Entry  Friday, March 27, 2015, 11:25, Travis Cave, Cyclotron, Standard Operation, Copper Blockers 
Copper Blockers have been removed from the cyclotron and one ladder has been installed.
Entry  Thursday, April 02, 2015, 12:09, Dan McDonald, Cyclotron, Standard Operation, Lid Down operations April, 2, 2015 
Lid down Start at 11:17, lid went down without any issues or stop's. Lid finish at 11:45 
 
 
Entry  Tuesday, January 05, 2016, 09:58, Travis Cave, Cyclotron, Standard Operation, Opened the shield door 
The shield door on the B2 level has been opened.
Entry  Wednesday, February 03, 2016, 08:16, Dan McDonald, Cyclotron, Standard Operation, Cyclotron lid up  lid_up_2016.pdf
Lid up procedure Started at  12:00pm. Initial numbers. # 1-47,2-49,3-45,4-47,5-47,6-47,7-49,8-45,9-50,10-50,11-51,12-49. After a number of unsuccessful
attempts at jogging the system and trouble shooting it was decided to suspend operations record numbers  and resume on Feb 2nd. Final numbers for
Feb 1st #1-1289,2-1297,3-1288,4-1295,5-1283,6-1298,7-1287,8-1289,9-1290,10-1296,11-1287,12-1296.
Entry  Tuesday, February 09, 2016, 14:48, Travis Cave, Cyclotron, Standard Operation, shadow shields 
All shadow shields have been installed. Ladders, the pothole covers and the second rad survey will be done tomorrow.
Entry  Wednesday, February 10, 2016, 14:53, Travis Cave, Cyclotron, Standard Operation, shadow shields 
All cyclotron in tank work is completed.
Entry  Tuesday, February 16, 2016, 16:32, Isaac Earle, Cyclotron, Standard Operation, HE1 Probe Removed from Cyclotron 
The HE1 Probe was removed from the cyclotron this morning following the procedure in Document-126165 (currently in draft status, to be released after
the probe has been reinstalled).  The procedure took approximately 2 hours from when the trolley was put into the tank until when it was removed from
the tank with the probe.  The procedure took from 8am - noon including putting the bridge into the cyclotron, and removing the probe from the trolley
Entry  Friday, February 19, 2016, 10:17, Isaac Earle, Cyclotron, Standard Operation, HE1 Probe Installed in Cyclotron 
 The HE1 Probe was reinstalled into the cyclotron this morning following Section 3.2 in Document-126165 (to be reviewed and released after camera
view screen captures added).  The procedure took approximately 1 hour from when the trolley was moved into the cyclotron tank until when it was removed.
 Camera view screenshots were captured throughout the procedure and the probe head was inspected with the left outrigger camera after installation
Entry  Thursday, February 25, 2016, 11:41, Travis Cave, Cyclotron, Standard Operation, Ex 2C removal 
Ex 2C has been removed from the cyclotron. A trip into the tank was needed to free the probe, hung up on the usual spot.
Entry  Tuesday, March 01, 2016, 13:27, Travis Cave, Cyclotron, Standard Operation, Ex 2C install 
EX 2C has been installed back into the cyclotron.
Entry  Wednesday, March 09, 2016, 17:09, Ron Kuramoto, Cyclotron, Development, EX4N new housing installation dspage07994143927104268192.pdfExtr_4N_Final_instalation_-_gimbal-pipe-valve.docxIMG_1886.JPG
The new EX4N housing assembly drawing TEC0071 (unfinished) was installed and connected to the EX4 tank side port flange over a 3 day period from Feb29
– Mar 2, 2016. This was a hands on installation spread amongst 5 people with the total accumulated dose was 2.97 mSv.  See W/P C2016-02-29-5
 
Entry  Tuesday, March 15, 2016, 13:56, Dan McDonald, Cyclotron, Standard Operation, Lid Down 2016 
Lid down Started at 12:15, station and count numbers. Lid went down with out incident as station 1 and 7 show the counters will need replacing. We are
going to change counters before the end of this shutdown to ensure proper orientation in case of emergency lid up scenario. 
Start          12:15                  
Entry  Thursday, April 07, 2016, 11:04, Travis Cave, Cyclotron, Standard Operation, Closed the shield door 
The shield door on the B2 level of the RH building has been closed.
Entry  Tuesday, January 31, 2017, 14:41, Travis Cave, Cyclotron, Standard Operation, Shield installation 
200, 400, 500, 600, and a pallet of 700 series of shield have been installed in the cyclotron.
Entry  Thursday, February 09, 2017, 15:21, Isaac Earle, Cyclotron, Standard Operation, HE2 Probe Removed 
 The HE2 probe was removed from the cyclotron today following the
procedure in Document #126165.  An orbital bridge position of 247.35° provided better alignment than 247.2
from the procedure.  The probe signal head was intentionally left in the "up" position by Diagnostics Group which did not cause any issues
Entry  Tuesday, February 21, 2017, 13:40, Isaac Earle, Cyclotron, Standard Operation, HE2 Probe Returned to Cyclotron 
 The HE2 probe was reinstalled in the cyclotron this morning following the procedure in Document #126165.  An orbital bridge position of 247.35°
was used (same as for the removal on Feb 9th).  The installation went smoothly.
Entry  Tuesday, February 28, 2017, 15:45, Jason Kapalka, Cyclotron, Standard Operation, 2C extraction probe removal and reinstallation 
2C extraction probe was removed from cyclotron tank on 2017-02-07 by RH and Probes group members with service 
bridge, upper resonator trolley, and 2C attachment. Three QDLs were disengaged remotely, while one had to be 
disengaged locally in the tank (just like in 2013, 2014, 2015, and 2016).
Entry  Friday, March 03, 2017, 13:30, Jason Kapalka, Cyclotron, Standard Operation, CP continuity test 
Performed continuity test at Cyclotron center post with RH and Operations group members using the service bridge, 
tool trolley, and probe attachment on 2017-03-03.
Entry  Tuesday, March 14, 2017, 11:23, Jason Kapalka, Cyclotron, Standard Operation, Start/end of shutdown photo and video survey Cyclotron_Video_Inspecting_Guidelines_(RevX_20170314).xlsx
The start of shutdown photo and video survey was performed in the Cyclotron tank by the RH group using the 
service bridge and video trolley on 2017-01-27 (see attached pictures).
 
Entry  Tuesday, March 14, 2017, 12:02, Jason Kapalka, Cyclotron, Standard Operation, Radiation survey Procedure_for_Cyclotron_Tank_Radiation_Survey_by_Don_Jackson_(20000106_Obsolete).doctankworkssubplot.m2017_01_30_shields_out_tank_superimposed.png2017_02_02_shields_in.png
The unshielded radiation survey was performed in the Cyclotron tank by the RH group using the service bridge, 
tool trolley, and radiation survey attachment on 2017-01-30 (see attached plot).