  871   Wednesday, March 25, 2015, 10:37 chad fisherSouth Hot-CellDevelopment  TM2 optics tray build

TM2 optics tray build is continuing. Going well. Hope to have assembly and alignment finished by Friday.

 

 

  885   Monday, April 13, 2015, 08:59 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - June 26 2015

See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.

Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015.    See attachments 3,4.

  886   Wednesday, April 15, 2015, 09:01 Anders MjosConditioning StationDevelopment  Archiver variables added by Controls

 

 

 

 

 

 

 

 

 

 

The following variable have been added to the archiver (as per work request)

TCS:TS5:RDTEMP 
TCS:TCM1:EE:RDTEMP 
TCS:TCM1:COIL1:RDTEMP 
TCS:TCM1:TBHT:RDTEMP 
TCS:TCM1:TGHT:RDTEMP 
TCS:TCM1:MSP:RDTEMP 
TCS:TCM1:HVC1:RDTEMP 
TCS:TCM1:HS:RDTEMP 
TCS:FC:SCALECUR 
TCS:COL:SCALECUR 
TCS:TK2:RDLEVEL 
TCS:TK2:RDLEVEL 
TCS:DIF1:RDFLOW 
TCS:CHILL:RDHRS

The archiver was restarted.

 

 

  903   Tuesday, April 28, 2015, 11:09 Anders MjosITWMaintenance  Resistance measured of TGHT and TBHT lines to ITW

The new TBHT and TGHT power supplies were brough up to high current; 350 A and 420 A respectively. The TGHT power supply was limited by PLC to 420 A. The resistance calculated for both the TBHT and TGHT copper lines from the electrical services room to the ITW pit was 1.35 mOhm. See attached spreadsheet for details.

Dave Morris has been contacted to correct the current limit for the TGHT supply to 600 A.

  909   Monday, May 04, 2015, 13:32 Anders MjosConditioning StationMaintenance  TK2 expansion tank topped up

Caled cyclotron ops to open P23 and confirmed penthouse valve open.

Filled up TK2 to 21 in water leve.

  913   Monday, May 11, 2015, 10:45 Anders MjosConditioning StationMaintenance  RGA electronics box installed

 The communications chip has been replaced. The electronics box has been grounded (see attached pdf).

  930   Wednesday, June 03, 2015, 11:22 David WangConditioning StationStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015

I revised the Target Hall schedule to July 21 2015. It is the time new TM2 with ZrC target started at ITW.

2015-06-04, Updated the schedule with   new PDF view. See attachments 3, 4

  945   Friday, June 12, 2015, 13:27 David WangSouth Hot-CellStandard Operation  TM2 new source tray has been remotely transferred from TH into SHC successfully.

TM2 new source tray has been remotely transferred into SHC successfully. The transfer table has been moved back to TH within 1 hour.  I swiped the table and found about 150counts contamination. It is much better comparing to last time using since we removed this table out of SHC as quick as we can. The table will be cleaned with windex  after Target Hall is surveyed.

  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015

Weekly update Target Hall schedule 2015-06-15. See attachment 1,2

 2015-06-19, Update the schedule on  the end of the week. See attachment 3,4

  957   Tuesday, June 23, 2015, 10:55 chad fisherSouth Hot-CellRepair  Left Manipulator Repair

The master wrist/tong cable has been replaced on the left manipulator. Everything appears to function well so far.

  959   Tuesday, June 23, 2015, 16:49 Anders MjosConditioning StationDevelopment  TCS is beeing migrated to ISAC

by controls group (Dave Morris).


Friday, June 26, 2015

TCS has been migrated to ISAC controls. Access is possible on a per user basis from isacepics1.triumf.ca

  968   Tuesday, June 30, 2015, 09:47 chad fisherSouth Hot-CellRepair  manipulator repair

The right hand manipulator has been repaired. It took 43 minutes and I received ~ 0.56 mSv

  975   Thursday, July 02, 2015, 11:51 Travis CaveSpent Target VaultStandard Operation UC#12Spent target moved

UC#12 has been moved from the south hot cell and placed into storage. It is in pail #125 and in spot 1C of the vault it had a reading of 25.1mSv/hr upon removal from the south hot cell. See PDF for vault details.

  977   Friday, July 03, 2015, 09:27 Anders MjosConditioning StationDevelopment  Controls working on access control in EPICS

 Some reboots will be done.

  981   Tuesday, July 07, 2015, 10:50 Anders MjosConditioning StationDevelopment  EPICS migration update - archiver
  • The archiver is now merged with ISAC - data available under Utilities - Archiver Retrieval
  • Old archiver data is available under Utilities -> Archiver Retrieval - old
  • Strip tool save/load and export files under /data/tcsdata
  • Login via isacepics1.triumf.ca. TCS button on ISAC menu
  982   Tuesday, July 07, 2015, 12:12 David WangConditioning StationRepair  CS TP1S replacement

CS TP1S had been replaced with a new TP-301 pump this morning.The old pump was broken last week.

  999   Thursday, July 16, 2015, 07:38 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 07 2015

Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2

2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4

  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filter

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.

The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.

  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Update Target Hall schedule after the changing on TM2 process. See attachment 1,2