  RH-ISAC, Page 106 of 140  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Category Type Moduledown Target/Number Subject
  848   Wednesday, February 25, 2015, 10:44 David WangITWMaintenance  2015 shut dwon ITW water sensor coils and pedal wheels replacement

Dan and I replaced pedal wheels and coils on ITW water flow sensors. It is a shut down job we did every two years. See attachment for detail.

Attachment 1: 2015_shut_down_ITW_water_sensors__replacements.pdf
2015_shut_down_ITW_water_sensors__replacements.pdf
  849   Thursday, February 26, 2015, 09:22 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Mar 25th

TH shut down activities schedule from Feb 23th-March 25th. The schedule will be updated each week. See attachment 1.

Feb-27-2015: Updated the schedule, and uploaded as PDF file. See attachment 2.

Attachment 1: Target_Hall_shut_down_activities.mpp
Attachment 2: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf
  850   Friday, February 27, 2015, 09:34 chad fisherSouth Hot-CellMaintenance  Hot cell Entry February 25 2015

See attached report.

Summary:

Radio problems just before entry to cell. Inspection afterwards revealed batteries charge but battery in one radio shorts out after a couple loads/cycles.

Fields in hot cell range from 630 uSv/h @ 1 m to 1.5mSv/h @ 1m. Contributing to the fields is the febiad coil line removed from TM4 in the south west corner of the hot cell.

Contamination/particulate on table as mostly black colored and of a fairly substantial size, but seamingly easy to collect. Distinquishable pieces of target material present.

Hot cell window show no sign of leaking on the inside of cell.

Pre-filter changed.

Manipulators lubricated.

Hot cell entry procedures appear to still be fairly successful in minimizing contamination migration from the hot cell.

 

Attachment 1: ISAC_South_Hot_Cell_Entry.pdf
ISAC_South_Hot_Cell_Entry.pdf ISAC_South_Hot_Cell_Entry.pdf ISAC_South_Hot_Cell_Entry.pdf ISAC_South_Hot_Cell_Entry.pdf
  853   Thursday, March 05, 2015, 07:17 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th update

TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned. See attachments for updated schedule.

I updated the schedule today. See attachment 3, 4 for updating.  2015-Mar-10.

2013-Mar -13, I updated the schedule to show the jobs we finished this week. See attachment 5,6

Attachment 1: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf
Attachment 2: Target_Hall_shut_down_activities.mpp
Attachment 3: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 4: Target_Hall_shut_down_activities.mpp
Attachment 5: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 6: Target_Hall_shut_down_activities.mpp
  854   Thursday, March 05, 2015, 14:30 chad fisherSouth Hot-CellDevelopment  Dissection Box

Box for dissecting targets almost complete. Should be done tomorrow.

Attachment 1: 20150305_142144.jpg
20150305_142144.jpg
  855   Monday, March 09, 2015, 09:42 chad fisherSouth Hot-CellDevelopment  Hot Cell Table Swiping

3 swipes of the south hot cell table were taken from the target hall through the roof hatch (2 standard, 1 alpha).

Initial results of the table swipes are pending however swipes of the pool tool and end effector are clean, 0 counts, booties, gloves clean.

Fall arrest equipment has a puzzling 6000 counts, and suit 500 counts.

 

 

  861   Friday, March 13, 2015, 13:36 Travis CaveSpent Target VaultStandard Operation ThO#1Spent Target Move

The ThO#1 has been placed in the storage vault placed in pail #122 in spot 2B of the vault. It was 6.2mSv/hr upon removal from the south hot cell. see attached PDF for details.

Attachment 1: Storage_Vault_March_13_2015.pdf
Storage_Vault_March_13_2015.pdf Storage_Vault_March_13_2015.pdf Storage_Vault_March_13_2015.pdf Storage_Vault_March_13_2015.pdf
  864   Tuesday, March 17, 2015, 10:33 Travis CaveSpent Target VaultStandard Operation UC#11Spent Target Move

The spent UC#11 has benn moved from the south hot cell to the spent target vault. See attached PDF for details.

Attachment 1: Vault_Storage_March_17_2015.pdf
Vault_Storage_March_17_2015.pdf Vault_Storage_March_17_2015.pdf Vault_Storage_March_17_2015.pdf Vault_Storage_March_17_2015.pdf
  865   Friday, March 20, 2015, 13:37 chad fisherSouth Hot-CellDevelopment  TM2 Optics Tray

Final assembly and alignment of TM2 optics tray continued today. Front section is "aligned".

