ID Date Author Categorydown Type Subject Text Attachments
  141   Wednesday, May 04, 2022, 12:07 Adam NewsomeTrolleyDevelopmentTool Trolley: Brass air fittings replacement completeAll of the old brass air fittings on the
Tool Trolley have now been swapped over to
push-connect style fittings. As these are
  
  155   Thursday, August 03, 2023, 10:43 Adam NewsomeTrolleyDevelopmentPrevious generation video trolley decommissionedThe "old" video trolley featuring
scissor mechanism and DSLR camera has officially
been decommissioned. Going forward, Video
  
  157   Thursday, September 14, 2023, 13:51 Adam NewsomeTrolleyMaintenanceLift Trolley: upgrades to camera tilt mechanismThe two camera tilt mechanisms on the lift
trolley have been upgraded. Upgrades include:
For the individual camera:
 PXL_20230914_193143524.jpg 
  158   Friday, September 15, 2023, 10:15 Adam NewsomeTrolleyMaintenanceLift Trolley: mirror actuation mechanism repair/upgradeThe mirror actuation mechanism was observed
to be "sticky" during 2023 winter
shutdown - it occasionally did not function
 PXL_20230915_164811247.jpg 
  168   Friday, February 16, 2024, 11:11 Adam NewsomeTrolleyRepairLift Trolley: vertical motion failure, motor relays replacedToday (2024-02-16) when operating the lift
trolley to install shields in the cyclotron,
the vertical motion was observed to be intermittently
  
  30   Monday, January 27, 2014, 14:42 Travis CaveShieldingStandard Operationshields and radiation survey The cyclotron radiation survey was aborted
due to the orbit not working recording the
numbers correctly. One shield has been in
 Meeting_Orbital_Counter_Problem_Jan_2014.pdf 
  31   Tuesday, January 28, 2014, 14:59 Travis CaveShieldingStandard Operationshields 200's, 400's, 500's, 600's, and a pallet
of 700's have been installed
  
  38   Tuesday, February 25, 2014, 15:00 Travis CaveShieldingStandard OperationshieldsStarted on the removal of shields.   
  39   Wednesday, February 26, 2014, 14:55 Travis CaveShieldingStandard OperationshieldsMore shields have been removed from the
cyclotron only 16 remain. I was also noted
that the lift trolley is making an odd noise
  
  42   Tuesday, April 08, 2014, 10:45 Travis CaveShieldingStandard OperationLarge shield door on the RH B2 levelThe large shield door on the RH B2 level
of the remote handling building has been
shut.
  
  63   Thursday, March 19, 2015, 13:14 maicodallavalleShieldingStandard OperationRemote Handling B2 level Shielding doorThe Remote Handling B2 level Shielding
door has been closed.
  
  78   Friday, February 05, 2016, 14:55 Travis CaveShieldingStandard Operationshadow shieldsall 200, 400, 500, 600, and some 700 series
of shield are in.
  
  97   Tuesday, March 07, 2017, 09:31 Jason KapalkaShieldingStandard OperationBlockers/Shields/Covers/LaddersThe seven copper blockers were removed from
the Cyclotron tank by the RH group using
the service bridge, lift 
 Checklist_for_Cyclotron_Shields_and_Blocks_and_Porthole_Covers_(Rev4_As_Run_2017).pdf 
  126   Wednesday, January 13, 2021, 11:35 Adam NewsomeShieldingMaintenanceShadow Shields Inspection - 2021 ShutdownAll shadow shields which are remotely placed
inside the cyclotron during shutdown were
inspected by Adam Newsome and Chris Peterson
  
  136   Wednesday, January 19, 2022, 09:50 Travis CaveShieldingStandard OperationShield door is now open The shield door is now open on the
RH B2 level.
  
  2   Tuesday, February 07, 2012, 18:09 Grant MinorService BridgeRepairService Bridge Center Post Bearing Maintenance and Orbit Counter (2011/2012)Repair
of Orbit Limit Switch Plastic Belt
During
 Stripped_Orbit_Limit_Belt_Sept_23_2011.JPGBridge_Belt_Repair_Fall_2011.JPGOrbit_Counter_Wheel_Just_Before_Skip_Point.JPGD7900_detail_Feb_7_2012.JPGCyclotron_Orbit_Counter_Wheel_emails_Mar-Sep_2011.pdf 
  6   Thursday, October 25, 2012, 13:58 maicodallavalleService BridgeMaintenanceOrbit DriveIt was observed during the last time the
Cyclotron service bridge was used the orbit
drive chain had a lot of slack. The drive
  
  9   Monday, February 04, 2013, 13:52 Grant MinorService BridgeRepairHydraulic cylinder failure on service bridgeThe hydraulic cylinder on the West side
of the service bridge (used to raise the
bridge for insertion into the Cyclotron)
 6x 
  13   Wednesday, February 13, 2013, 08:55 maicodallavalleService BridgeRepairService Bridge/Carrier Hydraulic JacksOn Monday February 4TH  the Service
Bridge was being lifted into  the Cyclotron
with the Carrier. It was noticed that one
 Hydraulic_Jack_RC-254.pdf 
  24   Monday, September 30, 2013, 14:02 Travis CaveService BridgeMaintenancenew festooningThe festooning and bearings for the festooning
cars for both outriggers has been replaced
and it is in working order.
  