Entry  Thursday, June 15, 2017, 11:29, Isaac Earle, North Hot-Cell, Development, , , NHC inlet ducting installed IMG_0217.jpgIMG_0218.jpgIMG_0219.jpgIMG_0214.jpg
The North Hot Cell inlet ducting assembly was installed today in the target hall at the north end of the NHC roof block.  A small section of the
perforated aluminum sheet on the TCS cage had to be trimmed for the assembly to fit (see IMG_0214).  At each end of the assembly it was fastened to
the roof structure using a 1/4"-20 tapped hole in the steel roof, and a 1/4"-20 anchor in the north wall of the target hall.  The base flange
Entry  Thursday, June 22, 2017, 11:10, chad fisher, South Hot-Cell, Maintenance, , , In cell airline 
The in cell airline has preemptively been replaced. The hose was, as far as I know the original.
Entry  Friday, June 23, 2017, 12:08, David Wang, Crane, Repair, , , TH crane inspection and probem fixing by Gordon crane  
Gordon crane technician Peter came in today and checked TH crane. Maico  and I were there with him. What he found is that brake gap on both side  of
main hoist decreased after months of using.  The solution is to lock  the automatic self adjustment system so the gap will be fixed there.  Each year
during annual inspection, they will adjust the gap manually.  After he locked both side of device, I tested the crane up and down  couple of times. The
Entry  Friday, June 23, 2017, 17:28, Isaac Earle, North Hot-Cell, Development, , , NHC module flange and cameras installed IMG_0231.jpgIMG_0234.jpgIMG_0240.jpgIMG_0245.jpgIMG_0240.jpg
 The North Hot Cell module support flange (IRH1152D) was installed on June 21, 2017 using 1/8" rubber sheet as a sealing gasket.  The
rubber was glued at the seams with Loctite 495 instant adhesive.  Cameras with all required wiring and connectors were installed on the mounting bars
(IGN0325D) and then aligned to provide the same view as at other module installation locations in the target hall.  A cable with 5 video signals,
Entry  Thursday, June 29, 2017, 11:55, David Wang, Conditioning Station, Repair, , , TCS HV cable and feed through installation 
John Chow and I installed new TCS HV cable and feed through with their mounting panel back to TCS Faraday cage this Tuesday. ECO-4269 has been issued
for the new cable feed through and mounting panel.
Entry  Thursday, June 29, 2017, 14:42, Travis Cave, Spent Target Vault, Standard Operation, , UC#20, Spent Target Move Vault_Storage_June_29_2017.pdf
 The spent UC#20 has been moved from the south hot cell to the spent target vault. It was placed in pail #150 and spot 1B in the vault. See attached
for details of the vault.
Entry  Wednesday, July 05, 2017, 15:36, Isaac Earle, North Hot-Cell, Development, , , NHC and SHC nuclear ventilation flow sensors installed IMG_0264.JPGIMG_0265.JPG
 Installation of new flow sensors and transmitters for the NHC and SHC duct lines was completed in the target hall today.  The sensors are
Dwyer DS-300-8 in-line sensors for 8" pipe; The transmitters are Dwyer MS0121 magnesense differential transmitters with 4-20mA output.  The transmitters
will be wired to the new PLC control system when the upgrade is done.
Entry  Thursday, July 06, 2017, 14:23, Isaac Earle, North Hot-Cell, Repair, , , Slave side Z motion tape snapped on NHC right side manipulator 
The NHC right side manipulator was evaluated today to check if operation was normal through all ranges of motion.  The manipulator was first moved
through usual motions without the electric motion drives: the feel was fairly normal, a sound could be heard from the master side Z motion tapes rubbing
on the sides of the pulleys, this problem had been identified a few weeks ago however it was significantly reduced since the master side upper and lower
Entry  Monday, July 10, 2017, 09:09, Dan McDonald, North Hot-Cell, Repair, , , manipulator cart repair IMG_2955.JPG
A  hydraulic leak was found on the manipulator  install and repair cart, upon further investigation the cause was a faulty cylinder. Once the
cylinder was removed and disassembled the inner bore was found to be scored beyond repair. Another point of interest was that the rod was painted to the
point that when retracted it compromised the rod seal causing the cylinder to leak. attached are photos outlining the issues. new cylinders are being sourced
Entry  Wednesday, July 12, 2017, 11:05, Anders Mjos, Conditioning Station, Maintenance, , , Testing of new high voltage cable 2017-07-12_HV_Cable_Test.xlsx
The target hall has been locked-out as per Document-70039.