Attachment 1: 20150320_113132[2].jpg
20150320_113132[2].jpg
Attachment 2: 20150320_113018_1[1].jpg
20150320_113018_1[1].jpg
  866   Monday, March 23, 2015, 07:56 David WangITEStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th update

This schedule is following Dons schedule on module moves. See attachments for updating.

2015-03-27: Weekly update the schedule. The shut down job is close to the end. See attachment 3, 4.

Attachment 1: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 2: Target_Hall_shut_down_activities.mpp
Attachment 3: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 4: Target_Hall_shut_down_activities.mpp
  867   Monday, March 23, 2015, 14:03 chad fisherSouth Hot-CellStandard Operation Ta#45Ta#45 inserted into hot cell

Ta#45 has been inserted into the hot cell. Swipe taken of inner tool port area: 100000 counts/min.

  871   Wednesday, March 25, 2015, 10:37 chad fisherSouth Hot-CellDevelopment  TM2 optics tray build

TM2 optics tray build is continuing. Going well. Hope to have assembly and alignment finished by Friday.

 

 

Attachment 1: 20150325_101718.jpg
20150325_101718.jpg
Attachment 2: 20150325_101735.jpg
20150325_101735.jpg
Attachment 3: 20150325_102024.jpg
20150325_102024.jpg
  885   Monday, April 13, 2015, 08:59 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - June 26 2015

See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.

Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015.    See attachments 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
  886   Wednesday, April 15, 2015, 09:01 Anders MjosConditioning StationDevelopment  Archiver variables added by Controls

 

 

 

 

 

 

 

 

 

 

The following variable have been added to the archiver (as per work request)

TCS:TS5:RDTEMP 
TCS:TCM1:EE:RDTEMP 
TCS:TCM1:COIL1:RDTEMP 
TCS:TCM1:TBHT:RDTEMP 
TCS:TCM1:TGHT:RDTEMP 
TCS:TCM1:MSP:RDTEMP 
TCS:TCM1:HVC1:RDTEMP 
TCS:TCM1:HS:RDTEMP 
TCS:FC:SCALECUR 
TCS:COL:SCALECUR 
TCS:TK2:RDLEVEL 
TCS:TK2:RDLEVEL 
TCS:DIF1:RDFLOW 
TCS:CHILL:RDHRS

The archiver was restarted.

 

 

  903   Tuesday, April 28, 2015, 11:09 Anders MjosITWMaintenance  Resistance measured of TGHT and TBHT lines to ITW

The new TBHT and TGHT power supplies were brough up to high current; 350 A and 420 A respectively. The TGHT power supply was limited by PLC to 420 A. The resistance calculated for both the TBHT and TGHT copper lines from the electrical services room to the ITW pit was 1.35 mOhm. See attached spreadsheet for details.

Dave Morris has been contacted to correct the current limit for the TGHT supply to 600 A.

Attachment 1: Resistance_from_Electrical_Room_to_Target_Station.xlsx
  909   Monday, May 04, 2015, 13:32 Anders MjosConditioning StationMaintenance  TK2 expansion tank topped up

Caled cyclotron ops to open P23 and confirmed penthouse valve open.

Filled up TK2 to 21 in water leve.

  913   Monday, May 11, 2015, 10:45 Anders MjosConditioning StationMaintenance  RGA electronics box installed

 The communications chip has been replaced. The electronics box has been grounded (see attached pdf).

Attachment 1: 2015-05_RGA_GND_connection.pdf
2015-05_RGA_GND_connection.pdf 2015-05_RGA_GND_connection.pdf 2015-05_RGA_GND_connection.pdf
  930   Wednesday, June 03, 2015, 11:22 David WangConditioning StationStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015

I revised the Target Hall schedule to July 21 2015. It is the time new TM2 with ZrC target started at ITW.

2015-06-04, Updated the schedule with   new PDF view. See attachments 3, 4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
  945   Friday, June 12, 2015, 13:27 David WangSouth Hot-CellStandard Operation  TM2 new source tray has been remotely transferred from TH into SHC successfully.

TM2 new source tray has been remotely transferred into SHC successfully. The transfer table has been moved back to TH within 1 hour.  I swiped the table and found about 150counts contamination. It is much better comparing to last time using since we removed this table out of SHC as quick as we can. The table will be cleaned with windex  after Target Hall is surveyed.

  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015

Weekly update Target Hall schedule 2015-06-15. See attachment 1,2

 2015-06-19, Update the schedule on  the end of the week. See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf