Friday, February 05, 2016, 08:48, Keith C Ng, Primary Beamlines, Maintenance, 4VVR1 Removal
|
Returned work permit C2016-01-27-2 due to tank lid being raised and elevated fields make the work area un-favourable to work in. Work will resume to
blank off the combination magnet flange when the tank lid is closed in March.
Tasks remaining: |
Wednesday, March 16, 2016, 17:19, Ron Kuramoto, Primary Beamlines, Development, 4VQ3 Removal
|
On 8March2016, under W/P C2016-03-08-2, 4VQ3 was lifted out of BL4V with the vault orbit crane where it was first weighed then lifted onto the
RH flat deck rail dolly. It was then moved into the RH basement where it was surveyed before lifting it up onto the Red wagon cart in the RH loading
bay. It was then pulled to the Meson Hall loading bay by fork lift where and then over the Cycloton vault to the top of the E-Hall roof beams under |
Wednesday, March 16, 2016, 17:57, Ron Kuramoto, Primary Beamlines, Development, 4VQ1&Q2 Removal 13x
|
On 14March2016, 4VQ1&Q2 were removed from BL4V and lowered into the Vault basement B3 level where they were stored in the south west corner
on their respective wood pallets. The hot ends of both magnets were place against the west wall. 4VQ2 was lifted out first and moved temporarily
downstream where it was separated from its magnet stand. Q2 was then craned into the basement where it was tipped 45o to lay on the flat side |
Friday, February 19, 2016, 14:03, Keith C Ng, Primary Beamlines, Development, 4V CM1 blanking
|
Continued with work blanking off CM1 flange.
- Placed lead shot on left and right side of the CM1 flange to lower fields. No significant change, went from 2.8 mSv to 1.9-2 mSv.
- Inspected indium flange, some residue on 3 and 9 (left and right) clock sides of knife flange. No significant indium stuck on, some small cleanup |
Monday, February 22, 2016, 16:09, Keith C Ng, Primary Beamlines, Development, 4V CM1 blanking
|
Rolled indium into new blanking plate turned down to 5.550". Dry fit with no indium
ok. Assembled hook eyes from the previous blank off plate (removed from the slits box?). Used the same 20.5 mm spring compression (1.5 turns of the nut |
Friday, May 06, 2022, 11:27, Keith C Ng, Primary Beamlines, Standard Operation, 4V CM1 RH joint install
|
2022 Apr 28 to 29:
Installed a new remote handling 4" indium joint for new beamline 4 north section. Issues were encountered in clearance between the downstream
steering magnet and the compression collar of the joint. Joint installation itself went smoothly. |
Thursday, March 01, 2012, 16:01, Keith C Ng, Primary Beamlines, Repair, 2C Rad Hard Valve Replacement
|
4" indium flanges at the 2C rad hard valve were cleaned of the remaining indium by C. Ballard. Both upstream and down stream flanges were done,
ready for installation of new valve. |
Wednesday, February 14, 2018, 10:36, Keith C Ng, Primary Beamlines, Repair, 1a q12 q13
|
Uncovered and placed bridges for 1a q12 q13 for doug's re cabling work. See WP C2018-02-13-2: work
permit |
Friday, January 23, 2015, 15:21, Keith C Ng, Primary Beamlines, Maintenance, 1VQ4 joint section (WR #2686)
|
1VQ4 & 1VQ6 beamtube was installed by UCN group. RH provisonally installed aluminum indium carrier ring with no indium into joint space with clamping
collar and pin drive. Joint is currently connected but not vacuum tight. Joint will be sealed with indium at a later date, tbd.
|
Wednesday, January 14, 2015, 11:00, Keith C Ng, Primary Beamlines, Maintenance, 1VQ4 & 1VQ6 beamtube removal (WR #2686)
|
Disconnected and removed beam tube from 1VQ4, 5, 6.
- Q6 end had transition end removed with pin drive driven into the retracted position and left behind but indium joint was still intact. |
Thursday, March 31, 2016, 15:32, Keith C Ng, Primary Beamlines, Development, 1VM3 to 1VQ4 joint.
|
Re-installed indium vacuum joint for 1VQ4, routing installation. R. Kuramoto sprayed silicone grease on to the threads and bushings on pin drive. Drove
down tapererd pins and stopped 1/16" short of old marker markings. RK. Commented on the drive screw bending under load, reversed drive 1/2 turn
to relieve the stress on the screw. |
Monday, January 14, 2013, 16:36, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement
|
continued with o ring replacement, replaced all relevant o ring seals on valve (valve body seal and actuator arm dynamic seals).
- valve re installed and services reconnected.
- valve cycled and checked; valve, limit switches ok. |
Friday, January 11, 2013, 15:44, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement
|
Assisted vacuum group with removing 1AVA8:
- uncovered valve area and set up remote handling bridge over valve.
- shut off pneumatic supply to valve to render valve in mid position (shut off valve in 1A tunnel). disconnected electrical services and air supply |
Tuesday, January 15, 2013, 16:37, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement
|
Job completed today and shielding block over valve restored.
- He leak checked valve and accessible up stream joints, no leaks found.
- J McKinnon checked power supplies for nearby steering magnets before and after covering valve. supplies working ok. |
Thursday, March 05, 2015, 08:42, Keith C Ng, Primary Beamlines, Repair, 1AT1 area water leak fixes 11x
|
1) Quick connect fittings on the rotary collimator were leaking (the two red collared fittings in photo below).
|
Tuesday, January 23, 2018, 15:44, Keith C Ng, Primary Beamlines, Repair, 1AQ15 insulator repair
|
Assisted beamlines in replacing 2 insulators on 1A Q15 magnet. #10 and #14 insulators were found to be leaking at the ceramic, where the stainless steel
fitting joins the insulator. They were both replaced. During re-installation of the #10 ceramic, the VCR coil termination broke off the coil end and a
new one with updated design (see TBP0379) had to be soldered back in its place. The original SS fittings are deemed to have problems in their construction |
Tuesday, April 16, 2019, 11:19, Ron Kuramoto, Primary Beamlines, Repair, 1AQ14 B/L Flange Broken Thermocouple
|
On March 7,2019 the Thermocouple (TC) cable which monitors the temperature of the 1AQ14 B/L vacuum joint was broken when the iron shield block (Triumf Dwg
D-3237 aka M8 Tongue block) was restored on the east of the T2 Monolyth. See attached photos. This TC (Omega #KTSS-116U-144) is attached to the 1AQ14
Indium ring seal (Triumf Ref Dwg TBP0372D) and should be replaced the next time this B/L joint is serviced.
The Controls Group has noted on the CCSC2, |
Tuesday, February 05, 2013, 16:12, Keith C Ng, Primary Beamlines, Maintenance, 1A triplet repair (ground fault) (Completed)
|
Today: D. Preddy completed another power test on 1A Q14, 15, 16 after all iron/steel shielding was restored. Magnet power and steering supplies were
checked and O.K.ed. R. Kuramoto deems triplet repair job completed.
|
Wednesday, January 23, 2013, 15:51, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault)
|
Continued work on finding ground fault in 1A triplet magnets;
D. Preddy connected ohmeters to 1AQ14 & 15 power supplies with power leads disconnected. Ohmmeters were connected from magnet power leads to |
Thursday, January 24, 2013, 17:05, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault)
|
Continued with work on finding ground fault on 1A triplet;
Uncovered Q15 & 16 to 1AS1 area. See photo below for setup. |
|