Tuesday, October 27, 2020, 10:25, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, parasitic target commissioning
|
2020-10-27 10:24 setup introduced yesterday. Pumping over night IGP1: 5.7e-7T. Water leak check ok. Performing heating elements check.
2020-10-27 10:43 Heating elements check show low cooling. Ramping up target 1A/15s to 200A.
2020-10-27 11:54 all ok 200A, thermocouples show room temperature on cartridge and heat shield. Ramping up target 2A/10s to 300A.
2020-10-27 11:54 all ok 300A, thermocouples show 28/25degC. Ramping up target 2A/10s to 400A.
2020-10-27 11:54 all ok 400A, thermocouples show 36.5/29degC. Ramping up target 2A/10s to 500A.
2020-10-27 11:54 all ok 500A, thermocouples show 48.9/33degC. Ramping up target 2A/15s to 550A.
2020-10-27 12:43 all ok 550A, thermocouples show 55/34degC. Ramping up target 2A/15s to 600A.
2020-10-27 12:43 all ok 600A, thermocouples show 61.5/35.2degC. Ramping up target 2A/15s to 625A.
2020-10-27 13:14 all ok 625A, thermocouples show 64.6/34.2degC. Ramping up target 2A/15s to 650A. |
Monday, November 02, 2020, 18:32, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, HEA heat treatment
|
2020-11-02 6:32: roughing on
2020-11-02 7:21: Turbo on for a while, IGP1:1.8e-5T . water leak check ok.
2020-11-02 7:47: IGP1:1e-5T . Ramping up target heater to 200A, 1A/10s.
2020-11-02 7:47: TGHT at 275A, pyrometer at 1300degC. Leaving it hot for 24h.
2020-11-04 9:06: After 37h treatment, ramping down to 0A.2A/10s.
2020-11-04 9:46: target ramped down. Venting.
2020-11-04 17:30: Big amounts of outgassing non detected in GP1 coated some inner walls in evap2. The walls got cleaned with acetone. All as before now.
|
Wednesday, November 04, 2020, 17:31, Ferran Boix Pamies, Empty, 41882-2, TARGET BOAT, Done, Parasitic target graphite outgassing.
|
2020-11-04 17:31: target installed with boat containing graphite container for outgassing. Roughing pump on.
2020-11-04 17:49 turbo on, leaving it pumping over night.
2020-11-05 11:32 leak check ok. Ramping up target to 200A 2A/10s.
2020-11-05 11:53 IGP1:1.1e-6T . Ramping up target to 300A 1A/10s.
2020-11-05 11:53 IGP1:1.2e-6T . Pyrometer:1320degC. Ramping up target to 400A 1A/10s.
2020-11-05 11:53 IGP1:1.8e-6T . Pyrometer:1650degC. Ramping up target to 500A 1A/10s.
2020-11-05 12:57 IGP1:3.4e-6T . Pyrometer:1910degC. Ramping up target to 525A 1A/10s.
2020-11-05 13:02 IGP1:3.6e-6T . Pyrometer:1990degC. Leaving it hot for 1h.
2020-11-05 14:00 IGP1:2e-6T stable . Pyrometer:1990degC. cooling down 2A/10s.
|
Thursday, November 05, 2020, 15:13, Ferran Boix Pamies, Empty, 41882-2, TARGET BOAT, Done, cleaning treatment.
|
2020-11-05 15:44 empty and naked boat in for heating up system and clean up. Turbo on.
2020-11-06 16:58 IGP1:4e-7T leak check ok. Ramping up target to 500A. 1A/10s.
2020-11-09 12:43 The target was left at 1500degC during the weekend.
2020-11-17 14:11 turbo pump off. Slow venting.
2020-11-18 09:18 Evap2 vented. Target removed. |
Tuesday, November 24, 2020, 12:56, Marla Cervantes, , 44139-8-SK , TARGET BOAT, Done, Graphite casting conditioning
|
Tuesday, November 24, 2020, 09:23
A batch of 60 discs of 18 mm diameter were loaded in a tantalum tube. The tantalum tube was wrapped with 3 layers of Ta foil for heat shielding and mounted in the EVAP2. EVAP2 pumped down overnight and Aaron made a leak test this morning (elog 524).
