  ID Date Author Category Type Module Target/Number Subject Text Attachments
  118   Wednesday, June 06, 2012, 13:36 chad fisherSouth Hot-CellStandard OperationTM1Ta#38Target Change Nb#6 - Ta#38Nb#6 was removed from TM1...it looked very
clean.
Ta#38 was installed onto TM1...fit
  
  117   Wednesday, June 06, 2012, 08:21 David WangITWStandard OperationTM1 TM1 disconnected in ITWI disconnected TM1 in ITW yesterday morning.The
general radioactive level in ITW over the
TM top (300mm) is about 350 usv/hr. contacting
  
  116   Tuesday, June 05, 2012, 15:06 Bevan MossITWStandard OperationTM1Nb#6Module move from ITW to SHC TM1 has been moved from ITW to the
SHC. The move did encounter some issues,
one of the railings for preventing people
  
  115   Tuesday, June 05, 2012, 12:20 Bevan MossSouth Hot-CellStandard OperationTM1Ta#38Target inserted into HCTa#38 has been placed into the south hot
cell. Swipes of the tool port were taken
there was a count of 600 on the floor and
  
  114   Monday, May 28, 2012, 13:05 David WangITEStandard Operation  I moved 5 shielding blocks from ITW to ITE .5 shielding blocks have  been transferred
from  ITW to ITE. ITE ventilation is
opened, and ITW closed. All ITE water 
  
  113   Friday, May 25, 2012, 10:48 Travis CaveSpent Target VaultStandard Operation  Moving the spent targets to mini storage.Five targets were moved to the mini storage
today in preparation for transfer of the
targets to the F308s later next week. The
 Mini_Vault_Storage_May_25_2012.pdfVault_Storage_May_25_2012.pdf 
  112   Tuesday, May 22, 2012, 15:19 David WangITEStandard OperationTM4sic 27TM4 in ITE under pumping

Normal
0





  
  111   Tuesday, May 22, 2012, 12:36 David WangITEStandard OperationTM4sic 27TM4 connection in ITEAll TM4 connections in ITE is done. The
station and TM4 is under roughing now.
  
  110   Tuesday, May 22, 2012, 10:50 Travis CaveITEStandard OperationTM4SiC#27module movedModule has been moved from conditioning
station to the east target station. Move
went well.
  
  109   Tuesday, May 22, 2012, 10:00 David WangConditioning StationStandard OperationTM4sic 27helium pressure test on heat shield circuitI did a helium pressure test on heat shield
circuit. The leak detector is concected to
the TM4 primary vacuum system.The IG1 is
  
  108   Tuesday, May 22, 2012, 08:33 Travis CaveConditioning StationStandard OperationTM4SiC#27Electrical checkElectrical check of TM#4 with SiC#27 under
vacuum at that conditioning station. See
attached PDF for details.
 TM#4_SiC#27_pre_beam_under_vac.PDF 
  107   Friday, May 18, 2012, 08:37 David WangSouth Hot-CellStandard OperationTM4sic 27leak check on heat shield circuitChad and I leak checked the heat shield
circuit after sic 27 target  installed.
It took 20minutes  to pump down
  
  106   Friday, May 18, 2012, 08:29 Travis CaveSouth Hot-CellStandard OperationTM4SiC#27Electrical checkTM#4 with SiC#27 has had its electrical
check. See attached PDF for details.
 TM#4_SiC#27_pre_beam.PDF 
  105   Friday, May 18, 2012, 08:17 chad fisherSouth Hot-CellStandard OperationTM4SiC#27SiC#27 InstalledSiC#27 has been installed onto TM4. Fit
was very good. All electrical connections
double checked with mirror.
  
  104   Thursday, May 17, 2012, 14:08 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 has been moved from the north east
silo to the south hot cell for target installation. 
No problems with the move.
  
  103   Wednesday, May 16, 2012, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#26Spent target moveSiC #26 was moved from the south hot cell
into storage today. The target was is in
pail # 94 and was placed in slot 1B in the
 Vault_Storage_May_16_2012.pdf 
  102   Tuesday, May 15, 2012, 14:29 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 moved from the south hot cell to the
north east storage silo. No issues with the
move.
  
  101   Tuesday, May 15, 2012, 12:14 chad fisherSouth Hot-CellStandard OperationTM4SiC#26SiC#26 removal TM4 degredationSiC#26 was removed from target module #4
this morning. Target shows the now standard
arc marks on the 9 pin connector housing...pictures
 19x 
  100   Tuesday, May 15, 2012, 11:45 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26Electrical checkResults of the electrical check of TM#4
with SiC#26 attached post beam.
 TM#4_SiC#26_FEBIAD_post_beam.PDF 
  99   Monday, May 14, 2012, 12:37 Travis CaveITEStandard OperationTM4SiC#26module moveTM#4 with SiC #26 was moved from the East
Station to the South Hot Cell. Bevan was
at the helm of the PLC. There was no issue
  