93
|
Tuesday, April 24, 2012, 10:36 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | Nb#6 | HV test April 23 | A HV test was complete on TM1 with
Friedhelm, David, and Myself. The module
behaved as it has in other tests. The vacuum |
|
92
|
Tuesday, April 24, 2012, 10:02 |
Travis Cave | ITW | Standard Operation | TM1 | Nb#6 | module move | TM#1 with Nb#6 from the conditioning station
to the west target station, move was uneventful.
Mike LaRoss was there today for move in place |
|
90
|
Friday, April 20, 2012, 14:07 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | Nb#6 | module move | TM#1 with Nb#6 is now in the conditioning
station. The fields of the module at the
south cell was 15.8mSv/hr. The move was uneventful. |
|
89
|
Thursday, April 19, 2012, 09:48 |
David Wang | South Hot-Cell | Standard Operation | TM1 | LP SIS Nb 6 | leak check heat shield circuit | Chad and I did a leak check on TM1 Nb5
target heat shield circuit. The leak detector
was connected to heat shield circuit.The |
|
88
|
Thursday, April 19, 2012, 09:36 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | Nb#6 | Electrical check | Electrical check has been completed of
TM#1 with Nb#6 attached. Our new micro-ohm
meter was also used for the first time for |
|
87
|
Tuesday, April 17, 2012, 11:30 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module moved | TM#1 moved from conditioning station to
the south hot cell, the module had a field
of 16mSv/hr. The move was not without |
|
86
|
Tuesday, April 17, 2012, 10:15 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Nb#6 | Target inserted into south hot cell | Nb#6 has been inserted into the south hot
cell in preparation for ionstallation onto
TM1. During the pre-insertion inspection |
|
85
|
Monday, April 16, 2012, 16:17 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | No Target | High Voltage Test | A high voltage test was completed
on a target free TM1 in the conditioning
station. Only the turbo pumps on the target |
|
84
|
Friday, April 13, 2012, 12:31 |
David Wang | Conditioning Station | Development | TM1 | | TM1 and conditioning station leak check. |
Normal
0
|
|
83
|
Thursday, April 12, 2012, 14:40 |
David Wang | Conditioning Station | Development | TM1 | | conditioning staion and TM1 is under TP1 and TP2 pumping now. | TM1 moved to conditioning station to today.
After moving, I connected the vacuum system
which include all gauges ,vacuum lines , |
|
82
|
Thursday, April 12, 2012, 09:38 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | no target | Move ot TM#1 | TM#1 has been moved from the NE silo to
the Conditioning Station. |
|
81
|
Thursday, April 05, 2012, 10:30 |
David Wang | ITE | Standard Operation | TM4 | | I moved 5 shielding blocks back to ITE this morning. | MAA is secured .The ITE and MAA are
ready for taking proton beam now. |
|
80
|
Tuesday, April 03, 2012, 12:11 |
David Wang | Conditioning Station | Development | | | leak check on conditioning station vacuum system | I did a leak check on conditioning station
vacuum system today.The vacuum system had
been roughed over night . This morning before |
|
79
|
Monday, April 02, 2012, 08:17 |
David Wang | Conditioning Station | Development | | | conditioning station IMC pump down. | I pumped down conditioning station IMC
today. The inside bellow pressure is -20
psi on the gauge.Visually checked the bellow |
|
78
|
Tuesday, March 13, 2012, 12:24 |
Anders Mjos | South Hot-Cell | Standard Operation | TM1 | UCx#3 | UCx#3 Autopsy |
|
|
77
|
Tuesday, March 13, 2012, 09:43 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#3 | UCx#3 to spent vault | UCx#3 was packaged into a spent can, double
bagged and the bag and cans filled with argon
as much as possible. Lid was attached and |
|
76
|
Tuesday, March 13, 2012, 09:42 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#3 | UCx#3 Autopsy | An autopsy was performed on UCx#3 yesterday
afternoon. This autopsy followed the plan
written by Anders. Indeed, both sides of |
|
75
|
Monday, March 12, 2012, 11:54 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module moved | TM#1 has been moved from the south hot
cell to the north east silo, move went well. |
|
74
|
Monday, March 12, 2012, 10:03 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UC#3 | UC#3 Removal | UC#3 was removed from TM1 this morning.
Upon removing the oven heater bolts BOTH
legs fell demonstrating that both sides of |
|
73
|
Monday, March 12, 2012, 09:19 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UCx#3 | module move | TM#1 with UC#3 was moved from the west
maa to the south hot cell, move went well |
|