The target material will be heated to 1990 degC. To measure the temperature, the tube has a Ta foil close to the graphite foils and it is held in place with a tantalum spring. Another Ta spring holds the graphite foils in the opposite side of the tube. The temperature will be measured with the Omega pyrometer (slope 0.99)
IGP1 = 6e-7 Torr. Note: The pressure has an usual behavior (see 2020-11-24-IGP1 and 2020-11-24IGP1-zoom out). After ~9 hrs, the pressure became stable (see 2020-11-24IGP1 -stable)
Tuesday, November 24, 2020, 13:00
IGP1 = 6.7e-7 Torr
Good vacuum of 3e-2 Torr and Bad vacuum 5e-2 Torr
The autoramp is set to 80 A at 1 A each 10 s
Tuesday, November 24, 2020, 13:43
IGP1 = 2.7e-5 Torr
TGHT = 1.13 V 80.5 A
Autoramp is set to to 100 A at 1 A each 20 s
Tuesday, November 24, 2020, 13:57
IGP1 = 2.5e-5 Torr and going down
TGHT = 100.2 A, 1.47 V
Autoramp is set to to 120 A at 1 A each 20 s
Tuesday, November 24, 2020, 14:06
IGP1 = 2.09e-5 Torr
TGHT = 1.6 v, 122 A
Autoramp is set to 200 A at 2 A each 10 s
Tuesday, November 24, 2020, 14:18 IGP1 = 5.4e-5 Torr
IGP1 = 1.5e-5 Torr
TGHT = 2.9 V, 200.5 A
Omega = 1123 °C
Autoramp is set to 450 A, conditions:
2 A each 10 s with a good vacuum of 3e-2 Torr and a bad vacuum 5e-2 Torr
Tuesday, November 24, 2020, 14:45
The autoramp was stopped at 424 A
TGHT = 421.65 A, 8.353 V
IGP1= 2.5e-5 Torr and going down
Omega 2020 degC
The TGHT current was reduced to 420 A (8.27 V) and the temperature reduced to 2007 degC
Tuesday, November 24, 2020, 21:03
IGP1 = 2.09e-6 Torr
TGHT = 7.899 V, 421.312 A
Temperature = 1870 degC
Autoramp is set to 0 A at 1 A/min |
Monday, February 01, 2021, 13:57, Darwin Ortiz Rosales, SiC, 40282-4, TARGET BOAT, Done, Sintering of SiC discs for SEM
|
Monday, February 01, 2021, 13:52
Ta boat loaded with 20 Disc on either end capped with Ta springs to prevent overexpansion. discs wrapped Graphite foil and boat wrapped in Ta heat-shields (3 layers).
Sample A on left side and sample B on right side.
Desired temperature= 1800C (expected TGHT 410 A).
good vacuum = 3.00 e-05 Torr
bad vacuum = 5.00 e-05 Torr
Evap2 left to pump down over night.
Tuesday, February 02, 2021, 10:01
Pressure stable at IGP1= 7.8e-7 Torr
TGHT autoramp set to 50 A @ 1/min
Tuesday, February 02, 2021, 13:45
IGP1=3.5e-6 Torr
TGHT =49.9 A, 0.56 V
Ramp at 1A/min to 100A
Wednesday, February 03, 2021, 08:25
IGP1= 5.5 e-07 Torr
TGHT = 100 A, , 1.2 V
Yesterday the camera failed to operate. Cloud service discontinued. The TS camera is offline but it is a different provider. Will start ramping to 400A .
Ramp rate 2A/min
Wednesday, February 03, 2021, 15:55
ramped up to 520 A and 9.1V TGHT
Temperature average 1644 C but suspect actual temperature higher.
Held for 5 hours and started ramp down at -2A/min
Thursday, February 04, 2021, 9:35
IGP1= 2.99e-7 Torr
Begin pumpdown procedure and remove container
Note: SiC evaporation on most discs. The temperature was too high. Need to repeat.
|
Tuesday, February 09, 2021, 06:48, Aaron Schmidt, , NA, , Done, Ta coating test
|
Monday, February 08, 2021, 17:00: Installed brackets w/ Ta wire and a small piece of Re to test voltage drop.
Rough down, TP on. Waterlines open.
Tuesday, February 09, 2021, 06:44: Vacuum @ 8.63e-07T.
Tuesday, February 09, 2021, 06:45: Shut TP & roughing pump ff. Valves are close. Ready for power outage.
