  58   Friday, March 06, 2015, 14:38 Travis CaveCyclotronStandard OperationShield RemovalAll shields and ladders have been removed
from the tank, all the port holes have been
uncovered, the tank seal has been vacuumed,
  
  62   Tuesday, March 17, 2015, 13:04 maicodallavalleCyclotronMaintenanceUpper Bearings Station #5 and #10The Upper bearings on Station #5 and Station
#10 have been serviced. The Upper Bearing
were disassembled. The old gear was removed
  
  65   Friday, March 27, 2015, 07:31 Dan McDonaldCyclotronRepairLid up operationsLid up recap for  March 26th 2015.

Start time 14:50       
  
  66   Friday, March 27, 2015, 11:25 Travis CaveCyclotronStandard OperationCopper BlockersCopper Blockers have been removed from
the cyclotron and one ladder has been installed.
  
  67   Thursday, April 02, 2015, 12:09 Dan McDonaldCyclotronStandard OperationLid Down operations April, 2, 2015Lid down Start at 11:17, lid went down
without any issues or stop's. Lid finish
at 11:45 
  
  74   Tuesday, January 05, 2016, 09:58 Travis CaveCyclotronStandard OperationOpened the shield doorThe shield door on the B2 level has been
opened.
  
  77   Wednesday, February 03, 2016, 08:16 Dan McDonaldCyclotronStandard OperationCyclotron lid up Lid up procedure Started at  12:00pm.
Initial numbers. # 1-47,2-49,3-45,4-47,5-47,6-47,7-49,8-45,9-50,10-50,11-51,12-49.
After a number of unsuccessful attempts at
 lid_up_2016.pdf 
  80   Tuesday, February 09, 2016, 14:48 Travis CaveCyclotronStandard Operationshadow shieldsAll shadow shields have been installed.
Ladders, the pothole covers and the second
rad survey will be done tomorrow.
  
  81   Wednesday, February 10, 2016, 14:53 Travis CaveCyclotronStandard Operationshadow shieldsAll cyclotron in tank work is completed.   
  82   Tuesday, February 16, 2016, 16:32 Isaac EarleCyclotronStandard OperationHE1 Probe Removed from CyclotronThe HE1 Probe was removed from the cyclotron
this morning following the procedure in Document-126165
(currently in draft status, to be released
  
  83   Friday, February 19, 2016, 10:17 Isaac EarleCyclotronStandard OperationHE1 Probe Installed in Cyclotron The HE1 Probe was reinstalled into
the cyclotron this morning following Section
3.2 in Document-126165 (to be reviewed and
  
  84   Thursday, February 25, 2016, 11:41 Travis CaveCyclotronStandard OperationEx 2C removalEx 2C has been removed from the cyclotron.
A trip into the tank was needed to free the
probe, hung up on the usual spot.
  
  85   Tuesday, March 01, 2016, 13:27 Travis CaveCyclotronStandard OperationEx 2C installEX 2C has been installed back into the
cyclotron.
  
  86   Wednesday, March 09, 2016, 17:09 Ron KuramotoCyclotronDevelopmentEX4N new housing installationThe new EX4N housing assembly drawing TEC0071
(unfinished) was installed and connected
to the EX4 tank side port flange over a 3
 dspage07994143927104268192.pdfExtr_4N_Final_instalation_-_gimbal-pipe-valve.docxIMG_1886.JPG 
  87   Tuesday, March 15, 2016, 13:56 Dan McDonaldCyclotronStandard OperationLid Down 2016Lid down Started at 12:15, station and
count numbers. Lid went down with out incident
as station 1 and 7 show the counters will
  
  88   Thursday, April 07, 2016, 11:04 Travis CaveCyclotronStandard OperationClosed the shield doorThe shield door on the B2 level of the
RH building has been closed.
  
  91   Tuesday, January 31, 2017, 14:41 Travis CaveCyclotronStandard OperationShield installation200, 400, 500, 600, and a pallet of 700
series of shield have been installed in the
cyclotron.
  
  93   Thursday, February 09, 2017, 15:21 Isaac EarleCyclotronStandard OperationHE2 Probe Removed The HE2 probe was
removed from the cyclotron today following
  
  94   Tuesday, February 21, 2017, 13:40 Isaac EarleCyclotronStandard OperationHE2 Probe Returned to Cyclotron The HE2 probe was reinstalled in
the cyclotron this morning following the
procedure in Document #126165.  An orbital
  
  95   Tuesday, February 28, 2017, 15:45 Jason KapalkaCyclotronStandard Operation2C extraction probe removal and reinstallation2C extraction probe was removed from cyclotron
tank on 2017-02-07 by RH and Probes group
members with service 
  