Entry  Wednesday, June 16, 2021, 09:59, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 1 of 2) - Complete PXL_20210519_210527283_-_Copy.jpgPXL_20210216_175228151_-_cylinder_air_tubing_replaced.jpgPXL_20210615_171909579.jpg
The following items from Phase 1 of 2 of Bridge Lift Mechanism Refurbishment (O504) are complete:

    Replacement of pneumatic tubing
    Replacement of hydraulic cylinders for lifting, and procurement of spare

The
newly refurbished system has been tested by Dan McDonald (June 16, 2021) and verified as functioning.
Entry  Tuesday, April 03, 2018, 11:57, Travis Cave, Cyclotron, Standard Operation, Blue Shield Door Shut. 
 The Blue Shield Door on the B2 level of the RH building has been closed.
Entry  Tuesday, March 07, 2017, 09:31, Jason Kapalka, Shielding, Standard Operation, Blockers/Shields/Covers/Ladders Checklist_for_Cyclotron_Shields_and_Blocks_and_Porthole_Covers_(Rev4_As_Run_2017).pdf
The seven copper blockers were removed from the Cyclotron tank by the RH group using the service bridge, lift 
trolley, and attached checklist on 2017-01-30.
Entry  Monday, March 11, 2013, 19:43, Grant Minor, Cyclotron, Repair, Adjustment of tank lid upper limit by 1/4" upwards cyclotron_upper_limit_station_10_before_adjustment_11Mar2013_002.jpgcyclotron_upper_limit_station_10_after_adjustment_11Mar2013_004.jpgcyclotron_upper_limit_station_1_before_adjustment_11Mar2013_005.jpgcyclotron_upper_limit_station_1_after_adjustment_11Mar2013_006.jpgcyclotron_upper_limit_lamp_on_11Mar2013_008.jpg
This morning Don Jackson commented to Grant Minor that he believed the tank lid was still not raised high enough to safely operate the Remote Handling
bridge and trolleys, despite it having been raised 0.5" yesterday to the point of engaging the limit switches (see e-log from yesterday).  Don
said he believed this to be the case as a result of a visual inspection with binoculars from the outside of the tank, as well as from the views achievable
Entry  Saturday, April 04, 2020, 10:03, Dan McDonald, Trolley, Development, Addition of DC motor controller mounts 
Upper and lower resonator trolleys received mounting plates and brackets to accommodate DC motor controls for updated drive motors.
Entry  Friday, January 31, 2014, 10:07, Travis Cave, Cyclotron, Standard Operation, 2C removal 
2C has been successfully removed from the cyclotron and is now currently sitting in the B2 level of the RH building. A tank access was needed to feel
the stuck QDL.
Entry  Wednesday, February 04, 2015, 13:57, Travis Cave, Cyclotron, Standard Operation, 2C removal 
2C has been removed from the cyclotron.
Entry  Friday, February 07, 2014, 10:50, Travis Cave, Cyclotron, Standard Operation, 2C install 
2C has been installed into the cyclotron.
Entry  Tuesday, February 28, 2017, 15:45, Jason Kapalka, Cyclotron, Standard Operation, 2C extraction probe removal and reinstallation 
2C extraction probe was removed from cyclotron tank on 2017-02-07 by RH and Probes group members with service 
bridge, upper resonator trolley, and 2C attachment. Three QDLs were disengaged remotely, while one had to be 
disengaged locally in the tank (just like in 2013, 2014, 2015, and 2016).
Entry  Tuesday, February 14, 2012, 15:40, Grant Minor, Trolley, Standard Operation, 2C Removal - all 4 QDLs were actuated remotely this year! 2C_probe_Feb_14_2012_labelled.JPG2C_probe_solenoid_5_Feb_14_2012_labelled.JPG
Today Remote Handling staff (Maico Dalla Valle, Travis Cave) used the Remote Handling 2C probe removal trolley to remove the probe assembly from inside
the Cyclotron.  This is a regular yearly MRO task that is done every shutdown.
This task involves lining up the 2C trolley on the service bridge with the 2C probe assembly remotely with cameras, using a set of alignment markings
Entry  Tuesday, February 17, 2015, 11:28, Travis Cave, Cyclotron, Standard Operation, 2C Installation 
2C extraction probe has been re-installed in the cyclotron. After some problems on the first install attempt, do to a busted micro-switch that was causing
the 24 Volt DC system to short out.
Entry  Monday, February 06, 2017, 20:32, Jason Kapalka, Elevation Jack, Maintenance, 2017 Cyclotron Elevating System Maintenance  Cyclotron_Elevation_Maintenance_Rotation_Record_20170829.xlsx
The Cyclotron Elevating System planned maintenance work this year was performed on Jack Station #3, #8, #9, and #10.

Start date: January 10, 2017
Entry  Wednesday, January 27, 2016, 10:51, maicodallavalle, Elevation Jack, Maintenance, 2016 Cyclotron Elevation System Maintenance  
The Cyclotron Elevating System Shut Down  work done this year was done on Station #9 and Station #10.
 
 Work done on Station #9
Entry  Friday, January 23, 2015, 10:27, maicodallavalle, Elevation Jack, Maintenance, 2015 Jack Maintenance - Stations #4 and Station #9 
The Cyclotron Elevating System Shut Down  work done this year was done on Station #4 and Station #9.
 
 Work done on Station #4
Entry  Tuesday, September 25, 2012, 08:57, maicodallavalle, Elevation Jack, Maintenance, 2012 Service Maintance of #4 Station Jacking System  
Shut down work for 2012.Replaced serviced Jacking Station #6. Tapered alignment pins were damaged. They were skimmed and checked and installed. Station
#4 was removed and the spare Station was put in its place.Station # 4 Upper Bearing was inspected and serviced.Station #4 had a problem with the Jack on
the right side.The coupling hub than joins the Jack to the High Field was installed backwards.(Not sure how long the hub has been like this maybe 15-20
Entry  Tuesday, January 28, 2025, 12:31, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation - 2025 Elevation_System_Checklist_-_2025.xlsxLid_Up_2025_Thermal_Imaging.pdf
The lid up operation took place on Jan. 28, 2025 under work permit  C2025-01-28-1
 
Entry  Friday, March 21, 2025, 11:13, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2025 Elevation_System_Checklist_-_2025.xlsxLid_Down_2025-03-21_Thermal_Imaging_Report.pdf
The lid down operation took place on March 21, 2025 [slightly ahead of schedule].

Entry  Tuesday, May 07, 2024, 09:35, Adam Newsome, Elevation Jack, Standard Operation, Lid down operation (third) - 2024  Motor_Contactor_6_-_2024.PNGElevation_System_Checklist_-_2024_Lid_down_-_third.pdf
A third lid down operation took place over May 6-7, 2024. 

The  system was energized a few minutes ahead of time.
Entry  Thursday, February 02, 2023, 07:05, maicodallavalle, Service Bridge, Repair, Hinged Festoon Rail at Cyclotron  
The Hinged section of the festoon rail at Cyclotron has a piston to keep rail in the up position for shutdown work (Bridge and Trolley in tank work).
A plastic liner for the piston has fallen apart and needs to be replace.
A spare one has been temporarily put into  place until another one has been machined and reinstalled. 
Entry  Wednesday, October 16, 2024, 11:37, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 2 of 2) - Complete  6x
See previous e-log for phase 1: e-log 134
 
Phase 2 of the bridge lift mechanism refurbishment was completed. The scope of work for this phase includes replacement of the hydraulic pump (including