  Evaporator_2, Page 12 of 25  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Tuesday, May 14, 2019, 13:57, Aaron Schmidt, , , LP-FEBIAD, Done, Test FEBIAD 
 Tuesday, May 14, 2019, 13:56: Removed old HS w/ flexible lines & swapped in the FEBIAD. (HS waterlines are still purged.) Roughing.
Tuesday, May 14, 2019, 14:06: Turbo pump on. 
Tuesday, May 14, 2019, 14:22: Waterlines opened. Vacuum ok @ 5.34e-05T & dropping. 
Entry  Friday, May 10, 2019, 16:58, Marla Cervantes, , 43943-1, , Done, TaC coating/sintering for graphite insert test 
 Friday, May 10, 2019, 16:54
A tantalum tube was coated with TaC,and wrapped with three tantalum sheets,
the tube was set in the EVAP2 to sinter the TaC coating.
Entry  Tuesday, April 30, 2019, 09:35, Darwin Ortiz Rosales, Empty, 43044-6, LP-SIS, Done, TaC coating/sintering 43044_6a.png43044_6b.png
Tuesday, April 30, 2019, 09:33
Container was coated with TaC and wrapped with 2 Ta heat shields.
Desired temp = 1900  C, Omega slope set = 0.990, Auto ramping TGHT at 1A/min to reach 400A, 
Entry  Tuesday, April 23, 2019, 13:55, Aaron Schmidt, Ta, 43044-4, LP-SIS, In progress, Conditioning Ta#58 Ta#58_Loading_data.pdfTa#58_Evap_2_Conditioning..docx
Ta#58 LP-SIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm
Entry  Wednesday, April 17, 2019, 09:06, Marla Cervantes, , 38295-10, LP-FEBIAD, Done, Graphite insert test 190417-TargetContainer-TEMP.pdfIMG_1074.JPG
 Wednesday, April 17, 2019, 09:03
An uncoated target container was loaded with a graphite insert and wrapped with 3 tantalum layers,
Two Ta caps were used
Entry  Tuesday, April 16, 2019, 13:40, Aaron Schmidt, , , , , Replace bottom insert on HS  
 Tuesday, April 16, 2019, 13:38: Replaced the bottom insert on the heat shield. 
Used small amount of isopropyl alcohol to wipe the inside if the HS out. 
Entry  Sunday, April 07, 2019, 08:13, Marla Cervantes, , 43630-5, , Done, Graphite insert test #5 190407-GraphiteInsertTest.pdfV1.JPGV2.JPG20190415_170133.jpg
 Sunday, April 07, 2019, 08:10
A graphite insert (with conical caps) was loaded in tantalum tube previously coated with TaC,
and wrapped with 3 tantalum foils,
Entry  Wednesday, April 03, 2019, 16:59, Marla Cervantes, TaC, 43630-5, , Done, TaC coating/sintering for graphite insert test 
 Wednesday, April 03, 2019, 16:57
Tantalum tube was coated with TaC and wrapped with Ta heat-shield (3 layers)
Desired temp = 1900 C (expected TGHT ~445A/7.5V).
Entry  Monday, April 01, 2019, 16:35, Darwin Ortiz Rosales, , 43630-4, , Done, TaC coating/graphite/sintering 
Monday, April 01, 2019, 16:35
Container was coated with TaC and a roll of graphite inserted inside the tube.   A couple of TaC coated Ta springs inside to keep graphite
pressed against walls of cylinder.
Entry  Monday, March 18, 2019, 15:58, Darwin Ortiz Rosales, ZrC, 43044-5, LP-SIS, Done, Sintering ZrC IMG_3070.JPGIMG_3066.JPG
Monday, March 18, 2019, 15:51
Total number of foils: 555
Total mass of material including graphite foils: 478 grams
Entry  Wednesday, March 13, 2019, 15:43, Marla Cervantes, , 43630-6, , Done, Graphite insert test #4 
 Wednesday, March 13, 2019, 15:41
An uncoated tantalum tube was loaded with a graphite insert (with conical caps).
3 tantalum foils were wrapped around the tantalum tube and a Ta cap was added.
Entry  Thursday, March 07, 2019, 09:22, Darwin Ortiz Rosales, Empty, 40282-4, TARGET BOAT, Done, Transfer tube TaC coating (Legnaro) 
Thursday, March 07, 2019, 09:09
Transfer tube from Legnaro was coated with TaC.
The transfer tube was set in a tantalum boat and wrapped with 3 heat shields,
Entry  Thursday, February 21, 2019, 09:15, Darwin Ortiz Rosales, Empty, 42464-4, HP-FEBIAD, Done,  190225EVAP2Trend.png190225EVAP2Trendb.png
Thursday, February 21, 2019, 09:01
Container coated with TaC and wrapped with 2 Ta heat shields.
Desired temperature= 1900 C, Omega Slope set = 0.990, Auto TGHT at 0.2A/min to reach 400A, TGHT will be tapped up accordingly to reach desired
Entry  Wednesday, February 13, 2019, 10:08, Darwin Ortiz Rosales, , 43630-1 , , Done, Graphite insert test 3b 
 Wednesday, February 13, 2019, 10:04
A previously coated tantalum tube with 3 layers of shielding (Details in e-log 426) was loaded with a graphite insert. 
Entry  Thursday, February 07, 2019, 15:20, Darwin Ortiz Rosales, Empty, 43630-1, , Done, TaC coating/sintering 
Thursday, February 07, 2019, 14:12
Tantalum tube coated with TaC and wrapped with 3 layers of Ta heat-shielding.
Desired temperature= 1900 Celsius (expected TGHT ~445A/7.5V)
Entry  Wednesday, January 23, 2019, 13:06, Marla Cervantes, , 43630-2, , Done, Graphite insert test #3 
 Wednesday, January 23, 2019, 13:01
A previously coated tantalum tube with 3 layers of shielding (Details in e-log
426) was loaded with a graphite insert. 
Entry  Friday, January 18, 2019, 15:11, Darwin Ortiz Rosales, Empty, 43044-5, LP-SIS, Done, TaC coating/sintering (training/online use)  
Friday, January 18, 2019, 15:00
Container was coated with TaC and wrapped with 3 Ta heat shields.
Desired temp = 1900 C, Omega slope set = 0.990, Auto ramping TGHT at 1A/min to reach 400A, TGHT
Entry  Wednesday, January 16, 2019, 11:53, Marla Cervantes, TaC, 43630-2, , Done, TaC coating/sintering for graphite insert test 
 Tuesday, January 15, 2018, 17:30
Tantalum tube was coated with TaC and wrapped with Ta heat-shield (3 layers)
Desired temp = 1900 C (expected TGHT ~445A/7.5V), TBHT will be set fixed at 230A (max).
Entry  Thursday, December 20, 2018, 10:27, Marla Cervantes, , 43630-6, , Done, Tantalum tube heating 
Thursday, December 20, 2018, 10:24
A tantalum tube was loaded in evaporator 2 on Wednesday 19/Dec/2018.
It is going to be heated to 2000 C during 3 weeks 
Entry  Thursday, November 22, 2018, 10:19, Marla Cervantes, , 43630-7 , , Done, Graphite insert test #2 
 Thursday, November 22, 2018, 10:12
A previously sintered tantalum tube with 3 layers of shielding was loaded with a graphite insert.
The tube was loaded in evaporator 2 on Wednesday 21/11/2018 and pumped down