  RH-ARIEL, Page 5 of 5  Not logged in ELOG logo
  ID Date Author Category Type Subject Text Attachments
  8   Friday, December 05, 2014, 10:43 Isaac Earle100KW Beam DumpDevelopmentLower Lead Shield Drain Line InstalledA 1/8" SS tube was routed from the
Swagelok fitting on the front of the lower
lead shield to the service stand water catch
 IMG_4383.JPGIMG_4384.JPGIMG_4385.JPG 
  7   Wednesday, December 03, 2014, 10:45 Isaac Earle100KW Beam DumpDevelopmentBD Signals Traced from Service Stand to Junction BoxOn Dec 2 the cables from the BD service
stand area to the junction box were traced
to establish which sensors correspond to
  
  6   Wednesday, December 03, 2014, 10:36 Isaac Earle100KW Beam DumpDevelopmentUpper half of BD water blocks installed; Bypass loops installedOn December 2 the upper half of the RH
water blocks were installed (4 total) using
a 0.030" thick 6061-T6 Al shim torqued
 IMG_4381.JPG 
  5   Wednesday, December 03, 2014, 10:16 Isaac Earle100KW Beam DumpDevelopmentInstallation of Lower Lead Block and Beam Dump InsertOn November 28th the lower lead shield
was installed with 3/8" shimming at
the front end, and 11/32" shimming at
  
  4   Wednesday, November 26, 2014, 17:50 Isaac Earle100KW Beam DumpDevelopmentInstallation of Lower Center Block (TSH0461)Painting and relabeling of the modified
lower center block (TSH0461) was completed
on Monday Nov 24.  
 Beam_Dump_Lower_Center_Block_Alignment_-_Nov_25_2014_(from_Darren_Blom).txtIMG_1110.JPGIMG_1125.JPGIMG_4297.JPGIMG_4303.JPG 
  3   Friday, November 21, 2014, 13:37 Isaac Earle100KW Beam DumpDevelopmentDestructive Testing of 1" MDC Ceramic BreaksTesting was performed on the ceramic water
breaks to be used on the beam dump water
hose assemblies.  The ceramic breaks
 Ceramic_Water_Break_Test_#1.docxCeramic_Water_Break_Test_#2.docxTest_#1_Broken_Sample.JPGTest_#2_Broken_Sample.JPG 
  2   Wednesday, November 19, 2014, 13:49 Isaac Earle100KW Beam DumpDevelopmentDecision on Modifications to Lower Center Block (TSH0225)I received a call today from Jim Adamson
at Kaltech regarding modifications to shielding
block TSH0225.
  
  1   Tuesday, November 04, 2014, 16:58 John Wong100KW Beam DumpMaintenanceTesting ElogTuesday, November 04, 2014, 16:58
This is a test.

 
  