2568
|
Friday, April 26, 2024, 08:56 |
David Wang | Conditioning Station | Development | TM3 | | TM3 module top helium spray leak test. | TM3 module top helium spray leak test was
done yesterday. No leak on TM3 module
top @ LD base leak rate 0.0 x E-9 atm.cc/sec. |
|
2567
|
Wednesday, April 24, 2024, 10:15 |
David Wang | Conditioning Station | Standard Operation | TM3 | | TM3 has been moved from SHC to TCS. | TM3 has been moved from SHC to TCS.
The move is smooth. |
|
2566
|
Tuesday, April 23, 2024, 17:34 |
Carla Babcock | South Hot-Cell | Repair | TM3 | | TM3 wire pulling | Wires were pulled in TM3 and service cap
was closed up again:
Einzel lens wire (30kV kapton), routed |
|
2565
|
Friday, April 19, 2024, 10:44 |
David Wang | South Hot-Cell | Development | TM3 | | TM3 water lines helium spray leak check at SHC. | TM3 water lines helium spray leak check
at SHC is done. No leak has been found on
all lines. seeattachment |
|
2564
|
Wednesday, April 17, 2024, 11:58 |
David Wang | ITE/ITW | Maintenance | | | ITH:MP1S pump inside lubricant was changed today. | ITH:MP1S pump inside lubricant was changed
today. old lubricant is dirty with dark color.
they are stored in sealed waste oil jug and |
|
2563
|
Tuesday, April 16, 2024, 12:33 |
David Wang | Conditioning Station | Standard Operation | | | test TCS water system chillers stage in/out. | Monday and Tuesday, I started TCS water
system and enabled the TCS chillers auto
stage in/out. I saw chiller 2 in/out three |
|
2562
|
Thursday, April 11, 2024, 06:27 |
David Wang | South Hot-Cell | Development | TM3 | | TM3 new source tray was transferred into SHC on this Tuesday. | TM3 new source tray was transferred into
SHC on this Tuesday. one hook arm of transfer
jig is very close to optic tray tube when |
|
2561
|
Thursday, April 11, 2024, 06:07 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 was moved from silo to SHC yesterday. | Tm3 was moved from silo to SHC yesterday.
the move is smooth. |
|
2560
|
Monday, April 08, 2024, 09:29 |
David Wang | Cooling | Standard Operation | | | HALCW system general inspection. | water are supplied to both ITE and ITW.
I did a general inspection on HALCW system.
Two small leaks on 2" shut off valves |
|
2559
|
Thursday, April 04, 2024, 13:10 |
David Wang | Cooling | Maintenance | | | high active water refurbishment, reinstallation, and test operation. | both high active pumps ITC:MP1 and MP2
are refurbished by RH group Maico and Peter.
Pumps have been installed back to system |
|
2558
|
Wednesday, April 03, 2024, 10:48 |
chad fisher | South Hot-Cell | Maintenance | | | SE Manipulator wrist swap | On April 2, 2024 the wrist on the SE manipulator
of the SHC (Serial # 7986) was swapped with
a rebuild unit originally from SW position |
|
2557
|
Thursday, March 28, 2024, 09:26 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 has been moved from SHC to silo. | Tm3 has been moved from SHC to silo.
The move is smooth. |
|
2556
|
Wednesday, March 27, 2024, 09:52 |
David Wang | ITE | Standard Operation | | | ITE entrance module top and module flange o-ing to tank have been leak checked. | ITE entrance module top and module flange
o-ing to tank have been leak checked. no
leak at 0.0xe-9 atm.cc/sec. things are double |
|
2555
|
Wednesday, March 27, 2024, 09:49 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 has been moved to SHC from silo. | Tm3 has been moved to SHC from silo. the
move is smooth. |
|
2554
|
Monday, March 25, 2024, 10:55 |
David Wang | ITE | Standard Operation | | | ITE entrance module has been reconnected in ITE pit. | ITE entrance module has been reconnected
in ITE pit per document 190510. |
|
2553
|
Monday, March 25, 2024, 10:53 |
David Wang | ITE | Repair | | | ITE entrance module has been moved from TCS to ITE. | ITE entrance module has been moved from
TCS to ITE. The move is smooth. |
|
2552
|
Thursday, March 21, 2024, 11:35 |
Ferran Boix Pamies | ITE | Development | | | Wiring of new thermocouple PLC module | Thursday, March 21, 2024, 11:33 Three
channels are available now for thermocouple
readouts from the Target multipin. Wiring |
|
2551
|
Friday, March 15, 2024, 10:04 |
Adam Newsome | South Hot-Cell | Standard Operation | TM3 | | TM3 Move - SHC to NE Silo | TM3 was moved from SHC to NE silo. Cable
tray was recently installed. |
|
2550
|
Thursday, March 14, 2024, 14:54 |
David Wang | ITE | Maintenance | | | ITE entrance module has been moved from ITE pit to TCS. | ITE entrance module has been moved from
ITE pit to TCS. The move is smooth.ITE entrance
module top tank flange and o ring slot are |
|
2549
|
Wednesday, March 13, 2024, 11:12 |
Keith C Ng | Assembly/Bench Test | Repair | TM3 | | optics tray for tm3 | Alignment notes attached for the optics
tray for the refurbished tm3 with the new
service and source tray. |
|