Tuesday, February 09, 2021, 11:30: BP1 & TP1 back on.
Tuesday, February 09, 2021, 11:37: PS on. Vacuum @ 9.7e-06T & continuing down.
micron slope 0.98
Tuesday, February 09, 2021, 16:01 Pressure 7.26e-7 Torr
aiming at a temperature of 2000 degC on the wire; wire is not in the visual range of pycnometer; simulations of the system indicate that wire will be at 2000 degC at 60 W, hence current will be increased slowly.
Rate: 0.1 A/60 s to 10 A
Tuesday, February 09, 2021, 16:47 Tendence showed that at 5 A the power will be ~10 W, final ramping step was updated accordingly.
Tuesday, February 09, 2021, 16:49 Pressure dropping a bit: Current reading 7e-7 Torr
Tuesday, February 09, 2021, 17:09Pressure going down, curent will be ramped down at 0.2 A/min
Pressure: 6.958e-7 Torr, TGHT: 5 A, 2.748 V, omega is reading 1625 degC somewhere somehow, wire will stay at this conditions for 10 min to see if there is a pressure or voltage change.
Tuesday, February 09, 2021, 17:16 voltage and temperature are slowly increasing 2.789 V, and 1688 degC respectively.
Tuesday, February 09, 2021, 17:32 Voltage signal is noisy but it seems like the voltage is not increasing anymore, preassure has remained constant, wire is glowing, 1100 degC with manual pyrometer.
Tuesday, February 09, 2021, 17:44 TGHT: 2.81 V, 4.95 A, IGP1 6.63e-7 Torr. current will be increased manually at 0.2 A steps. At first step voltage is stable.
Tuesday, February 09, 2021, 18:13 TGHT: 6.6A, 3.981V (~26W), Omega 1741 degC and manual pyrometer ~1300 degC
Tuesday, February 09, 2021, 18:28 TGHT: 8A, 5.121V (~40W), omega 1816 degc, 1390 degC with manual pyrometer, step changed to 0.4A.
Tuesday, February 09, 2021, 18:34 TGHT: 8.8A, 5.88V (50W), omega 2008 degC, 1500 manual pyrometer
Tuesday, February 09, 2021, 18:56 TGHT: 9.6A, 6.64V, manual pyrometer 1800 degC, omega 2042 degC, wire is shinny enough for micron 2092 degC.
Tuesday, February 09, 2021, 19:01TGHT: 10A, 7V, ~1800 degC manual pyrometer, omega 2123 degC, micron 2152 degC
Tuesday, February 09, 2021, 19:15 TGHT: 10.5A, 7.47V, 2150 degC Omega, 2165 degC, ~1800 degC manual
Tuesday, February 09, 2021, 19:23 TGHT: 11A, 7.93 V, 2188 omega, 2210 deC micron
Tuesday, February 09, 2021, 19:29 TGHT: 11.5A, 8.37V, 2188 omega, 2210 deC micron
Tuesday, February 09, 2021, 19:33 TGHT: 12A, 9V, 2325 degC, 1900 degC manual, the wire changed shape and the preassure increase a bit , micron was readjusted to read, micron 2454 degC. Wire might be touching tube, only one more amper will be imputed.
Tuesday, February 09, 2021, 19:55 TGHT 13A, 9.865 V, 2404 degC omega , 2558 degC micron, manual pyrometer still reads 1800 degC, pressure increased with the power increment, bbut it seems like the wire touching the tube so no more current will be imputed.
Tuesday, February 09, 2021, 20:08 started ramping at -0.2A/min
Wednesday, February 10th , 20211, 10:00 System unloaded from EVAP2, wire has straightened, it has not sintered to the copper brackets, system is clean there is no evidence of coating. |
Thursday, February 11, 2021, 10:57, Marla Cervantes, , NA, , Done, Re coating Test 1
|
Thursday, February 10, 2021, 12:00
Objective: Heat a Re wire to evaporate it and deposit a layer of Re on the inner surface of a Ta tube.
A Re wire of 1mm diameter was clamped with Cu brackets in EVAP2, the wire is partially enclosed in a Ta tube. EVAP2 pumping down
The wire needs to be heated to 2500 degC since this is its sublimation temperature at 8e-7 Torr
There is not a reliable system to measure the temperature of the wire but the readings of the micron, manual, and omega pyrometers will be register.
