Tuesday, April 25, 2017, 19:35, Grant Minor, Crane, Repair, , , ISAC Target Hall Crane - West Hoist Brake Rattle
|
Normal
0
false
false
false
EN-US
X-NONE
X-NONE
|
Thursday, April 27, 2017, 16:58, Isaac Earle, North Hot-Cell, Development, , , Right side NHC manipulator installed    
|
Installation of the NHC right side manipulator was completed yesterday. The three piece manipulator was assembled in the module assembly
area on the manipulator cart which was then craned through the hatch to the NHC service area (the slave end had to be removed for it to fit through the
hatch). The installation went relatively smoothly except for the second (cold side) piece of lead shielding around the thru tube which would not |
Friday, April 28, 2017, 12:04, Anders Mjos, Conditioning Station, Maintenance, , , MP1 problem
|
TCS:MP1 was tripping of intermittently yesterday. It was found by Dave Morris that the current sensor was not set correctly causing the pump on status
to flicker at times. Dave adjusted the settings yesterday. The system should be operational and is currently running normally. |
Monday, May 01, 2017, 12:32, David Wang, Crane, Repair, , , TH crane burning smell
|
TH crane burning smell showed again this morning. It appeared after 1-1.5 hours of continuously using during the F308 flasks moving in TH.After a certain
time of using I think the brake gap is reduced because of thermal expansion. The main hoist and brakes work fine still. We knew these brakes gap
are tight especially on west side. So, It is not surprised that this burning smell appeared again. It does not affect the safe of crane use in my view. |
Tuesday, May 02, 2017, 09:48, Isaac Earle, North Hot-Cell, Development, , , NHC polycarbonate window cover panel installed    
|
The window cover panel has been installed on the hot side of the NHC shielding window according to drawing IRH1638. It was necessary to drill
and tap a hole in the steel frame first to achieve proper grounding for stud welding. The strength of all studs were checked by installing a nut
on the stud tightened against a block up against the steel frame, which was then torqued to a minimum of 10 ft*lbs. For the final installation the |
Tuesday, May 02, 2017, 13:49, Travis Cave, Spent Target Vault, Standard Operation, , , Spent Targets moved 
|
Five spent targets have been moved from the target storage vault to the mini vault in preparation for Thursdays loading of the F-308s. See attached for
the list of targets in the mini vault, and the new status of the storage vault. |
Monday, May 08, 2017, 09:49, David Wang, Conditioning Station, Standard Operation, , , TH schedule 132 update weekly 
|
Update TH schedule weekly to show the job process. |
Monday, May 08, 2017, 14:46, Travis Cave, Spent Target Vault, Maintenance, , , Mini Vault Door
|
Mini Vault Door as some difficulty over coming a small hump on its track. To open the door one needs to give the door a slight tug while
it is opening to over come this hump. |
Wednesday, May 10, 2017, 13:42, Anders Mjos, Conditioning Station, Repair, , , Leaky gauge at TCS:TS2 (e-fault: 9609)
|
Neil Wong will fix this leak tomorrow Friday. See attached schematics for location. |
Wednesday, May 10, 2017, 14:00, Anders Mjos, South Hot-Cell, Development, , ITE-Ta-LP-FEBIAD, Test target examination
|
Chad and Anders inspected the test target in the hot cell today. The lid had been previously removed.
The EE looked to have performed well.
A piece of Ta foil was found inside the heat shield. It is not clear if this
has been there during operation or if it entered the heat shield while in the hot cell. The foil has markings which indicate that it has seen heat.
|
Thursday, May 11, 2017, 16:10, Isaac Earle, North Hot-Cell, Development, , , NHC roof block to TH north wall gap sealed
|
The gap between the north face of the NHC roof block and the target hall north wall in the area where the NHC inlet ducting will be installed has
been sealed with Sikaflex 1a flexible polyurethane sealant applied over foam backer-rod. |
Friday, May 12, 2017, 07:42, David Wang, Crane, Repair, , , TH crane burning smell, smoke, and big noise on east side main hoist brake assembly.
|
This morning, when I prepare for today's crane check, The crane made a very strong noise without any load during the full speed up motion. I stopped
the crane right away, and noticed that east side of main hoist motor area was smoking . The crane was moved to east end. And, I climbed up to the top,
and found the smoke is coming form brake side, and should be produced by braking. The smell is same as before.Unless other thing is wrong, I think |
Thursday, May 18, 2017, 10:41, Travis Cave, Spent Target Vault, Standard Operation, , UC#19, Spent Target move
|
The spent UC#19 target has been moved from the south hot cell into the spent target storage. It was placed in pail #145 and put in tray one spot C. See
attached PDF for all vault details. |
Tuesday, May 23, 2017, 14:10, David Wang, ITE, Standard Operation, , , ITE water interlock check is done.
|
We do this check once a year now. Rene found a target oven reset issue during the check . He will consult with Friedhelm. The interlock check is good. |
Friday, June 09, 2017, 11:21, chad fisher, North Hot-Cell, Maintenance, , , Model 'N' Slave Removal Through Roof
|
Isaac and Chad disengaged the slave end of the manipulator and performed a slave removal through the slave removal roof hatch. This is part of investigation
into a 'Z' motion tape that is "rubbing" on its drum on the master side of the manipulator during manual 'Z' retraction of 'Z' extension.
This also was the first test of the concept of removing the manipulator slave through the manipulator hatch that was built into the roof. |
Monday, June 12, 2017, 13:51, Travis Cave, Spent Target Vault, Standard Operation, , , Spent Target move
|
The spent Ta#51 target has been moved from the south hot cell to the spent target vault. It was placed in pail#149 and put in spot 8B of the vault. |
Tuesday, June 13, 2017, 11:10, Grant Minor, Crane, Maintenance, , , ISAC THall Crane 100% / 125% Load Test Documentation - 2011    
|
The ISAC Target Hall Crane was load tested and re-certified in January 2011 prior to doing a near-capacity lift for the North Hot Cell roof structure
(IRH1112E).
Photos and documentation from Norelco is attached. |
Thursday, June 15, 2017, 11:29, Isaac Earle, North Hot-Cell, Development, , , NHC inlet ducting installed   
|
The North Hot Cell inlet ducting assembly was installed today in the target hall at the north end of the NHC roof block. A small section of the
perforated aluminum sheet on the TCS cage had to be trimmed for the assembly to fit (see IMG_0214). At each end of the assembly it was fastened to
the roof structure using a 1/4"-20 tapped hole in the steel roof, and a 1/4"-20 anchor in the north wall of the target hall. The base flange |
Thursday, June 22, 2017, 11:10, chad fisher, South Hot-Cell, Maintenance, , , In cell airline
|
The in cell airline has preemptively been replaced. The hose was, as far as I know the original. |
Friday, June 23, 2017, 12:08, David Wang, Crane, Repair, , , TH crane inspection and probem fixing by Gordon crane
|
Gordon crane technician Peter came in today and checked TH crane. Maico and I were there with him. What he found is that brake gap on both side of
main hoist decreased after months of using. The solution is to lock the automatic self adjustment system so the gap will be fixed there. Each year
during annual inspection, they will adjust the gap manually. After he locked both side of device, I tested the crane up and down couple of times. The |
|