22
|
Wednesday, June 10, 2015, 14:57 |
Isaac Earle | 100KW Beam Dump | Development | BD Water System Leak Test | A leak test was performed on the beam dump
water system on June 9 in the afternoon.
- Pipe segments tested: The entire |
|
21
|
Monday, June 08, 2015, 15:23 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Seal Re-Install | On Monday June 8 the following work
was performed by Isaac Earle and Keith Ng:
- EHDT beamline vented |
|
20
|
Monday, June 08, 2015, 15:15 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Vacuum Leak | - On Thurdsay June 4th the EHDT beamline
section was vented by Vacuum Group so that
they could install a new pump |
|
19
|
Tuesday, June 02, 2015, 16:42 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Water Block RH Test & Installation | Beam dump waterblocks #1 (BD
Inlet) and #3 (Upper Pb Inlet) were removed |
|
18
|
Thursday, May 28, 2015, 16:08 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Vac Seal RH Test & Installation | The following work was performed on
May 27 & 28, 2015:
- The beam dump 10kW Remote Handling |
|
17
|
Friday, May 15, 2015, 11:06 |
Isaac Earle | 100KW Beam Dump | Development | BD and Upper Pb Shield Water Hoses Replaced | The beam dump and upper lead shield
flexible hose assemblies have been replaced
with smaller diameter versions to allow for |
|
16
|
Thursday, May 07, 2015, 16:23 |
Isaac Earle | 100KW Beam Dump | Development | RH Clamp Installed with Used Seal | The remote handling 4" marman flange
clamp was reinstalled today with a used seal.
It is "Clamp B" as tested |
|
15
|
Wednesday, May 06, 2015, 14:19 |
Isaac Earle | 100KW Beam Dump | Development | EHDT Beam Pipe Section Installed | - On May 4th the EHDT beam pipe section
was installed by Mike Vogel of Beamlines
Group |
|
14
|
Friday, April 17, 2015, 14:37 |
Isaac Earle | 100KW Beam Dump | Development | RH Clamp Delivered to Beamlines Group | A 4" Remote Handling Marman
Flange Clamp was delivered to Doug Preddy
today to be used to clamp the EHDT beam pipe |
|
13
|
Friday, March 20, 2015, 11:45 |
Isaac Earle | 100KW Beam Dump | Development | Lower Half of BD EHDT Shielding Installed | The lower half of the beam dump EHDT
shielding was installed yesterday by Plant
Group. After installation of the service |
|
12
|
Friday, February 06, 2015, 13:32 |
Isaac Earle | 100KW Beam Dump | Development | TEL5079 Hose Modification | When the EHDT shielding service stand shield
plug was installed in January it was found
that the Beam Dump Outlet Hose (TEL5079) |
|
11
|
Monday, December 22, 2014, 14:21 |
Isaac Earle | 100KW Beam Dump | Development | Water System Leak Checked | This morning Bill Richert pressurized the
beam dump water cooling system with 30psi
air and held for 2 hours. He reported |
|
10
|
Friday, December 19, 2014, 14:05 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump & Lead Shielding Design Documentation | As there likely won't be an opportunity
to properly document the design of the beam
dump insert and cooled lead shielding in |
|
9
|
Tuesday, December 16, 2014, 16:36 |
Isaac Earle | 100KW Beam Dump | Development | Upper Pb Shield and Water Hoses Installed | The upper lead shield was installed
this morning. Also the water hoses
for lower lead shield, beam dump, and upper |
|
8
|
Friday, December 05, 2014, 10:43 |
Isaac Earle | 100KW Beam Dump | Development | Lower Lead Shield Drain Line Installed | A 1/8" SS tube was routed from the
Swagelok fitting on the front of the lower
lead shield to the service stand water catch |
|
7
|
Wednesday, December 03, 2014, 10:45 |
Isaac Earle | 100KW Beam Dump | Development | BD Signals Traced from Service Stand to Junction Box | On Dec 2 the cables from the BD service
stand area to the junction box were traced
to establish which sensors correspond to |
|
6
|
Wednesday, December 03, 2014, 10:36 |
Isaac Earle | 100KW Beam Dump | Development | Upper half of BD water blocks installed; Bypass loops installed | On December 2 the upper half of the RH
water blocks were installed (4 total) using
a 0.030" thick 6061-T6 Al shim torqued |
|
5
|
Wednesday, December 03, 2014, 10:16 |
Isaac Earle | 100KW Beam Dump | Development | Installation of Lower Lead Block and Beam Dump Insert | On November 28th the lower lead shield
was installed with 3/8" shimming at
the front end, and 11/32" shimming at |
|
4
|
Wednesday, November 26, 2014, 17:50 |
Isaac Earle | 100KW Beam Dump | Development | Installation of Lower Center Block (TSH0461) | Painting and relabeling of the modified
lower center block (TSH0461) was completed
on Monday Nov 24. |
|
3
|
Friday, November 21, 2014, 13:37 |
Isaac Earle | 100KW Beam Dump | Development | Destructive Testing of 1" MDC Ceramic Breaks | Testing was performed on the ceramic water
breaks to be used on the beam dump water
hose assemblies. The ceramic breaks |
|