Forced IG1, IG1S and IG2 to switch on BIAS power supply
Wednesday, July 12, 2017, 11:53: 70 kV at 0.16 mA
Entry  Tuesday, July 18, 2017, 15:04, Travis Cave, Crane, Maintenance, , , Failure of the ISAC TH Crane Rotate. 
 Earlier in the day it was noted that the rotate function of the crane had creased operation. After David has finished the block moves. Don and
I checked the Crane's control unit in the ISAC crane control room and found the breaker tripped for the rotation. The breaker was reset and the crane's
rotation is now operational. If this occurs in the future only Travis Cave, Don Jackson or a TRIUMF Electrician are allowed in that control box as it is
Entry  Wednesday, August 02, 2017, 15:41, Keith C Ng, Assembly/Bench Test, Development, , , spare source tray build 20170802_sourcetray_RHB_8264.JPG20170802_sourcetray_RHB_8266.JPG
After re zeroing alignment telescope to master jig and adjusted parts into place:
 
Orientation: X = Left -, Right+; Y = Up +, Down -
Entry  Thursday, August 03, 2017, 15:02, Travis Cave, Spent Target Vault, Standard Operation, , SiC#36, Spent Target Move Vault_Storage_August_3_2017.pdf
 The spent SiC#36 has been moved from the south hot cell to the spent target vault.
Entry  Wednesday, August 09, 2017, 16:39, Isaac Earle, North Hot-Cell, Development, , , NHC drain line into sump identified 
 The NHC drain line was tested by pouring approximately 10 gallons of water through the drain grate at the base of the NHC partition wall.  Water
was seen a few minutes later pouring into the sump labeled "ACTIVE SUMP" from the light coloured pipe on the west side of the inside of the sump.
 Rob Walker had previously said that the hot cells drain into the sump next to this one which is labeled "SANITARY SUMP", which appears
Entry  Tuesday, August 15, 2017, 12:10, Isaac Earle, North Hot-Cell, Development, , , ISAC Active Sump low water level measured 
The ISAC active sump in the Active Service Room (#002 on B2 level) was pumped out yesterday using the standard procedure (Section 5.5.2 of the ISAC Operators'
Manual, V1.0).  The procedure makes use of the auto stop feature of the pump-out system which stops when a low level float switch is triggered.  The
water level was measured after pumping stopped, and was found to be approximately 21" above the base of the sump.  A new section of pipe will
Entry  Thursday, August 17, 2017, 14:38, Isaac Earle, North Hot-Cell, Development, , , 4/6 NHC roof blocks installed 7x
 Roof blocks IRH1641, IRH1642, IRH1643, and IRH1644 have been fully assembled, labeled, and installed as per drawing IRH1652.  Fabrication
of TCS shield block (IRH1646) and NHC module port block (IRH1645) is still in progress.
 
Entry  Friday, August 25, 2017, 16:33, Anders Mjos, Conditioning Station, Repair, , , Testing HV after cooling line repair 2017-08-25_HV_Water_Line_Test.xlsx
 The BIAS voltage was brought up to 70 kV today and held there for 1h. No sparking observed.
Entry  Wednesday, August 30, 2017, 11:37, Travis Cave, Spent Target Vault, Standard Operation, , Ta#52, Spent Target move Vault_Storage_August_30_2017.pdf
The spent Ta#52 target has been moved from the south hot cell to the spent target vault. See attached PDF for details.
Entry  Tuesday, September 19, 2017, 10:40, chad fisher, South Hot-Cell, Maintenance, , , South East Manipulator Maintenence 
Entered hot cell to preform replacement of slave tong cable. Existing cable shows no signs of wear so it has been re-installed. A spare tong cable has
been loaded into a spare tong while in the hot cell in preparation for next time this cable needs to be replaced.
Entry  Thursday, September 28, 2017, 11:59, Travis Cave, Spent Target Vault, Standard Operation, , Ta#53, Spent Target move Vault_Storage_September_28_2017.pdf
The spent Ta#53 has been moved to the spent target vault. See attached file for details.