448
|
Wednesday, September 11, 2013, 11:31 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved to the
conditioning station from the south hot cell. |
|
447
|
Wednesday, September 11, 2013, 09:35 |
David Wang | ITW | Standard Operation | TM1 | UCx | 5 shielding blocks have been moved to ITW | I moved 5 shielding blocks to ITW this
morning .I checked the water signals in electrical
room before the moving, and everything is |
|
446
|
Tuesday, September 10, 2013, 12:11 |
Isaac Earle | South Hot-Cell | Repair | TM3 | | Module side heat shield water block polishing and blank-off installation | The sealing surfaces of the module
side heat shield water block were polished
on September 9th in the morning using Chad's |
|
445
|
Friday, September 06, 2013, 17:50 |
Grant Minor | South Hot-Cell | Development | TM3 | | C-Seal crush investigation |
|
|
444
|
Friday, September 06, 2013, 16:41 |
Bevan Moss | South Hot-Cell | Development | TM3 | | C-Seal crush investigation | Today Maico completed the new leak
testing tool and blank off. He tested them
with C-seals without springs and all was |
6x |
443
|
Wednesday, September 04, 2013, 19:01 |
Grant Minor | South Hot-Cell | Repair | TM3 | | Inspection / Ante Room Leak Check Results on TM3 Heat Shield lines (3 Sept 2013) | Yesterday, Grant entered the Ante Room
with David Wang to visually inspect the two
sets of failed c-seals from the Heat Shield |
|
442
|
Wednesday, September 04, 2013, 18:53 |
Grant Minor | South Hot-Cell | Repair | TM3 | | Maico's measurements of new c-seals and bench-tested c-seals | Today Maico measured the thickness of three
indium-plated inconel c-seals, presumably
Ultra-Seal P/N 50606. These seals had |
|
441
|
Wednesday, September 04, 2013, 12:21 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Ante-room work | September 3rd
David Wang and myself lowered the
leak testing cart into the Ante room and |
|
440
|
Friday, August 30, 2013, 14:55 |
Bevan Moss | South Hot-Cell | Repair | TM3 | N/A | Heat Shield Repair |
|
|
439
|
Friday, August 30, 2013, 10:27 |
Bevan Moss | South Hot-Cell | Repair | TM3 | N/A | Heat Shield Repair |
|
|
438
|
Thursday, August 29, 2013, 17:16 |
Bevan Moss | South Hot-Cell | Repair | TM3 | N/A | Heat Shield Repair | Today Chad entered the south hot
cell on work permit 2013-08-29-3 to repair
the leaking heat shield line. The heat shield |
|
437
|
Thursday, August 29, 2013, 12:03 |
Grant Minor | South Hot-Cell | Repair | TM3 | no target | Heat Shield Circuit Leak |
|
|
436
|
Thursday, August 29, 2013, 10:09 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Heat Shield Circuit Leak |
|
|
435
|
Thursday, August 29, 2013, 09:08 |
chad fisher | South Hot-Cell | Repair | TM3 | | Heat Shield Circuit Leak | The heat shield circuit was pressurized
with air (15-20 psi) and snoop applied to
the water block joint and brazes. Bubbles |
|
434
|
Thursday, August 29, 2013, 06:48 |
David Wang | Conditioning Station | Development | TM3 | | TM3 leak check in CS with new source tray. | A huge leak had been found on HS circuit
during 60 psi helium pressurize test. Other
circuits are free of obvious major leak at |
|
433
|
Wednesday, August 28, 2013, 14:25 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved from
the conditioning station to the south hot
cell. The fields observed around the containment |
|
432
|
Wednesday, August 28, 2013, 14:17 |
Travis Cave | South Hot-Cell | Standard Operation | | UC#6 | Spent target move | Spent target move, UC#6 has been moved
from the south hot cell to the target storage.
The target is in pail 108 and in slot 8C |
|
431
|
Tuesday, August 27, 2013, 17:18 |
Grant Minor | Conditioning Station | Repair | TM3 | no target | TM3 Rev 3 source tray - prelminary leak check results at CS | David Wang started a helium leak check
on TM3 at the CS this morning.
David will create an e-log once his |
|
430
|
Tuesday, August 27, 2013, 14:14 |
Travis Cave | ITW | Standard Operation | TM1 | UC#7 | module move | TM#1 with UCx#7 has been moved from the
south hot cell to the west target station. |
|
429
|
Tuesday, August 27, 2013, 11:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#7 | Electrical check | TM#1 with UCx#7 electrical check, numbers
look good, see PDF for details. |
|