According to COMSOL simulations a power and taking in consideration the EVAP2's power loss, a power of 520 W (5A, 10V) is required.
Thursday, February 11, 2021, 15:39
Pressure 3.78e-7 Torr, current rate set to 10 A @ 0.5 A/min
Thursday, February 11, 2021, 16:32
Pressure: 4.01e-7 Torr, TGHT = 10A, 1.719 V. The voltage has stabilized, the wire is glowing but not enough for reading with micron nor omega, manual reads 970 degC. Also, the wire formed an arc (crest).
Thursday, February 11, 2021, 16:44
Pressure 3.8e-7 Torr, TGHT = 10 A, 1.723 V ramp set to 20A @ 0.2 A/min
Thursday, February 11, 2021, 17:26
Pressure increasing 4.7e-7 torr, TGHT = 20 A, 4.016 V, the wire does not seem to be changing,
Thursday, February 11, 2021, 18:02
Ramp set to 30A @0.4A/min
Pressure 7.2e-7 Torr, TGHT = 30A, 6.561V, manual pyrometer reads 1720degC
Ramp set to 40A @0.4A/min
Thursday, February 11, 2021, 18:35
Pressure 2.1e-6Torr and increasing, TGHT = 40A, 9.1V, manual pyrometer reads ~1880 degC
Ramp set to 50A @ 0.4 A/min
|
Saturday, February 13, 2021, 08:14, Darwin Ortiz Rosales, SiC, 41992-1, TARGET BOAT, Done, Sintering of SiC discs for SEM
|
Saturday, February 13, 2021, 08:10
Ta boat loaded with 80 discs enclosed in graphite foil in pockets of 20. Sample A at both ends and sample B in the middle spaced out. Boat wrapped in Ta heat-shields (3 layers).
(A B B A)
Desired temperature= 1800C (expected TGHT approx 410 A).
good vacuum = 3.00 e-05 Torr
bad vacuum = 5.00 e-05 Torr
Evap2 left to pump down over previous night.
IGP1= 5.4e-7 Torr and stable
Initiating TGHT ramp up at 1 A/ min to 30 A
Saturday, February 13, 2021, 12:19
IGP1= 6.9e-06 Torr
Ramp to 50 A 1A/min
Saturday, February 13, 2021, 14:35
IGP1 = 6.4e-6 Torr
Pressure trending down.
Saturday, February 13, 2021, 14:56
IGP1= 4.9 e-6 Torr
Initiate Ramp up @ 1 A/min to 400 A
Changed ramp up to 0.5 A/min at around 11:30 pm
Sunday, February 14, 2021, 11:43
The current will be ramped up to 420 A according to the trendline approximation (see attachement 1)
Sunday, February 14, 2021, 12:26
IGP1 = 8.9 e-06 Torr and trending down
TGHT = 420 A, 7.5 V
OMEGA = 1730 C
Will ramp up to 428 A manually
Sunday, February 14, 2021, 12:30
Reached 428 A on TGHT.
OMEGA = 1760 C
Will bump to 430 A and hold for 4 hours
OMEGA= 1765 C
Sunday, February 14, 2021, 18:00
OMEGA = 1789 C
IGP1= 7.5 e -7 Torr
TGHT = 430.5 A , 7.8 V
Start ramping down at -1A/min to zero A
|
Tuesday, February 23, 2021, 08:59, Marla Cervantes, , NA (Cu-tube), , Done, Re coating Test 2
|
Tuesday, February 23, 2021, 08:49
Yesterday a heat shield was washed and when dry it was installed in the EVAP2,
A 1mm thick rhenium wire was held within two copper brackets to pass through a Cu tube with the intention of coating its inside face
Tuesday, February 23, 2021, 08:58 IGP1 = 7.7e-7 Torr
Pressure 5.88e-7 Torr, current rate set to 10 A @ 0.5 A/min
Pressure 6.1e-7 Torr, current rate set to 20 A @ 0.5 A/min
Pressure 8.51e-7 Torr current rate set to 30 A @ 0.5 A/min, temperature corrected 1800 degC (measured with filament pyrometer)
After 10 min the current and voltage are stable and the pressure is going down
Tuesday, February 23, 2021, 16:25
It seems like the wire is touching the tube so the system will be cool down.
