1527
|
Monday, May 08, 2017, 09:49 |
David Wang | Conditioning Station | Standard Operation | | | TH schedule 132 update weekly | Update TH schedule weekly to show the job
process. |
 |
1528
|
Monday, May 08, 2017, 14:46 |
Travis Cave | Spent Target Vault | Maintenance | | | Mini Vault Door | Mini Vault Door as some difficulty
over coming a small hump on its track. To
open the door one needs to give the door |
|
1531
|
Wednesday, May 10, 2017, 13:42 |
Anders Mjos | Conditioning Station | Repair | | | Leaky gauge at TCS:TS2 (e-fault: 9609) | Neil Wong will fix this leak tomorrow
Friday. See attached schematics for
location. |
|
1532
|
Wednesday, May 10, 2017, 14:00 |
Anders Mjos | South Hot-Cell | Development | | ITE-Ta-LP-FEBIAD | Test target examination | Chad and Anders inspected the test target
in the hot cell today. The lid had been previously
removed. |
|
1533
|
Thursday, May 11, 2017, 16:10 |
Isaac Earle | North Hot-Cell | Development | | | NHC roof block to TH north wall gap sealed | The gap between the north face of
the NHC roof block and the target hall north
wall in the area where the NHC inlet ducting |
|
1534
|
Friday, May 12, 2017, 07:42 |
David Wang | Crane | Repair | | | TH crane burning smell, smoke, and big noise on east side main hoist brake assembly. | This morning, when I prepare for today's
crane check, The crane made a very strong
noise without any load during the full speed |
|
1542
|
Thursday, May 18, 2017, 10:41 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#19 | Spent Target move | The spent UC#19 target has been moved from
the south hot cell into the spent target
storage. It was placed in pail #145 and put |
|
1548
|
Tuesday, May 23, 2017, 14:10 |
David Wang | ITE | Standard Operation | | | ITE water interlock check is done. | We do this check once a year now. Rene
found a target oven reset issue during the
check . He will consult with Friedhelm. The |
|
1555
|
Friday, June 09, 2017, 11:21 |
chad fisher | North Hot-Cell | Maintenance | | | Model 'N' Slave Removal Through Roof | Isaac and Chad disengaged the slave end
of the manipulator and performed a slave
removal through the slave removal roof hatch. |
|
1556
|
Monday, June 12, 2017, 13:51 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent Target move | The spent Ta#51 target has been moved from
the south hot cell to the spent target vault.
It was placed in pail#149 and put in spot |
|
1558
|
Tuesday, June 13, 2017, 11:10 |
Grant Minor | Crane | Maintenance | | | ISAC THall Crane 100% / 125% Load Test Documentation - 2011 | The ISAC Target Hall Crane was load tested
and re-certified in January 2011 prior to
doing a near-capacity lift for the North |
    |
1560
|
Thursday, June 15, 2017, 11:29 |
Isaac Earle | North Hot-Cell | Development | | | NHC inlet ducting installed | The North Hot Cell inlet ducting assembly
was installed today in the target hall at
the north end of the NHC roof block. A |
   |
1562
|
Thursday, June 22, 2017, 11:10 |
chad fisher | South Hot-Cell | Maintenance | | | In cell airline | The in cell airline has preemptively been
replaced. The hose was, as far as I know
the original. |
|
1563
|
Friday, June 23, 2017, 12:08 |
David Wang | Crane | Repair | | | TH crane inspection and probem fixing by Gordon crane | Gordon crane technician Peter came in today
and checked TH crane. Maico and I were there
with him. What he found is that brake gap |
|
1564
|
Friday, June 23, 2017, 17:28 |
Isaac Earle | North Hot-Cell | Development | | | NHC module flange and cameras installed | The North Hot Cell module support
flange (IRH1152D) was installed on June 21,
2017 using 1/8" rubber sheet as a sealing |
    |
1574
|
Thursday, June 29, 2017, 11:55 |
David Wang | Conditioning Station | Repair | | | TCS HV cable and feed through installation | John Chow and I installed new TCS HV cable
and feed through with their mounting panel
back to TCS Faraday cage this Tuesday. ECO-4269 |
|
1575
|
Thursday, June 29, 2017, 14:42 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#20 | Spent Target Move | The spent UC#20 has been moved from
the south hot cell to the spent target vault.
It was placed in pail #150 and spot 1B in |
|
1577
|
Wednesday, July 05, 2017, 15:36 |
Isaac Earle | North Hot-Cell | Development | | | NHC and SHC nuclear ventilation flow sensors installed | Installation of new flow sensors
and transmitters for the NHC and SHC duct
lines was completed in the target hall today. |
 |
1578
|
Thursday, July 06, 2017, 14:23 |
Isaac Earle | North Hot-Cell | Repair | | | Slave side Z motion tape snapped on NHC right side manipulator | The NHC right side manipulator was evaluated
today to check if operation was normal through
all ranges of motion. The manipulator |
|
1579
|
Monday, July 10, 2017, 09:09 |
Dan McDonald | North Hot-Cell | Repair | | | manipulator cart repair | A hydraulic leak was found on the
manipulator install and repair cart,
upon further investigation the cause was |
|