Entry  Monday, December 15, 2014, 08:50, Anders Mjos, Conditioning Station, Maintenance, TM2, , TK2 level below 15 in (secondary loop) 
    Reply  Monday, December 15, 2014, 09:41, Anders Mjos, Conditioning Station, Maintenance, TM2, , Water leak found at the isolation transforer 
       Reply  Monday, December 15, 2014, 12:53, Anders Mjos, Conditioning Station, Maintenance, TM2, , TCSTK2 topped up 
       Reply  Monday, December 15, 2014, 13:25, Anders Mjos, Conditioning Station, Maintenance, TM2, , BIASSW1 temperature and flow removed from interlock chain 
Message ID: 821     Entry time: Monday, December 15, 2014, 12:53     In reply to: 820
Author: Anders Mjos 
Category: Conditioning Station 
Type: Maintenance 
Module: TM2 
Target/Number:  
Subject: TCSTK2 topped up 

Anders Mjos wrote:

Anders Mjos wrote:

 The level dropped below 15 in over the weekend. MP2 stopped, but MP3 condtinued pumping.

 e-fault submitted and Niel Wong has been contacted.

Niel Wong came and had a look at the system. We decided to close the circuit as the water is no longer used with the new power supplies. The circuit will be monitored, but not repaired unless it is needed again.

 Due to the water leak, the expansion tank needed topping up. It was filled from 14 in to 20 in. See work permit I2014-12-15-2.