Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ARIEL, Page 4 of 5  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Wednesday, June 10, 2015, 14:57, Isaac Earle, 100KW Beam Dump, Development, BD Water System Leak Test 
A leak test was performed on the beam dump water system on June 9 in the afternoon.
- Pipe segments tested: The entire HAW system except for the expansion tank, air separator and HAW pump
- Test medium: air
Entry  Monday, June 08, 2015, 15:23, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Seal Re-Install 
 On Monday June 8 the following work was performed by Isaac Earle and Keith Ng:
- EHDT beamline vented
- Band clamp and o-ring seal removed
Entry  Monday, June 08, 2015, 15:15, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Vacuum Leak BD_Flanges_and_Clamp_Jaws_Dimension_Check_-_Keith_Ng_-_June_5_2015.pdf
- On Thurdsay June 4th the EHDT beamline section was vented by Vacuum Group so that they could install a new pump
- After pumping down again a leak was found at the BD front flange seal around the top of the seal
- The RH clamp and Helicoflex seal were removed and an o-ring seal was installed with a band clamp
Entry  Tuesday, June 02, 2015, 16:42, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Water Block RH Test & Installation BD_Water_Block_RH_Test_Procedure_-_June_2_2015.docx
Beam dump waterblocks #1 (BD Inlet) and #3 (Upper Pb Inlet) were removed as per the attached procedure
on June 1-2.  The following was noted:
- The RH pole tool (TRH1244) and water tool wrench (TRH1243) fit easily over all four water block
Entry  Thursday, May 28, 2015, 16:08, Isaac Earle, 100KW Beam Dump, Development, Beam Dump Vac Seal RH Test & Installation BD_Vac_Flange_RH_Test_Procedure_-_June_2_2015.docx
The following work was performed on May 27 & 28, 2015:
- The beam dump 10kW Remote Handling setup was arranged as shown in the attached procedure
- The EHDT split ring clamp was found to be installed too far downstream and the pole tool could not be installed properly;  the position
Entry  Friday, May 15, 2015, 11:06, Isaac Earle, 100KW Beam Dump, Development, BD and Upper Pb Shield Water Hoses Replaced 
 The beam dump and upper lead shield flexible hose assemblies have been replaced with smaller diameter versions to allow for easier remote handling.
 The new beam dump hoses are TEL5501 (Rev A) & TEL5502 (Rev A).  The new upper lead hoses are TEL5503 (Rev B) and TEL5504 (Rev B).  All
Swagelok joints were installed 1-1/4 turns past finger tight as per Swagelok instructions.  The new Swagelok connections have not been leak tested
Entry  Thursday, May 07, 2015, 16:23, Isaac Earle, 100KW Beam Dump, Development, RH Clamp Installed with Used Seal 
The remote handling 4" marman flange clamp was reinstalled today with a used seal.  It is "Clamp B" as tested in Document-114623.
 The purpose of installing the clamp now is to prepare for the upcoming remote handling test of the vacuum joint and one of the water blocks.
During installation it was found that it will be necessary to manipulate both the BD flange and the EHDT beam pipe flange to have the seal mated
Entry  Wednesday, May 06, 2015, 14:19, Isaac Earle, 100KW Beam Dump, Development, EHDT Beam Pipe Section Installed IMG_4922.JPGIMG_4924.JPGIMG_4925.JPG
- On May 4th the EHDT beam pipe section was installed by Mike Vogel of Beamlines Group
- A new Helicoflex seal was used (provided by Vacuum Group)
- 4" RH Clamp was installed by Isaac Earle.  Clamp became stiff in early travel, was backed off, then fully tighetend down to stop-ring
Entry  Friday, April 17, 2015, 14:37, Isaac Earle, 100KW Beam Dump, Development, RH Clamp Delivered to Beamlines Group 
 A 4" Remote Handling Marman Flange Clamp was delivered to Doug Preddy today to be used to clamp the EHDT beam pipe section to the beam dump
during beam pipe installation.
The clamp is one of the two manufactured in 2014, Identified with marker "B"
Entry  Friday, March 20, 2015, 11:45, Isaac Earle, 100KW Beam Dump, Development, Lower Half of BD EHDT Shielding Installed IMG_4791.JPGIMG_4792.JPGIMG_4795.JPGBL_Group_Alignment_Report_-_steel_plug_for_beam_dump.pdfBL_Group_Alignment_Report_-_steel_shielding_block_for_beam_dump.pdf
 The lower half of the beam dump EHDT shielding was installed yesterday by Plant Group.  After installation of the service stand plug, the
position of the south and east faces of the plug were checked with the laser tracker w.r.t. EHAT MB4.  The south face was within approximately 2mm
of nominal, and the east face was approximately 6mm east of nominal position.  It was decided that this positioning was acceptable.  The modified
Entry  Friday, February 06, 2015, 13:32, Isaac Earle, 100KW Beam Dump, Development, TEL5079 Hose Modification 
When the EHDT shielding service stand shield plug was installed in January it was found that the Beam Dump Outlet Hose (TEL5079) was interfering with
the plug.  The following remedial action was taken:
- Upper lead water blocks disconnected and upper lead shield removed w/ hose assemblies and upper half of water blocks attached
Entry  Monday, December 22, 2014, 14:21, Isaac Earle, 100KW Beam Dump, Development, Water System Leak Checked 
This morning Bill Richert pressurized the beam dump water cooling system with 30psi air and held for 2 hours.  He reported no change in pressure
which indicates the flexible hose connections installed last week are leak tight.
