  ID Date Author Category Type Subjectdown Text Attachments
  86   Friday, February 05, 2016, 08:48 Keith C NgPrimary BeamlinesMaintenance4VVR1 RemovalReturned work permit C2016-01-27-2 due
to tank lid being raised and elevated fields
make the work area un-favourable to work
  
  91   Wednesday, March 16, 2016, 17:19 Ron KuramotoPrimary BeamlinesDevelopment4VQ3 Removal On 8March2016, under W/P C2016-03-08-2,
4VQ3 was lifted out of BL4V with the vault
orbit crane where it was first weighed then
 IMG_1893.JPGIMG_1893.JPGIMG_1899.JPGIMG_1902.JPGIMG_1907.JPG 
  92   Wednesday, March 16, 2016, 17:57 Ron KuramotoPrimary BeamlinesDevelopment4VQ1&Q2 Removal On 14March2016, 4VQ1&Q2 were
removed from BL4V and lowered into the Vault
basement B3 level where they were stored
 13x 
  88   Friday, February 19, 2016, 14:03 Keith C NgPrimary BeamlinesDevelopment4V CM1 blankingContinued with work blanking off CM1 flange.
- Placed lead shot on left and right
side of the CM1 flange to lower fields. No
 20160219_beamline4v_P1030499.JPG 
  89   Monday, February 22, 2016, 16:09 Keith C NgPrimary BeamlinesDevelopment4V CM1 blanking 
Rolled
indium into new blanking plate turned down
 20160222_beamline4v_P1030502.JPG20160222_beamline4v_P1030511.JPG20160222_beamline4v_P1030505.JPG20160223_4VCM1_blank_off_inspection_report.pdf 
  130   Friday, May 06, 2022, 11:27 Keith C NgPrimary BeamlinesStandard Operation4V CM1 RH joint install 2022 Apr 28 to 29:
Installed a new remote handling 4"
indium joint for new beamline 4 north section.
 2022_4v_cm1_rh_joint_install.pdf 
  6   Thursday, March 01, 2012, 16:01 Keith C NgPrimary BeamlinesRepair2C Rad Hard Valve Replacement4" indium flanges at the 2C rad hard
valve were cleaned of the remaining indium
by C. Ballard. Both upstream and down stream
  
  111   Wednesday, February 14, 2018, 10:36 Keith C NgPrimary BeamlinesRepair1a q12 q13Uncovered and placed bridges for 1a q12
q13 for doug's re cabling work. See WP C2018-02-13-2:
work
 P1030907.JPG 
  60   Friday, January 23, 2015, 15:21 Keith C NgPrimary BeamlinesMaintenance1VQ4 joint section (WR #2686) 1VQ4 & 1VQ6 beamtube was installed
by UCN group. RH provisonally installed aluminum
indium carrier ring with no indium into joint
 20150123_ucnbuild_IMG_1197.JPG20150123_ucnbuild_IMG_1202.JPG20150123_ucnbuild_IMG_1205.JPG20150123_ucnbuild_IMG_1207.JPG20150123_ucnbuild_IMG_1209.JPG 
  59   Wednesday, January 14, 2015, 11:00 Keith C NgPrimary BeamlinesMaintenance1VQ4 & 1VQ6 beamtube removal (WR #2686)Disconnected and removed beam tube from
1VQ4, 5, 6.  
  
  93   Thursday, March 31, 2016, 15:32 Keith C NgPrimary BeamlinesDevelopment1VM3 to 1VQ4 joint.Re-installed indium vacuum joint for 1VQ4,
routing installation. R. Kuramoto sprayed
silicone grease on to the threads and bushings
  
  20   Monday, January 14, 2013, 16:36 Keith C NgPrimary BeamlinesMaintenance1AVA8 valve o ring replacementcontinued with o ring replacement, replaced
all relevant o ring seals on valve (valve
body seal and actuator arm dynamic seals).
  
  19   Friday, January 11, 2013, 15:44 Keith C NgPrimary BeamlinesMaintenance1AVA8 valve o ring replacementAssisted vacuum group with removing 1AVA8:
- uncovered valve area and set up
remote handling bridge over valve.
  
  21   Tuesday, January 15, 2013, 16:37 Keith C NgPrimary BeamlinesMaintenance1AVA8 valve o ring replacementJob completed today and shielding block
over valve restored.
- He leak checked valve and accessible
  
  74   Thursday, March 05, 2015, 08:42 Keith C NgPrimary BeamlinesRepair1AT1 area water leak fixes1) Quick connect fittings on the rotary
collimator were leaking (the two red collared
fittings in photo below).
 11x 
  107   Tuesday, January 23, 2018, 15:44 Keith C NgPrimary BeamlinesRepair1AQ15 insulator repairAssisted beamlines in replacing 2 insulators
on 1A Q15 magnet. #10 and #14 insulators
were found to be leaking at the ceramic,
 vlcsnap-00001.jpgvlcsnap-00002.jpg20180123_1aq15repair_P1030875.JPG20180123_1aq15repair_P1030880.JPG 
  119   Tuesday, April 16, 2019, 11:19 Ron KuramotoPrimary BeamlinesRepair1AQ14 B/L Flange Broken ThermocoupleOn March 7,2019 the Thermocouple (TC) cable
which monitors the temperature of the 1AQ14
B/L vacuum joint was broken when the iron
 1AQ14_FlgTC1_7Mar2019.jpeg1AQ14_FlgTC2__7Mar2019.jpeg1AQ14_FlgTC3_7Mar2019.jpeg 
  33   Tuesday, February 05, 2013, 16:12 Keith C NgPrimary BeamlinesMaintenance1A triplet repair (ground fault) (Completed)Today: D. Preddy completed another power
test on 1A Q14, 15, 16 after all iron/steel
shielding was restored. Magnet power and
  
  25   Wednesday, January 23, 2013, 15:51 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Continued work on finding ground fault
in 1A triplet magnets;
 
 20130123_tripletrepair_P1020666.JPG20130123_tripletrepair_P1020664.JPG20130123_tripletrepair_P1020669.JPG 
  26   Thursday, January 24, 2013, 17:05 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Continued with work on finding ground fault
on 1A triplet;
 
 20130124_tripletrepair_IMG_0047.JPG20130122_tripletrepair_IMG_0011.JPG20130124_tripletrepair_IMG_0040.JPG 