Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC  Not logged in ELOG logo
Entry  Monday, December 15, 2014, 08:50, Anders Mjos, Conditioning Station, Maintenance, TM2, , TK2 level below 15 in (secondary loop) 
    Reply  Monday, December 15, 2014, 09:41, Anders Mjos, Conditioning Station, Maintenance, TM2, , Water leak found at the isolation transforer 
       Reply  Monday, December 15, 2014, 12:53, Anders Mjos, Conditioning Station, Maintenance, TM2, , TCSTK2 topped up 
       Reply  Monday, December 15, 2014, 13:25, Anders Mjos, Conditioning Station, Maintenance, TM2, , BIASSW1 temperature and flow removed from interlock chain 
Message ID: 820     Entry time: Monday, December 15, 2014, 09:41     In reply to: 819     Reply to this: 821   822
Author: Anders Mjos 
Category: Conditioning Station 
Type: Maintenance 
Module: TM2 
Target/Number:  
Subject: Water leak found at the isolation transforer 

Anders Mjos wrote:

 The level dropped below 15 in over the weekend. MP2 stopped, but MP3 condtinued pumping.

 e-fault submitted and Niel Wong has been contacted.

Niel Wong came and had a look at the system. We decided to close the circuit as the water is no longer used with the new power supplies. The circuit will be monitored, but not repaired unless it is needed again.

ELOG V2.9.2-2455