Entry  Friday, December 19, 2014, 14:05, Isaac Earle, 100KW Beam Dump, Development, Beam Dump & Lead Shielding Design Documentation Cooled_Lead_Shielding_Scanned_Design_Notes_(Isaac_Earle).pdf
 As there likely won't be an opportunity to properly document the design of the beam dump insert and cooled lead shielding in design notes, a list
of design reviews, released on Docushare is provided below.  These provide a reasonable overview of the design process for each item.  In addition
the attached PDF of scanned notes provides detailed information on the lead shielding design.  Further notes, ANSYS documents, meeting minutes, concept
Entry  Tuesday, December 16, 2014, 16:36, Isaac Earle, 100KW Beam Dump, Development, Upper Pb Shield and Water Hoses Installed BD_Hose_Install_Notes.pdfIMG_4407.JPGIMG_4408.JPGIMG_4410.JPG
 The upper lead shield was installed this morning.  Also the water hoses for lower lead shield, beam dump, and upper lead shield were all installed.
 See attached photos and hose installation information PDF.
Entry  Friday, December 05, 2014, 10:43, Isaac Earle, 100KW Beam Dump, Development, Lower Lead Shield Drain Line Installed IMG_4383.JPGIMG_4384.JPGIMG_4385.JPG
A 1/8" SS tube was routed from the Swagelok fitting on the front of the lower lead shield to the service stand water catch tray as shown in the
attached photos.
The tube was routed to fit in the cut-out and chamfered corner gaps of block TSH0387 in the de-rated EHDT shielding assembly TSH0293.
Entry  Wednesday, December 03, 2014, 10:45, Isaac Earle, 100KW Beam Dump, Development, BD Signals Traced from Service Stand to Junction Box 
On Dec 2 the cables from the BD service stand area to the junction box were traced to establish which sensors correspond to which cable number in the
junction box.
 
Entry  Wednesday, December 03, 2014, 10:36, Isaac Earle, 100KW Beam Dump, Development, Upper half of BD water blocks installed; Bypass loops installed IMG_4381.JPG
On December 2 the upper half of the RH water blocks were installed (4 total) using a 0.030" thick 6061-T6 Al shim torqued to 60ft*lbs as was tested
in Document-114260.
Bypass loops for testing the cooling system piping were installed as shown in the attached photo.
Entry  Wednesday, December 03, 2014, 10:16, Isaac Earle, 100KW Beam Dump, Development, Installation of Lower Lead Block and Beam Dump Insert 
On November 28th the lower lead shield was installed with 3/8" shimming at the front end, and 11/32" shimming at the rear end.  The south
and east faces were aligned as flush as possible with the lower center block.  The beam dump insert was then placed on the rails in the lower lead
shield.
Entry  Wednesday, November 26, 2014, 17:50, Isaac Earle, 100KW Beam Dump, Development, Installation of Lower Center Block (TSH0461) Beam_Dump_Lower_Center_Block_Alignment_-_Nov_25_2014_(from_Darren_Blom).txtIMG_1110.JPGIMG_1125.JPGIMG_4297.JPGIMG_4303.JPG
Painting and relabeling of the modified lower center block (TSH0461) was completed on Monday Nov 24.  The
height of the modified block was measured at the four corners using a tape measure and found to be approximately 533mm at all corners.
The block was lowered to the E-Hall and aligned on Tuesday Nov 25.   No cantilever lift was required because the catwalk above the hatch had
Entry  Friday, November 21, 2014, 13:37, Isaac Earle, 100KW Beam Dump, Development, Destructive Testing of 1" MDC Ceramic Breaks Ceramic_Water_Break_Test_#1.docxCeramic_Water_Break_Test_#2.docxTest_#1_Broken_Sample.JPGTest_#2_Broken_Sample.JPG
Testing was performed on the ceramic water breaks to be used on the beam dump water hose assemblies.  The ceramic breaks are a custom MDC product
with the following description:  3kV ceramic break, 1" OD tube 0.083" wall thickness, 2" length, 304SS tube stub each end, 250psi water
rating (see TRIUMF PO#  TR199315).
ELOG V2.9.2-2455