Pressure 6.8e-7 Torr current rate set to 0A at -0.1 A/min
Tuesday, February 23, 2021, 17:38
Pressure 6e-7 Torr, TGHT = 23.3 A, 4.854 V, Temp 1788 deg C Omega, 1540 degC filament
current rate set to 0A at 0.2A/min
Wednesday, February 24, 2021, 09:37
Venting EVAP2
Wednesday, February 24, 2021, 16:47
The wire and Cu tube were fix such that the wire's deformation does not lead it to touch the tube, then the assembly was attached again and the EVAP2 was pumped down.
IGP1 = 9.3e-7 Torr, current rate is set to 5 A at 0.5 A/min
Wednesday, February 24, 2021, 17:04
IGP1 = 9e-7 Torr TGHT = 5.175A, 0,749 V
current rate is set to 10 A at 0.5 A/min
Wednesday, February 24, 2021, 17:23
IGP1 = 8.8e-7 Torr, TGHT = 10A, 1.78V
current rate is set to 20 A at 0.5 A/min
Since the wire seemed to be touching the tube, the system was vented.
The tube was shifted and the heat shield installed again, the system was pumped over nigth.
Thursday, February 25, 2021, 09:15
A water leak was performed and no leak was observed
IGP1= 4.95e-7 Torr
Thursday, February 25, 2021, 09:32 The current is increased at 0.5 A/min to 5 A
Thursday, February 25, 2021, 10:00
The current was tapped manually at 0.5 A to 6 A the wire is now glowing dimmly
Current rate set to 10A at .5 A/min
Current rate set to 20 A at 0.5A/min
Current rate set to 30 A at 0.5A/min
Thursday, February 25, 2021, 11:17 IGP1= 5.7e-7 Torr, TGHT=30.5A, 6.718V, filament=1740 degC
voltage and current stable, pressure going down.
Thursday, February 25, 2021, 11:21
Current rate set to 40 A at 0.4 A/min
Thursday, February 25, 2021, 11:53 IGP1 = 5.9e-7 Torr, TGHT = 9.267V, 39.15A, filament = 2060 degC
voltage and current stable, pressure going down.
Current rate set to 50 A @ 0.2A/min
During ramping the voltage reduced a bit and I decided to stop the ramp and reduce the current, the voltage stayed constant but the current started increasing slowly without me inputting it so I decided to ramp down the current at 0.2A/min.
When the current reached 0A the power supplies and the pumps were turned off, after an ~1h when the turbo pump had already stopped, the EVAP2 was vented and open.
The wire sintered to the copper tube confirming that the wire was in contact with the tube during heating.
The Cu tube present a grey metallic coloration indicating a Re coating.
The set up together with the copper heat shield were removed from the |
Friday, February 26, 2021, 09:28, Ferran Boix Pamies, Empty, none, , Done, Parasitic target thermal tests
|
Tests were performed with external power supply. No target boat or container.
Small power on heating small heating elements on parasitic target attached on isac heatshield with water cooling on.
|
Tuesday, March 02, 2021, 11:32, Darwin Ortiz Rosales, TaC, 44691-5, LP-SIS, Done, TaC coating/sintering
|
Tuesday, March 02, 2021, 11:26
Ta tube was coated with TaC and wrapped with Ta heat-shields (3 layers)
Initial weight including heat-shields = 433.8 g
Desired temperature = 1900 C (expected TGHT ~430 A), TBHT will be set fixed at 230A (max).
Evap 2 will be pumped down over night.
