ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
588
|
Wednesday, January 22, 2014, 15:20 |
Anders Mjos | South Hot-Cell | Standard Operation | | UC#8 | Target Inspection - post beam | The Target Assembly was inspected with
Chad, Jens Henning and Anders today.
The Target Container was |
|
587
|
Wednesday, January 22, 2014, 15:00 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#8 | Spent target move | UC#8 has been moved from the south hot
cell to the vault storage. It was placed
in pail 113 and placed in slot 8A of the |
|
586
|
Wednesday, January 22, 2014, 10:51 |
David Wang | ITE | Repair | | | Removed 4 shielding blocks located on top of preseperator in TH | Travis and I removed 4 shielding blocks
located on top of pre-seperator in
TH. This is a job for ITE harp 9 re-installation |
|
585
|
Tuesday, January 21, 2014, 14:32 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | module move | TM#4 has been moved from the south hot
cell to the north west silo. |
|
584
|
Monday, January 20, 2014, 14:37 |
Travis Cave | ITE | Standard Operation | TM4 | UC#8 | module move | TM#4 with UC#8 has been moved from the
east target station to the south hot cell. |
|
583
|
Monday, January 20, 2014, 13:40 |
maicodallavalle | Spent Target Vault | Maintenance | | F-308 | Empty F-308s | Four empty F-308s just arrived back at
Triumf. I moved them from shipping
to the Remote Handling Shop for service and |
|
582
|
Monday, January 20, 2014, 13:38 |
David Wang | ITE | Standard Operation | TM4 | | DISCONNECTED TM4 IN ITE. | I DISCONNECTED TM4 IN ITE. ALL WATER LINES
HAD BEEN PURGED OUT WITH PRESSURE AIR. |
|
581
|
Monday, January 20, 2014, 13:35 |
David Wang | ITE | Standard Operation | TM4 | | 5 shielding blocks had been moved out of ITE | 5 SHIELDING BLOCKS HAD BEEN MOVED OUT OF
ITE.AIR SAMPLE AND SWIPED FIRST BLOCK AND
ITE PIT.NOTHING HAD BEEN FOUND ON ALPHA MONITOR |
|
580
|
Thursday, January 16, 2014, 10:36 |
chad fisher | South Hot-Cell | Repair | | | East Manipulator Repair | The repair/cable replacement on the east
manipulator is now complete.
Yesterday's initail cable replacement |
|
579
|
Thursday, January 09, 2014, 11:07 |
chad fisher | South Hot-Cell | Maintenance | | | Field Level | I have managed to reduce the field at the
broken manipulator from 12 mSv/h to 400 uSv/h. |
|
578
|
Thursday, December 12, 2013, 11:14 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV Chase Electrical Test | While under vacuum Travis and I completed
diagnostics of the HV chase. Majority of
the lines showed OL at 1kV but there were |
|
577
|
Monday, December 09, 2013, 14:47 |
David Wang | ITE | Standard Operation | TM4 | | I moved 5 shielding blocks from block storage area to ITE. | I moved 5 shielding blocks to ITE. The
ITE is configured to take proton beam. |
|
576
|
Monday, December 09, 2013, 13:15 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#41 | Spent target move | The spent Ta#41 target has been moved from
the south hot cell to the spent target storage
vault. It is an unnumbered pail (should be |
|
575
|
Friday, December 06, 2013, 15:09 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | TM2 no source tray 55kV 1 hour | Today 55kV was applied to TM2 and held
for over 1 hour with the EINZEL at 27.5kV.
There were 2 sparks and the current was unstable |
|
574
|
Thursday, December 05, 2013, 14:57 |
David Wang | ITE | Standard Operation | TM4 | | Connected TM4 in ITW | I connected TM4 in ITE. All turbo pumps
have been started and wok fine including
new TP3. Everything is good so far. |
|
573
|
Thursday, December 05, 2013, 14:55 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Leak check on TM4 target heat shield | Chad and I leak checked TM4 heat shied
water circuit at SHC. The pumping down was
very good.Base leak rate 0.0xe-9 atm.cc/sec. |
|
572
|
Thursday, December 05, 2013, 12:51 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#8 and no target | Electrical check | Electrical check was done on TM#4 without
a target and with the UC#8 target on see
attached PDF for results. |
|
571
|
Thursday, December 05, 2013, 12:04 |
Travis Cave | ITE | Standard Operation | TM4 | UC#8 | module move | TM#4 with UC#8 has been moved from the
south hot cell to the east target station. |
|
570
|
Wednesday, December 04, 2013, 14:09 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#41 | Electrical check | Electrical check of TM#4 with Ta#41 post
beam at the south hot cell. See PDF for details |
|
569
|
Wednesday, December 04, 2013, 13:57 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | Ta #47 | Ta #47 Removed - broken bolt | Ta #47 has been removed from TM4.
One containment box cover bolt would
not come out. Upon attempted removal with |
|