2526
|
Monday, January 22, 2024, 09:56 |
David Wang | ITW | Standard Operation | | | Entrance module has been connected in ITW pit. |
Entrance module has been connected in ITW pit per document 190510 " entrance module disconnection and removal procedure".
|
2527
|
Monday, January 22, 2024, 10:16 |
David Wang | ITE | Standard Operation | TM4 | UCx# | Tm4 waterlines helium pressure test and TM service cap helium leak check. |
Tm4 waterlines helium pressure test and TM service cap helium leak check was done last Friday. All water lines were pressurized with 70psi helium for 3 minutes each. The 3 minutes stable leak rate on all lines are less than 4.0 X E-9atm.cc/sec. some of lines had surging leak rate to 2xE-8 atm.cc/sec at the first 10 seconds of pressurization which should be a gas hammer result at the beginning. Based on the numbers, I would say all water lines are leak free still. I did helium spray on TM4 service cap. There could be a small leak in high E-9 atm. cc/sec on ion gauge and steer service panel o-ring. I will replace this o-ring when module is moved out of ITE. Other seals are leak free or less than 2.5X E-9 atm.cc/sec leak rate which are good. I am pretty confirm there is a small leak on ITE entrance module top. The leak rate and location will be confirmed when the rest of leak checks in ITE pit are done. |
2531
|
Thursday, January 25, 2024, 07:27 |
David Wang | Crane | Standard Operation | | | Inspection of target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 |
Tom Gauss inspected two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 yesterday. He certified the use of these two frames for 2024. Inspection tags have been issued and attached to frames. He has inspection record on them. |
2532
|
Thursday, January 25, 2024, 07:31 |
David Wang | Crane | Standard Operation | | | Inspection oftareg hall crane below hook attachment pins and plates ITA6550-01 |
Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01 yesterday. He certified the use of these pins and plates for year 2024. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08. After inspection, The inspection tag was issued and attached to pin. Tom has an inspection record on this job. |
2533
|
Friday, January 26, 2024, 08:30 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | window line VCR leak check after containment box removal/installation. |
Chad and I did window line VCRs leak check after containment box removal/installation. The first pair of VCRs have leak. Chad changed VCRs. Both VCr fittings on window lines are completely leak free to 0.0 XE-9 atm.cc/sec now. |
2534
|
Friday, January 26, 2024, 11:53 |
David Wang | Safe Module Parking | Standard Operation | TM4 | | Tm4 has been moved to SMP. |
TM4 has been moved to SMP. The move is smooth. I started SMP vacuum pump. The TM4 and SMP vessel is under vacuum now. |
2535
|
Friday, January 26, 2024, 11:57 |
David Wang | Safe Module Parking | Standard Operation | TM4 | | TM4 coil1, 2, and HS electrical check at SMP after module moving. |
TM4 coil1, 2 and HS are all OL at 250V at SMP after module move. This week, Chad and Carl fixed short issue on coil1, 2 and HS by insert dropped ultem ring back to position at SHC. |
2537
|
Friday, February 02, 2024, 07:48 |
David Wang | ITE | Standard Operation | TM4 | | ITE primary and secondary vacuum vessel leak check. |
ITE primary and secondary vacuum vessel leak check has been done. SST bellow for 2A3M19 wire scanner on entrance module top has a big leak to E-5 atm.cc/sec on tiny helium spray. The bellow will be replaced in March by probe group. The LD base leak rate is affected by this big leak so i cant keep the LD scale at 0.0Xe-9 atm.cc/sec during the leak check. Other seal are leak free to 8XE-9 atm.cc/sec. I have no big concern on ITE vacuum seals status by the result. |
2538
|
Tuesday, February 06, 2024, 13:28 |
David Wang | ITW | Maintenance | | | ITW exit 1 module has been disconnected and reconnected for o ring replacement |
ITW exit 1 module was disconnected for Exit module flange o -ring replacement yesterday. After oring replacement, the module has been reconnected. |
