Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_2, Page 31 of 34  Not logged in ELOG logo
  ID Date Author Target Material Target Oven W.O# Source Status Subject Text Attachments
  79   Monday, July 22, 2013, 15:03 John WongEmpty38634-7LP-SISDoneSintering empty target oven coated with TaC for UCx#7Monday, July 22, 2013, 15:00
Target container is coated with TaC
- this container will be used for UCx#7.
  
  78   Tuesday, June 18, 2013, 16:40 John WongSiC38481-6HP-FEBIADDoneSintering of SiC #29

    

       
            
  
  77   Monday, June 17, 2013, 16:59 Laura LambertSiC38481-6HP-FEBIADDoneSintering of SiC #29Monday, June 17, 2013, 16:57
Target is loaded with 510 SiC discs
Container was previously coated with
  
  76   Tuesday, May 28, 2013, 17:50 John Wong Target Boat #2  DoneSintering TaC coated end capsTuesday, May 28, 2013, 17:36
The target containers endcaps were
coated with TaC solution and let dry. 
  
  75   Tuesday, May 14, 2013, 17:15 John WongEmpty38481-6HP-FEBIADDoneSinteringTaC coatingTuesday, May 14, 2013, 17:04
Target oven is coated with TaC, and
wrapped with 3-Ta heat shields.
  
  74   Monday, May 13, 2013, 17:17 Nikita BernierBeO  DoneSintering BeO pellets #6

    

       
            
  
  73   Monday, May 13, 2013, 12:53 Nikita BernierBeO  DoneSintering BeO pellets #6

    

       
            
 600Down.png 
  72   Tuesday, May 07, 2013, 16:53 Nikita BernierBeO  DoneSintering BeO pellets #6 Tuesday, May 07, 2013, 16:48
 
  
  71   Tuesday, April 30, 2013, 11:20 Anders MjosEmpty38481-5HP-FEBIADDoneCTL thermal test CTL block on T/C F/T Ch 1
Supply on Ch 3
HS Return on Ch 4
 StripTool_2013-05-02.pngCTL_ITD0431_Evap2.pdf2013-04-30_Evap2_ITD0431_CTL_Thermal_Test.pdf 
  70   Tuesday, April 23, 2013, 10:11 Anders MjosEmpty38481-4HP-FEBIADDoneCTL test 

    
 2013-04-23_Evap2_ITD0300_CTL_Thermal_Test.xlsxCTL_ITD0300_Evap2.pdfDeformed_Ionizer_Tube.jpg 
  69   Monday, April 22, 2013, 18:49 John WongEmpty38481-4HP-FEBIADDoneCTL test


   
        
            
  
  68   Friday, April 19, 2013, 15:27 Anders MjosEmpty38481-4HP-FEBIADDoneCTL testTarget installed with 4 T/C
The target assembly is ITD0300 with
the CTL Cu cooling block slightly modified.
  
  67   Friday, April 19, 2013, 09:39 Rick MaharajEmpty  Donethermocouple Feedthru A thermocouple feedthru was installed
via 9 pin sub-D connector. It runs from the
the conflat cross on the top of the evaporator
  
  66   Thursday, April 11, 2013, 14:20 John WongEmpty39165-6LP-SISDoneCoating target oven /w TaC & sintering for UCx#6Monday, April 08, 2013, 17:39
Target container is coated with TaC;
the container will be used for the UCx#6
  
  65   Thursday, March 14, 2013, 12:27 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal test 3 (w/o CTL block)Thursday, March 12, 2013 
The CTL was removed and target heated
to 580A / 300A
 2013-03-13_-_FEBIAD-HP-A_TargetLeg_and_HeatShield_TC.pdf2013-03-13_-_FEBIAD-HP-A_TargetLeg_and_HeatShield_TC.xlsx 
  64   Wednesday, March 13, 2013, 16:08 Anders MjosEmpty38481-4HP-FEBIADDoneThermal testWednesday, March 13, 2013 
Thermocouple channels (see attached
PDF for photos)
 HP-FEBIAD-A_TC_at_fins.pdf 
  63   Monday, March 11, 2013, 15:59 John WongEmpty38481-4HP-FEBIADDoneCTL thermal test 2

    

       
            
 autorampingup_110.PNG 
  62   Monday, March 11, 2013, 12:23 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal test 2 

    
 2013-03-11_Evap2_Second_Thermal_Test.pdf 
  61   Wednesday, March 06, 2013, 17:53 John WongEmpty38481-4HP-FEBIADDoneCTL thermal test

    

       
            
 rampingup_1.PNGrampingup_2.PNGautorampingdown_23.PNG 
  60   Wednesday, March 06, 2013, 10:41 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal testWednesday, March 06, 2013
The Cool Transfer Line (CTL) test
target is installed for thermal tests. Drawing
 CTL_1st_Assebmly_Thermal_Test_Evap2.pdf2013-03-08_Evap2_First_Thermal_Test.pdf 
ELOG V2.9.2-2455