Good vacuum = 3.00 e-5 Torr
Bad vacuum = 5.00 e-5 Torr
Wednesday, March 03, 2021, 13:28
IGP1 = 4.0 e-7 Torr
Start ramping @ 1A/min to 20A on both TGHT and TBHT
Wednesday, March 03, 2021, 15:03
Start ramping @1/min to 60A on Both TGHT and TBHT
Wednesday, March 03, 2021, 22:42
TGHT = 60A, TBHT = 60A
IGP1= 4.2 e-7 stable
Start ramping to 400A @ .5A/min for TGHT and @0.5A/min for TBHT to 230A
Thursday, March 04, 2021, 11:56
TGHT = 400 A, TBHT =230A
IGP1= 1.9e-6 Torr
OMEGA = 1695 C
Continue ramp up @0.5A/min to 430A on TGHT
Thursday, March 04, 2021, 14:02
IGP1 = 1.87e-6 Torr
TGHT = 434 A , 7.2 V
OMEGA = 1787 C
Will tap up manually 450A @ on TGHT and leave at that current for ~4 hours
Thursday, March 04, 2021, 19:35
After ~ 5 hours at 1829 C max OMEGA reading
OMEGA = 815 C
Start ramp down at 1A/min on TGHT and 0.8A/min for TBHT
IGP1= 1.2e-6 Torr
|
Friday, March 05, 2021, 10:48, Darwin Ortiz Rosales, TaC, 44691-1, LP-SIS, Done, TaC coating/sintering
|
Friday, March 05, 2021, 10:47
Ta tube was coated with TaC and wrapped with Ta heat-shields (3 layers)
Initial weight including heat-shields = 431.0 g
Desired temperature = 1900 C (expected TGHT ~430 A), TBHT will be set fixed at 230A (max).
Evap 2 will be pumped down over night.
Good vacuum = 3.00 e-5 Torr
Bad vacuum = 5.00 e-5 Torr
Saturday, March 06, 2021, 10:29
IGP1= 2.7 e-07 Torr and stable
AutoRamp at 1A/min to 40 A on TGHT and TBHT
Saturday, March 06, 2021, 22:36
IGP1= 2.2e-07 Torr
TGHT = 40.3 A, .46V
TBHT = 38.48 A, .48 V (set to 40 A)
Start Autoramp at 0.5A/min to 400 A on TGHT and 230A on TBHT
Sunday, March 07, 2021, 07:48
IGP1=8.5e-7 Torr
TGHT = 287 A, 4.6V
TBHT = 232 A, 4.0 V
OMEGA = 1493C
Increase ramp speed on TGHT to 2A/min to 400A
Sunday, March 07, 2021, 08:36
IGP1=1.7 e-06 Torr
TGHT = 373.7 A, 6.3V
TBHT = 232.9 A, 4.1 V
OMEGA = 1752 C
Sunday, March 07, 2021, 08:53
IGP1= 1.7e-06 Torr
TGHT = 400 A, 6.8 V
TBHT = 232.8 A, 4.1 V
OMEGA= 1842
Ramp TGHT @ 2A/min to 420 A as per attached current approximation
Sunday, March 07, 2021, 09:25
OMEGA=1915 C
TGHT = 420A, 7.2V
TBHT= 232.8 A, 4.1V
IGP1= 1.6 e-06 Torr
Tap down manually to approx 1900 C
TGHT = 412.9 A, 7.0 V and OMEGA=1900 C
Will leave for about 4 hours at this temperature
Sunday, March 07, 2021, 13:05
IGP1= 1.1 e-06 Torr
TGHT = 415 A, 7.2 V
TBHT = 232.8 A, 4.1 V
OMEGA = 1880C
Start cool down at -2A/min on TGHT and -1A/min TBHT
|
Tuesday, March 09, 2021, 11:54, Darwin Ortiz Rosales, TaC, 42464-1, HP-FEBIAD, Done, TaC coating/sintering
|
Tuesday, March 09, 2021, 11:54
Container coated with TaC and wrapped with 3 Ta heat shields.
Desired temperature= 1900 C, Omega Slope set = 0.990, Auto TGHT at 0.2A/min to reach 400A, TGHT will be increased accordingly to reach desired Temp.
TBHT will be set fixed at 230 A max).
