141
|
Wednesday, May 04, 2022, 12:07 |
Adam Newsome | Trolley | Development | Tool Trolley: Brass air fittings replacement complete | All of the old brass air fittings on the
Tool Trolley have now been swapped over to
push-connect style fittings. As these are |
|
|
155
|
Thursday, August 03, 2023, 10:43 |
Adam Newsome | Trolley | Development | Previous generation video trolley decommissioned | The "old" video trolley featuring
scissor mechanism and DSLR camera has officially
been decommissioned. Going forward, Video |
|
|
157
|
Thursday, September 14, 2023, 13:51 |
Adam Newsome | Trolley | Maintenance | Lift Trolley: upgrades to camera tilt mechanism | The two camera tilt mechanisms on the lift
trolley have been upgraded. Upgrades include:
For the individual camera: |
|
|
158
|
Friday, September 15, 2023, 10:15 |
Adam Newsome | Trolley | Maintenance | Lift Trolley: mirror actuation mechanism repair/upgrade | The mirror actuation mechanism was observed
to be "sticky" during 2023 winter
shutdown - it occasionally did not function |
|
|
168
|
Friday, February 16, 2024, 11:11 |
Adam Newsome | Trolley | Repair | Lift Trolley: vertical motion failure, motor relays replaced | Today (2024-02-16) when operating the lift
trolley to install shields in the cyclotron,
the vertical motion was observed to be intermittently |
|
|
30
|
Monday, January 27, 2014, 14:42 |
Travis Cave | Shielding | Standard Operation | shields and radiation survey | The cyclotron radiation survey was aborted
due to the orbit not working recording the
numbers correctly. One shield has been in |
|
|
31
|
Tuesday, January 28, 2014, 14:59 |
Travis Cave | Shielding | Standard Operation | shields | 200's, 400's, 500's, 600's, and a pallet
of 700's have been installed |
|
|
38
|
Tuesday, February 25, 2014, 15:00 |
Travis Cave | Shielding | Standard Operation | shields | Started on the removal of shields. |
|
|
39
|
Wednesday, February 26, 2014, 14:55 |
Travis Cave | Shielding | Standard Operation | shields | More shields have been removed from the
cyclotron only 16 remain. I was also noted
that the lift trolley is making an odd noise |
|
|
42
|
Tuesday, April 08, 2014, 10:45 |
Travis Cave | Shielding | Standard Operation | Large shield door on the RH B2 level | The large shield door on the RH B2 level
of the remote handling building has been
shut. |
|
|
63
|
Thursday, March 19, 2015, 13:14 |
maicodallavalle | Shielding | Standard Operation | Remote Handling B2 level Shielding door | The Remote Handling B2 level Shielding
door has been closed. |
|
|
78
|
Friday, February 05, 2016, 14:55 |
Travis Cave | Shielding | Standard Operation | shadow shields | all 200, 400, 500, 600, and some 700 series
of shield are in. |
|
|
97
|
Tuesday, March 07, 2017, 09:31 |
Jason Kapalka | Shielding | Standard Operation | Blockers/Shields/Covers/Ladders | The seven copper blockers were removed from
the Cyclotron tank by the RH group using
the service bridge, lift
|
|
|
126
|
Wednesday, January 13, 2021, 11:35 |
Adam Newsome | Shielding | Maintenance | Shadow Shields Inspection - 2021 Shutdown | All shadow shields which are remotely placed
inside the cyclotron during shutdown were
inspected by Adam Newsome and Chris Peterson |
|
|
136
|
Wednesday, January 19, 2022, 09:50 |
Travis Cave | Shielding | Standard Operation | Shield door is now open | The shield door is now open on the
RH B2 level. |
|
|
2
|
Tuesday, February 07, 2012, 18:09 |
Grant Minor | Service Bridge | Repair | Service Bridge Center Post Bearing Maintenance and Orbit Counter (2011/2012) | Repair
of Orbit Limit Switch Plastic Belt
During |
|
|
6
|
Thursday, October 25, 2012, 13:58 |
maicodallavalle | Service Bridge | Maintenance | Orbit Drive | It was observed during the last time the
Cyclotron service bridge was used the orbit
drive chain had a lot of slack. The drive |
|
|
9
|
Monday, February 04, 2013, 13:52 |
Grant Minor | Service Bridge | Repair | Hydraulic cylinder failure on service bridge | The hydraulic cylinder on the West side
of the service bridge (used to raise the
bridge for insertion into the Cyclotron) |
6x |
|
13
|
Wednesday, February 13, 2013, 08:55 |
maicodallavalle | Service Bridge | Repair | Service Bridge/Carrier Hydraulic Jacks | On Monday February 4TH the Service
Bridge was being lifted into the Cyclotron
with the Carrier. It was noticed that one |
|
|
24
|
Monday, September 30, 2013, 14:02 |
Travis Cave | Service Bridge | Maintenance | new festooning | The festooning and bearings for the festooning
cars for both outriggers has been replaced
and it is in working order. |
|