Message ID: 588     Entry time: Wednesday, January 22, 2014, 15:20
Author: Anders Mjos 
Category: South Hot-Cell 
Type: Standard Operation 
Module:  
Target/Number: UC#8 
Subject: Target Inspection - post beam 

The Target Assembly was inspected with Chad, Jens Henning and Anders today.

  • The Target Container was broken.
  • Material was deposited on the Heat Shield around the Target Center Block
  • Material was deposited on the IG-LIS source.
  • Electrical checks to ground (HS)
    • The Extraction Electrode passed the electrical check at 1000V
    • The Exit Electrode (c) held only 40V at 22 kOhm
    • The IG Electrode 1 (f) held 250V at 390 MOhm
    • The IG Electrode 2 (g) held only 40V at 22 kOhm
  • IG 1 and IG 2 both held 250V at 450 MOhm to Exit Electorde (c)
  • No spark marks were observed on the 9-pin connector

See photos of the inspection on DocuShare