Good vac at 3.00e -5 Torr
Bad vac at 5.00e-5 Torr
Chamber pump down
Wednesday, March 10, 2021, 08:32
IGP1 = 2.6 e -07 Torr
Start autoramp @ 1A/min to 40 A on both TGHT and TBHT
***Autoramp aborted due to work on EF12 affecting EVAP2***
Will have to resume Thursday or Friday
Saturday, March 13, 2021, 7:54
IGP1= 3.8e-07 Torr
Initiate heating @ 0.5A/min TBHT and TGHT to 60 A
Saturday, March 13, 2021, 23:01
IGP1 = 2.7e-07Torr
TGHT = 60.5A, 0.7V
TBHT= 60.0A, 0.7V
Initiate ramp @ 1 a/min to 400 A on TGHT and 230A on TBHT
Sunday, March 14, 2021, 08:45
IGP1= 8.2e-07 Torr
TGHT = 400A, 5.6V
TBHT = 232.9A, 3.0V
OMEGA = 1142 C
Continue ramping to 460 A on TGHT at 1a/min
Sunday, March 14, 2021, 10:11
IGP1 = 1.0 e-06 Torr
TGHT= 460.4 A, 6.5 V
TBHT = 232.9 A, 3.0 V
OMEGA = 1239 C
Will ramp up to 500 A at 1a/min on TGHT
Sunday, March 14, 2021, 10:53
IGP1 = 1.3 e-06 Torr
TGHT= 495 A, 7.2 V
TBHT = 232.9 A, 3.0 V
OMEGA = 1316 C
Will ramp up to 600 A at 1a/min on TGHT
Sunday, March 14, 2021, 12:45
IGP1 = 3.0 e-06 Torr
TGHT= 604 A, 9.1 V
TBHT = 232.9 A, 3.1 V
OMEGA = 1610 C
Will ramp up to 660 A at 1a/min on TGHT
Sunday, March 14, 2021, 17:01
IGP1= 2.4e-06 Torr
TGHT = 664 A, 10V
TBHT = 232.9 A, 3.1V
OMEGA = 1733 C
tapping TGHT to 740 A
OMEGA = 1883 C
Sunday, March 14, 2021, 21:45
IGP1= 3.1e-06 Torr
TGHT = 744A, 11.5V
TBHT = 232.9 A, 3.2V
OMEGA = 1875 C
Start cooling TGHT @-3A/min and TBHT @-1A/min
|
Tuesday, March 16, 2021, 08:29, Darwin Ortiz Rosales, TaC, , TARGET BOAT, Done, sintering of TaC on Caps and springs
|
Tuesday, March 16, 2021, 08:28
Each endcap is separated with a disc of graphite foil and rolled into packs of 5 within a foil envelope in a target boat.
There are also 4 coated springs, one in between endcaps and three on the ends
The boat is wrapped with 3-layers of Ta heatshields.
Chamber pumping down
OMEGA slope = 0.99
Will ramp TGHT up to 40 A then autoramp to 400A at 1A/min.
Final desired temperature on OMEGA (tap)= 1800C
Tuesday, March 16, 2021, 11:22
IGP1= 3.5e-06 Torr
TGHT = 40A, 0.4V
Will ramp up at 1A/min to 400 A
Wednesday, March 17, 2021, 08:06
IGP1= 2.98 e-07 Torr
TGHT = 400 A, 4.3V
OMEGA shows no temperature reading. Will ramp up to 450A at 1A/min
Wednesday, March 17, 2021, 08:58
OMEGA still shows no reading
IGP1= 4.2e-07 Torr
ramping to 470A @ 1A/min
Wednesday, March 17, 2021, 09:21
OMEGA no reading
IGP1 = 4.4 e-07 Torr
TGHT = 470 A, 5V
ramp up to 490 A at 1A/min
Wednesday, March 17, 2021, 11:05
TGHT at 490 A, 5.2 V since 10 am. Will start cooling at 2 pm.
Wednesday, March 17, 2021, 13:47
TGHT = 493A, 5.3V
IGP1= 3.2e-07 Torr and stable
Start ramp down at -2A/min
Thursday, March 18, 2021, 11:20
The boat was dismounted but the materials had not sintered properly. The boat looked very twisted. Everything was transferred to a new boat with uncoated Ta caps at either end.
It was left overnight to establish vacuum.
Friday, March 19, 2021, 08:23
IGP1= 2.2 e-07 Torr
initiate heating at 1A/min on TGHT to 60 A
Friday, March 19, 2021, 10:04
IGP1= 3.6 e-07 Torr
TGHT = 60 A, .73 V
Ramp up to 450 A @ 2A/min
Friday, March 19, 2021, 14:26
OMEGA 1895 at 455A, 8.4 V
manually ramp down to 1800C
OMEGA 1800C at 416A, 7.6V
will leave like that for 3 hours more
Friday, March 19, 2021, 17:12
OMEGA 1795 C
TGHT = 415A, 7.6V
IGP1= 6.8e-07 Torr
Start ramp down at -2A/min
Monday, March 22, 2021, 23:07
Marla removed from Evap 2. Sintering vwas very good. The container with Ta caps is better for sintering these pieces.
|
Tuesday, March 23, 2021, 11:28, Marla Cervantes, Empty, 44489-6, , Done, Re-coating test 3
|
Objective: Coating the inner surface of a short tantalum boat with rhenium.
