Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_2, Page 8 of 35  Not logged in ELOG logo
Entry  Saturday, July 25, 2020, 08:58, Darwin Ortiz Rosales, ZrC, 44139-7-SK, , In progress, ZrC for Luca's experiments 
Friday, July 24, 2020, 15:00
Ta tube cotaining 497 ZrC discs wrapped with Ta heat-shields (3 layers)
Desired temperature= 1800C (expected TGHT 410 A), TBHT will be set fixed at 230A (max).
Entry  Friday, October 09, 2020, 09:50, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, Tests, radiation gun for parasitic target 
 2020-10-09 9:48 The target was installed the day before and left pumping over night. IGP1=4.7e-7Torr. leak check when water on, ok. Setting ramp
up
 2020-10-09 10:16 Ramping up the target to 50A, 1.5A/30s. All good. Going to 200A same rate.
Entry  Tuesday, October 13, 2020, 11:15, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, foil heating 
 2020-10-13 11:13 Target was left under vacuum over the weekend. IGP1: 1.6e-7T water on- leak check ok. Ramping up 2A/30s to 100A.
 2020-10-13 11:47 All ok at 100A. Ramping up, 1A/10s to 200A.
 2020-10-13 12:08 All ok at 200A. Temp tc on foil 200degC. Ramping up, 1A/10s to 300A.
Entry  Thursday, October 15, 2020, 18:51, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, heat gun plus parasitic target thermal comissioning. 
 2020-10-15 18:51 : Setup installed during the day. Pumped down to IGP1:1.5e-5T , water leak check ok. Ramping up to 100A. 
 2020-10-15 19:30 : A heating element was showing bad signs and failed very early. ramping down and venting. 
Entry  Tuesday, October 27, 2020, 10:25, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, parasitic target commissioning 
 2020-10-27 10:24 setup introduced yesterday. Pumping over night IGP1: 5.7e-7T. Water leak check ok. Performing heating elements check.
 2020-10-27 10:43 Heating elements check show low cooling. Ramping up target 1A/15s to 200A.
 2020-10-27 11:54 all ok 200A, thermocouples show room temperature on cartridge and heat shield. Ramping up target 2A/10s to 300A.
Entry  Monday, November 02, 2020, 18:32, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, HEA heat treatment 20201104_102925.jpg20201104_144831.jpg
2020-11-02 6:32: roughing on
2020-11-02 7:21: Turbo on for a while, IGP1:1.8e-5T . water leak check ok.
2020-11-02 7:47: IGP1:1e-5T . Ramping up target heater to 200A, 1A/10s.
Entry  Thursday, April 15, 2021, 18:33, Marla Cervantes, Ta, 44139-6-SK, TARGET BOAT, Done, Carbon penetration on Ta Ta-samples_heating.JPG
Thursday, April 15, 2021, 18:24
Tantalum samples were loaded in a tantalum testing tube and installed in the EVAP2 to heat under vacuum for 3 days at 2000 degC (~500A, 4kW).
The temperature is measured with the Omega pyrometer (slope 0.98)
    Reply  Thursday, August 08, 2024, 11:17, Marla Cervantes, C, 44139-5 SK, LP TUBE, Done, Graphite foils conditioning GraphiteFoil-Conditioning-EVAP2.JPG


    
        
            Aaron Schmidt wrote:
        
        
            
            Wednesday, August 07, 2024, 15:36: Roughing. Had initially been roughed & TP started w/ Marla CS,
Entry  Wednesday, August 14, 2024, 07:23, Marla Cervantes, C, 44139-5 SK, LP TUBE, Problems, EVAP2 Calibration - Vanadium  TP-not_speeding_up.JPG
Tuesday, August 13, 2024, 17:20 Pressure kept increasing when turning the turbo pump on 
Tuesday, August 13, 2024, 18:00 Pressure stayed constant when turning the turbo pump on
    Reply  Wednesday, August 14, 2024, 16:22, Marla Cervantes, C, 44139-5 SK, LP TUBE, Problems resolved, EVAP2 Calibration - Vanadium  


    
        
            Marla Cervantes wrote:
        
        
            
            Tuesday, August 13, 2024, 17:20 Pressure kept increasing when turning the turbo pump on
    Reply  Wednesday, August 14, 2024, 16:24, Marla Cervantes, C, 44139-5 SK, LP TUBE, In progress, EVAP2 Calibration - Vanadium  
 
 


    
        

           Marla Cervantes wrote:
        
        

           
            
            
Entry  Monday, November 07, 2022, 14:26, Darwin Ortiz Rosales, TaC, 44139-4, TARGET BOAT, Done, TaC coating sintering 
Monday, November 07, 2022, 14:24
The coated container tube was wrapped in four Ta foil heatshields.
Target temperature on OMEGA= 1850-1900 C
Entry  Wednesday, May 24, 2023, 15:23, Darwin Ortiz Rosales, , 44139-4, LP TUBE, Done, Graphite inside insert Experiment 1 Screenshot_Graphite_insert_Exp1.png
 
Wednesday, May 24, 2023, 15:22
A Ta container tube was wrapped with 4 Ta heatshields.  Note final container is 45220-11
Entry  Tuesday, June 06, 2023, 09:14, Darwin Ortiz Rosales, C, 44139-4, TARGET BOAT, Done, Graphite inside insert Experiment 2 (regular formulation discs) 
Tuesday, June 06, 2023, 09:11
A Ta container tube was wrapped with 4 Ta heatshields.  Note final container is 45220-6
272 graphite discs were loaded.
Entry  Thursday, September 29, 2022, 10:02, Darwin Ortiz Rosales, , 44139-3, TARGET BOAT, Done, 220926-Graphite conditioning in target tube 
Thursday, September 29, 2022, 09:57
A Ta container tube was wrapped with 3 Ta heatshields.
338 graphite discs were loaded.
Entry  Tuesday, October 25, 2022, 12:25, Darwin Ortiz Rosales, TaC, 44139-15-SK, LP-SIS, Done, TaC coating sintering 
Tuesday, October 25, 2022, 12:18
Container wrapped in 4 Ta foil heatshields
Target temperature on OMEGA= 1850-1900 C
Entry  Monday, June 01, 2020, 12:03, Aaron Schmidt, Ta, 44139-13, LP-SIS, In progress, Ta#60 Conditioning 
 Ta#60 LP-SIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm
Entry  Thursday, June 11, 2020, 13:01, Darwin Ortiz Rosales, Empty, 44139-12, LP-SIS, Done,  WO#_44139-12_TaC_sintering.PNG
 Thursday, June 11, 2020, 09:56
Previous day (Wednesday June 10, 2020) 
Container coated with TaC and wrapped with 3 Ta heat shields.
Entry  Wednesday, March 18, 2020, 07:21, Marla Cervantes, TaC, 44139-11, LP-SIS, Done, TaC coating/sintering IMG_1538.JPG
 Wednesday, March 18, 2020, 07:10
Ta tube was coated with TaC and wrapped with Ta heat-shields (3 layers)
Desired temperature= 1900 C (expected TGHT ~430 A), TBHT will be set fixed at 230A (max).
Entry  Sunday, May 24, 2020, 13:39, Marla Cervantes, Empty, 44139-11, LP-SIS, Done, TaC coating/sintering  TaC-coating-sintering.PNG
 Sunday, May 24, 2020, 06:54
Ta tube was coated with TaC and wrapped with Ta heat-shields (3 layers)
Desired temperature= 1900 C (expected TGHT ~430 A), TBHT will be set fixed at 230A (max).
ELOG V2.9.2-2455