2539
|
Tuesday, February 06, 2024, 13:36 |
David Wang | ITW | Maintenance | | | ITW exit 1 module tank flange o ring has been replaced. |
ITW exit 1 module tank flange o ring has been replaced. the old o r-ing was completely flat in slot without elastic property. tank flange, module flange, and o ring slot were clean by acetone and canister vacuumed. Raised up module 3 feet and pulled new o-ring over module top so new o ring could be installed without moving module out. after new o ring installation, craned down module to flange and raised up module 2 feet again to confirm the o ring is properly sit in slot. |
2544
|
Thursday, February 15, 2024, 13:52 |
David Wang | ITW | Standard Operation | | | ITW entrance module and exit 1 module leak check after module move and tank flange orings replacement. |
ITW entrance module and exit 1 module leak check on module service cap/top air to vacuum seals and module to tank flange o-rings have been done. all seals and o rings are leak free to 0.0 xE-9atm.cc/sec except one leak ( to low E-6 atm.cc/sec) on ITW RV4 KF50 o-ring was found. It caused by a cross o ring surface scratch on KF 50 flange. the scratch was sanded and polished out. on second time leak check, it is leak free. |
2547
|
Friday, February 16, 2024, 11:48 |
David Wang | Cooling | Maintenance | | | high active water transferr to holding tank |
100 liters of high active water from HALCW system( mostly from s-tank and pipe lines closing to pumps) are transferred to holding tank in 2A tunnel. Transfer is smooth. it is a preparation job for ITC:MP1/MP2 refurbishment. water sample is passed to RPG for assay. |
2548
|
Friday, February 23, 2024, 06:36 |
David Wang | ITE | Maintenance | | | ITE entrance module has been disconnected. |
ITE entrance module has been disconnected per document 190510. Its a preparation job for next month module moving out to SHC. |
2550
|
Thursday, March 14, 2024, 14:54 |
David Wang | ITE | Maintenance | | | ITE entrance module has been moved from ITE pit to TCS. |
ITE entrance module has been moved from ITE pit to TCS. The move is smooth.ITE entrance module top tank flange and o ring slot are cleaned, and old o ring are replaced. |
2553
|
Monday, March 25, 2024, 10:53 |
David Wang | ITE | Repair | | | ITE entrance module has been moved from TCS to ITE. |
ITE entrance module has been moved from TCS to ITE. The move is smooth. |
2554
|
Monday, March 25, 2024, 10:55 |
David Wang | ITE | Standard Operation | | | ITE entrance module has been reconnected in ITE pit. |
ITE entrance module has been reconnected in ITE pit per document 190510. |
2555
|
Wednesday, March 27, 2024, 09:49 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 has been moved to SHC from silo. |
Tm3 has been moved to SHC from silo. the move is smooth. |
2556
|
Wednesday, March 27, 2024, 09:52 |
David Wang | ITE | Standard Operation | | | ITE entrance module top and module flange o-ing to tank have been leak checked. |
ITE entrance module top and module flange o-ing to tank have been leak checked. no leak at 0.0xe-9 atm.cc/sec. things are double checked. |
2557
|
Thursday, March 28, 2024, 09:26 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 has been moved from SHC to silo. |
Tm3 has been moved from SHC to silo. The move is smooth. |
2559
|
Thursday, April 04, 2024, 13:10 |
David Wang | Cooling | Maintenance | | | high active water refurbishment, reinstallation, and test operation. |
both high active pumps ITC:MP1 and MP2 are refurbished by RH group Maico and Peter. Pumps have been installed back to system with new inlet/outlet flange gaskets. high active water surging tank is refilled with water and pumps were primed. I asked operator to switch on pumps separately. Both pumps work fine. They are quiet and pumps discharging pressure is a little bit better comparing to before refurbishment. Nitrogen gas is injecting into system. O2 level is decreasing and R is going up.
2024-04-09: Joel.S checked pumps phase current draw: MP1 16.8 to 17.1A on each phase. MP2 17.0 to 17.2 A on each phase. They are normal. Pump body temperature are below 45C which is fine. |