Thursday, March 02, 2017, 15:02, Isaac Earle, North Hot-Cell, Development, , , NHC roughing filter installed
|
The roughing filter assembly (RFM0001D) has been installed at the ventilation exhaust hole on the NHC partition wall. The filter used is
Model # 332-528-002 supplied by BGE Service & Supply Ltd (see PO # TR123998). Installation and removal of the filter using the manipulators will
be tested after they have been installed. |
Monday, March 06, 2017, 08:01, David Wang, Cooling, Repair, , , HALCW resin tank replacement. 11x
|
HALCW resin tank has been replaced. The old tank is stored in middle-west silo now. The field on old resin tank bottom is about 3.5 msv/ hr(on contact).
By shielding it into silo and putting two lead blankets on the top cover of the silo,The general field 1 feet above this silo is 25usv/hr. And, The field
around the silo area are less affected. This old tank will stay there as long as possible. For the new resin tank during preparation, It was found |
Tuesday, March 07, 2017, 09:25, David Wang, ITW, Repair, , , ITW HALCW 2" return line ball valve seals replacement.
|
Leaking seals on ITW HALCW 2" return line ball valve have been replaced. 8 liter waters are drained out for this job. Water are drained into a thick
plastic bag. The bag is tie strapped , labeled, and put into a yellow garbage bin in MAA. Water sample is given to RPG. After analyzing, RPG will
give instruction on how to deal with it. Since we just refilled NALCW to system before this job, the active level on sample is very low. We may dump them |
Tuesday, March 07, 2017, 14:41, David Wang, ITE, Maintenance, , , ITE dump plug water circuit is closed for ITE IG1S small surge.
|
It is closed @ 2:35PM by closing supply side valve first , the return side valve of ITE dump plug .
Opened ITE dump plug circuit valves @4:28PM. ITE IG1S still at 1XE-6. No change before and after of circuit closing and reopeneing. |
Friday, March 10, 2017, 09:19, chad fisher, South Hot-Cell, Standard Operation, , , South Hot Cell Field Measurements
|
The fields in the hot cell have been measured by means of a pole monitor through the tool port. Field was measured to be 25 uSv/h. |
Tuesday, March 14, 2017, 07:34, chad fisher, South Hot-Cell, Maintenance, , , Hot Cell Fields
|
I have re-measured the fields in the hot cell. Fields at shield door Al cover are 101 uSv\h, in cell at the east manipulator are 245 uSv\h, and the largest
field is 1.84 mSv\h...this appears to be the high current fasteners removed from the last target. |
Tuesday, March 14, 2017, 11:46, chad fisher, South Hot-Cell, Maintenance, , , 'Z' motion cable dry run
|
Did a dry run with the latest procedure with Dan Mcdonald. Elapsed time was approximately 30 min. |
Wednesday, March 15, 2017, 07:45, chad fisher, South Hot-Cell, Maintenance, , , South Hot Cell Fields
|
I have moved the suspected "hot" items in the hot cell and placed them under some lead bricks. I have re-measured the fields and it has been
reducded to 90 uSv\h at the manipulator repair area and 110 uSv/h at the previous 1.82 mSv\h area. |
Thursday, March 16, 2017, 12:24, chad fisher, South Hot-Cell, Maintenance, , , West 'Z' motion cable replacement
|
The west 'Z' motion cable on the east manipulator has successfully been replaced. The job took slightly less than an hour (including inspection of the
scissor table hoses) and I received 0.075mSv. Scissor table hoses appear to be fine and also didn't "shed" or flake at all when checked by hand. |
Tuesday, March 21, 2017, 10:05, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target assay.
|
All target in the ISAC spent target vault have been either assayed or had their fields measured or both. |
Thursday, March 23, 2017, 11:22, Grant Minor, Crane, Maintenance, , , Target Hall crane 20 ton hoist noise / smell - inspection by Gordon Crane & Hoist
|
Strange noise and a burning brake type smell was observed yesterday by David and Anders when running the main 20 ton hoist locally. A service call
was arranged today with Gordon Crane. No major issues were found. A more detailed summary is in the attached e-mail correspondence. Gordon
Crane will issue a formal report, but they recommend replacing both sets of brake disks and brake calipers. - Grant |
Friday, March 24, 2017, 11:12, Keith C Ng, Spent Target Vault, Standard Operation, , , 2A window transfer
|
Transfered the 2A window from the ISAC Storage Vault to the Cyclotron Vault Tunnel Storage area. RPG storage form attached. |
Friday, March 24, 2017, 11:19, Keith C Ng, Spent Target Vault, Standard Operation, , 2A3 window, Window now in vault
|
Travis Cave wrote:
The 2A3 window now has a lid, and lift yolk on it and it has been installed in the spent target vault |
Friday, March 24, 2017, 13:21, Travis Cave, Spent Target Vault, Standard Operation, , 2A window, 2A window has been removed from the vault.
|
2A window has been removed from the vault and moved over the cyclotron vault tunnels. Attached is the updated storage vault list. |
Monday, March 27, 2017, 06:33, David Wang, ITE, Standard Operation, , , ITE clean up
|
ITE clean up is done. HV cage inside is wiped. |
Monday, March 27, 2017, 12:55, David Wang, Spent Target Vault, Repair, , , S/W silo rust clean up
|
Rust on S/W silo and cover plate stored at silo area are cleaned up. |
Tuesday, April 04, 2017, 14:39, David Wang, Crane, Standard Operation, , , Crane check main hoist on jogging with shielding plug lifted.
|
Today, I checked TH crane main hoist when shielding plug is installed into ITE pit. I did some jogging actions on main hoist during the operation.
Everything looks fine. No burning smell, no strange noise. An outside crane expert suggest that jogging is the worst working situation for crane. We have
to use jogging actions during our crane operation. But, we could try to use less jogging when operate the crane. |
Wednesday, April 05, 2017, 11:57, David Wang, ITE, Maintenance, , , ITE target module flange o-ring repalcement
|
ITE target module tank flange o-ring was replaced yesterday before TM4 moving. ITE: IG1S reading looks fine so far. |
Thursday, April 06, 2017, 15:11, Grant Minor, Crane, Maintenance, , , Target Hall Crane 20 ton hoist - Report by Gordon Crane 5-Apr-2017
|
v\:* {behavior:url(#default#VML);}
o\:* {behavior:url(#default#VML);}
w\:* {behavior:url(#default#VML);}
.shape {behavior:url(#default#VML);}
Normal
0
false
false
false
|
Thursday, April 06, 2017, 15:16, Anders Mjos, Conditioning Station, Maintenance, , , Installation of new break out box to accommodate both ITM:MP2 and TCS:MP1
|
Installation by Marshall. Dave M from controls adjusted circuitry to get TCS:MP1 to start.
Work is being done in preparation for the Module Move Ventilation SAS project |
|