, Conditioning Station, Repair, TM2, , Started CS water package for TM2  

I finished the rest TM2 connections to CS, and started CS cooling package. Everything works fine so far.

Entry  Monday, August 17, 2015, 10:44, Anders Mjos, Conditioning Station, Development, TM2, LP-FEBIAD Test Target (empty), Conditioning TM2 Source Tray with FEBIAD test target FirstBeamTM2SourceTray2015-08-17.pngTM2_Source_Tray_with_FEBIAD_test_target.docx

TGHT, TBHT, ANODE and COIL power tested (some amps/volts)

Monday, August 17, 2015, 10:43: BIAS/EL/EE to 15/7.5/1.5 kV

Monday, August 17, 2015, 10:45 : COIL 20A, ANODE 200V

Keiko fixed the auto-ramping program and access rights to it.

Monday, August 17, 2015, 13:06: Auto-ramping at 2/1 A/min. Good/bad vacuum at 6E-6 and 8E-6 T

Monday, August 17, 2015, 13:24 : ANODE current limit set incorrectly. Corrected and 200V (9 mA)

Monday, August 17, 2015, 15:28: COIL to 50 A

Monday, August 17, 2015, 15:43: Reduced ANODE to 100 V

Monday, August 17, 2015, 16:56 : Increased EL to 8.3 kV to increase FC current.

Monday, August 17, 2015, 17:04 : FC0 current at 1.5E-8 A

Beam ionized and accelerated on the new TM2 source tray

Monday, August 17, 2015, 17:12 : TGHT / TBHT at 500 / 250 A. Will leave over night to outgas. ISAC ops are monitoring the source.


Tuesday, August 18, 2015, 08:07: Everything stable overnight. Continue ramping heaters.

Tuesday, August 18, 2015, 08:48: TBHT voltage limited by EPICS (hardcoded) at 273 A.

TGHT/TBHT at 600 / 273 A 

Tuesday, August 18, 2015, 09:52: Adjusted COIL current down to 0 and back up. Response seen on FC0.

Tuesday, August 18, 2015, 22:29 : Starting cool down.


 Wednesday, August 19, 2015, 08:26: Source and HV off. EE configured to conditioning mode. RGA off.

Wednesday, August 19, 2015, 08:42: BIAS/EL at 15 / 7.5 kV. PNG1 at 3.5E-6 T, IG1 at 3.9E-7 T

Wednesday, August 19, 2015, 08:53: BIAS/EL 20 / 10 kV. 2 sparks.

Wednesday, August 19, 2015, 09:54: BIAS/EL 30 / 15 kV. Some sparking around 28 kV required BIAS voltage to be reduced momentarily. 

Wednesday, August 19, 2015, 10:04: Sparking at 30 kV. Reduced BIAS to 13 kV to get spar rate to less than 10/min

Wednesday, August 19, 2015, 10:19 : BIAS current limiting. Switch off BIAS and EL

Wednesday, August 19, 2015, 12:04: Water off for purging and leak test.

Wednesday, August 19, 2015, 12:52: Vacuum response observed while David was working on purging the water lines. This turned out to be when the valve to the leak detector was opened.

Entry  Wednesday, August 19, 2015, 14:52, David Wang, Conditioning Station, Repair, TM2, , TM2 at CS 

During the TM2 HV test at CS, It failed. In order to confirm there is no any water leak inside the module after the heaters and beam extraction test, I disconnected all the water lines on the TM2, and purged the water lines with pressure air. Leak detector was reconnected back to the TM2 service cap, and all water lines are pressurized with 80psi helium again each for 2 minutes.No any leak had been found during the test. All the water lines are still perfectly sealed. Also, I checked all the vacuum to air seals on the top of the module.They are good either.  Anders used the RGA  tracking the helium during the test. No leak.

Entry  Thursday, August 20, 2015, 09:38, David Wang, Conditioning Station, Repair, TM2, , TM2 was disconnected at CS 

TM2 was disconnected at CS. Travis and I did  electrical check before the venting. After,The module was vented and moved to SHC. The moving is smooth.

Entry  Thursday, August 20, 2015, 11:00, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Electrical Check TM2_elecchkdummytgtatCS.PDF

TM#2 electrical check at the conditioning station. All pumps were off but the module was not vented.

Entry  Thursday, August 20, 2015, 13:48, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - Sep 08 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf

 Weekly update target hall schedule.See attachment 1,2

Spring and summer run is close to the end. This will be the last update on this old schedule. See attachment3,4.    A new schedule for TH activities after mini shut down will be posted next time.

Entry  Wednesday, August 26, 2015, 09:54, Anders Mjos, Conditioning Station, Maintenance, , , Topped up water in TCS:TK2 

 Filled to 24.9 in

Entry  Wednesday, August 26, 2015, 11:12, Travis Cave, Conditioning Station, Standard Operation, TM2, ZrC #7, Module moved 

TM#2 with ZrC#7 has been moved to the conditioning station from the south hot cell.

Entry  Wednesday, August 26, 2015, 14:28, David Wang, Conditioning Station, Standard Operation, TM2, ZrC, Leak check on TM2 HS and windowwater line with new ZrC target at SHC 

Chad and I leak checked TM2 HS and window circuit VCR joints with ZrC target and containment box installed at SHC. No leak has been found. They will   be helium pressurized  at CS later.

Entry  Wednesday, August 26, 2015, 14:30, David Wang, Conditioning Station, Standard Operation, TM2, ZrC, TM2 and Cs vacuum sysyem has been connected at CS. 

Turbo-pumps are started . The pumping down is good so far.

Entry  Wednesday, August 26, 2015, 14:52, David Wang, Conditioning Station, Standard Operation, TM2, ZrC, Helium pressure test on TM2 HS and window lines at CS 

LD base LR 0.0xE-9 atm.cc/sec , 80 psi helium 2 minutes on HS and window circuits. No leak. Also, the reinstalled(after rewiring job) TP2 and PNG1(steers) side panel have been leak checked. No leak.