Result:
- The wire snnaped around 376 W (53 A, and 7.09 V) and 2170 °C (measured with filament pyrometer)
- The tube does not have indications of coating
Thursday, March 25, 2021, 11:23
Yesterday a heat shield was installed in the EVAP2.
The desired temperature of the Re wire is 2500 degC
A water leak was performed (elog 539 describes it), no leak was detected.
Tuesday, March 23, 2021, 11:01
Pressure 3.8e-7 Torr, current rate set to 6 A @ 0.5 A/min
The wire started glowing at TGHT = 4W, 7A, 0.56V
When reaching 7A the current was increased 0.5 A manually
When reaching 16 A, the current was increased 1 A manually until reaching 54 A when the wire snapped |
Thursday, March 25, 2021, 11:24, Marla Cervantes, Empty, NA (Cu-Tube, , Done, Re-coat test 4
|
Objective: Coating the inner surface of a short tantalum tube with rhenium.
Result:
- The wire snnaped around 376 W (53 A, and 7.09 V) and 2170 °C (measured with filament pyrometer)
- The tube is coated
Thursday, March 25, 2021, 11:23
Yesterday a heat shield was installed in the EVAP2.
The desired temperature of the Re wire is 2500 degC
A water leak was performed (elog 539 describes it), no leak was detected.
Tuesday, March 23, 2021, 11:01
Pressure 3.8e-7 Torr, current rate set to 6 A @ 0.5 A/min
The wire started glowing at TGHT = 4W, 7A, 0.56V
When reaching 7A the current was increased 0.5 A manually
When reaching 16 A, the current was increased 1 A manually until reaching 54 A when the wire snapped |
Friday, March 26, 2021, 13:58, Marla Cervantes, Empty, 44489-6, , Done, Re-coat 1
|
Friday, March 26, 2021, 13:55
Yesterday a heat shield was installed in the EVAP2.
A 1mm thick rhenium wire was held within two copper brackets to pass through a Cu tube with the intention of coating its inside face.
The desired temperature of the Re wire is 2500 degC
A water leak was performed and no leak was detected
|
Friday, March 26, 2021, 16:23, Marla Cervantes, Empty, 44489-7, , Done, Re-coat 2
|
Objective: Coating the inner surface of a tantalum tube to make a destructive test and use a reference for the tantalum boats coatings
Results:
Sunday, March 27, 2021, 11:23
No water leak
IGP1 = 3.7e-7 torr
Sunday, March 27, 2021, 16:10
The wire was heated in the same manner as the last three runs
From 0A to 7A the autoramp was set to 0.5A/min
At 8A the wire started the glow dimmly
Above 8A, the wire was heated manually at 0.5A until 16A where the step was changed to 1A,
the temperature was measured with the filament pyrometer every 2 A starting at 10A
At 42 A the step was changed to 0.6A until 42.6A, 4.38V (2020 °C), the wire was kept at that temperature for 90 min
After that time, the current was ramped down at 0.5A/min until ~20A when the current rampping was changed too 1A/min
|
Sunday, March 28, 2021, 11:24, Marla Cervantes, , NA (Ta-tube), , Done, Re-coat 3
|
Objective: Coating the inner surface of a tantalum tube to make a destructive test and use a reference for the tantalum boats coatings
Results: The tube was coated
Sunday, March 28, 2021, 11:23
No water leak
IGP1 = 2.3e-7 torr
Sunday, March 28, 2021, 16:10
The wire was heated in the same manner as the last three runs
From 0A to 7A the autoramp was set to 0.5A/min
At 8A the wire started the glow dimmly
Above 8A, the wire was heated manually at 0.5A until 16A where the step was changed to 1A,
the temperature was measured with the filament pyrometer every 2 A starting at 10A
At 42 A the step was changed to 0.6A until 42.6A, 4.38V (2020 °C), the wire was kept at that temperature for 90 min
After that time, the current was ramped down at 0.5A/min until ~20A when the current rampping was changed too 1A/min
|
|