Entry  Friday, January 24, 2014, 14:10, Travis Cave, Cyclotron, Standard Operation, Copper blockers 
The copper blockers have been removed from the cyclotron and placed into the coffins.
Entry  Wednesday, January 29, 2014, 15:08, Bevan Moss, Cyclotron, Standard Operation, Shielding and Port Hole Covers 
 The Shielding and the Port Hole Covers have all been installed. No issues with the installation have caused any problems. This orbit, radial, and
vertical read back continues to be an issue.
Entry  Thursday, January 30, 2014, 13:47, Travis Cave, Cyclotron, Standard Operation, shields 
All shields, pothole covers, and ladders have been installed into the cyclotron.
Entry  Friday, January 31, 2014, 10:07, Travis Cave, Cyclotron, Standard Operation, 2C removal 
2C has been successfully removed from the cyclotron and is now currently sitting in the B2 level of the RH building. A tank access was needed to feel
the stuck QDL.
Entry  Friday, February 07, 2014, 10:50, Travis Cave, Cyclotron, Standard Operation, 2C install 
2C has been installed into the cyclotron.
Entry  Friday, February 21, 2014, 11:05, Bevan Moss, Cyclotron, Standard Operation, Old Monitor Box Removed, New installed 7x
 One of the beam spill monitor boxes was removed and placed into a lead coffin. The fields around the coffin prior to the monitor being placed in
were 145 uSv/hr just above the box and 33.5 uSv/hr inside of it. A swipe was taken inside the box at this time and a count of zero was found. The tray
for the monitor box was then placed into the coffin and the monitor removed from the cyclotrons. The field above the coffin with the monitor box was 1.0
    Reply  Friday, February 21, 2014, 15:58, Bevan Moss, Cyclotron, Standard Operation, Old Monitor Box Removed, New installed 
During the electrical test the was no contact.  To help investigate further the Montitor box was removed from the Cyclotron. It was found to have
zero counts. The issue is believed to have to do with the fit of the box but confirmation of the writing harness continuity needs to be completed. This
will continue on Monday. 
Entry  Monday, March 03, 2014, 13:09, Travis Cave, Cyclotron, Standard Operation, shields 
all shields, porthole covers and ladder out and copper blockers in. Some conmination was found on the pads of the ladders (about a 1000 count or so)
and was removed.
Entry  Tuesday, January 27, 2015, 14:40, Travis Cave, Cyclotron, Standard Operation, Day one of in tank work 
Day one of RH in tank work for the cyclotron (shields and blockers stuff like that) many pictures were taken.
Entry  Wednesday, January 28, 2015, 14:33, Travis Cave, Cyclotron, Standard Operation, Day two of in tank work 
All copper blocker removed from the cyclotron and first radiation survey done. Shields start tomorrow.
Entry  Thursday, January 29, 2015, 14:53, Travis Cave, Cyclotron, Standard Operation, Day three of in tank work 
Over 50% of the shields are in some 700's left and the monitor box covers.
Entry  Friday, January 30, 2015, 15:02, Travis Cave, Cyclotron, Standard Operation, Day four of in tank work 
All shields, ladders and pothole covers are in. One rad survey left to do.
Entry  Monday, February 02, 2015, 14:28, Travis Cave, Cyclotron, Standard Operation, Day five of in tank work 
Final Radiation Survey done. All in tank work completed bridge removed from the tank.
Entry  Wednesday, February 04, 2015, 13:57, Travis Cave, Cyclotron, Standard Operation, 2C removal 
2C has been removed from the cyclotron.
Entry  Tuesday, February 17, 2015, 11:28, Travis Cave, Cyclotron, Standard Operation, 2C Installation 
2C extraction probe has been re-installed in the cyclotron. After some problems on the first install attempt, do to a busted micro-switch that was causing
the 24 Volt DC system to short out.
Entry  Friday, March 06, 2015, 14:38, Travis Cave, Cyclotron, Standard Operation, Shield Removal 
All shields and ladders have been removed from the tank, all the port holes have been uncovered, the tank seal has been vacuumed, and the copper blockers
installed into the cyclotron.
Entry  Tuesday, March 17, 2015, 13:04, maicodallavalle, Cyclotron, Maintenance, Upper Bearings Station #5 and #10 
The Upper bearings on Station #5 and Station #10 have been serviced. The Upper Bearing were disassembled. The old gear was removed and wiped clean. All
parts were inspected.All parts were greased and then reassembled.All Fall Protection Platform railing was collapsed on both stations #5and #10.
Entry  Friday, March 27, 2015, 07:31, Dan McDonald, Cyclotron, Repair, Lid up operations 
Lid up recap for  March 26th 2015. 
Start time 14:50        Master- 33                              
Finish 15:25        Master -47413             Zero jogs
Entry  Friday, March 27, 2015, 11:25, Travis Cave, Cyclotron, Standard Operation, Copper Blockers 
Copper Blockers have been removed from the cyclotron and one ladder has been installed.
Entry  Thursday, April 02, 2015, 12:09, Dan McDonald, Cyclotron, Standard Operation, Lid Down operations April, 2, 2015 
Lid down Start at 11:17, lid went down without any issues or stop's. Lid finish at 11:45 
 
 