462
|
Monday, October 07, 2019, 09:18 |
Darwin Ortiz Rosales | TaC | | TARGET BOAT | In progress | Sintering TaC coating on endcaps and springs | Friday, October 04, 2019, 11:37
Each endcap is separated with |
|
|
463
|
Tuesday, October 08, 2019, 14:16 |
Aaron Schmidt | SiC | | HP-FEBIAD | In progress | Temp measurements. | Tuesday, October 08, 2019, 14:14: Remove
Flex line HS.
HS: 42752-1 |
|
|
464
|
Thursday, October 17, 2019, 13:53 |
Darwin Ortiz Rosales | TaC | 44062-3 | LP-SIS | In progress | TaC coating/sintering | Thursday, October 17, 2019, 12:00
Ta tube was coated with TaC and wrapped
with Ta heat-shields (3 layers) |
|
|
467
|
Thursday, November 21, 2019, 08:10 |
Aaron Schmidt | SiC | | HP-FEBIAD | In progress | Temperature mapping. | Thursday, November 21, 2019, 08:09:
PS on. Leak issue resolved (Evap 2 Elog 466).
Vacuum @ 4.10e-07T. |
|
|
468
|
Friday, November 22, 2019, 18:32 |
Fernando Maldonado & Marla Cervantes | TaC | | HP-FEBIAD | In progress | TaC coating/sintering | Friday, November 22, 2019, 18:18:
|
|
|
470
|
Monday, November 25, 2019, 11:35 |
Aaron Schmidt | | | | In progress | Flex - line HS installed | Leak noted on previous TaC sintering
on HP FEBIAD # 42464-3.
Swapped out gaskets on HS flex line |
|
|
474
|
Tuesday, December 03, 2019, 08:24 |
Aaron Schmidt | | | LP-FEBIAD | In progress | Temperature mapping. | Tuesday, December 03, 2019, 08:15: Waterlines
opened. Vacuum ok @ 4.06e-07T
Tuesday, December 03, 2019, 08:23: |
|
|
486
|
Monday, June 01, 2020, 12:03 |
Aaron Schmidt | Ta | 44139-13 | LP-SIS | In progress | Ta#60 Conditioning | Ta#60 LP-SIS target
description: |
|
|
492
|
Saturday, July 25, 2020, 08:58 |
Darwin Ortiz Rosales | ZrC | 44139-7-SK | | In progress | ZrC for Luca's experiments | Friday, July 24, 2020, 15:00
Ta tube cotaining 497 ZrC discs |
|
|
496
|
Tuesday, August 11, 2020, 10:17 |
Ferran Boix Pamies | Empty | 41882-1 | TARGET BOAT | In progress | Contamination foils temperature test | The target was prepared and put under vacuum
on 2020-08-10
|
|
|
497
|
Wednesday, August 12, 2020, 08:58 |
Aaron Schmidt | | | | In progress | Install Flex line HS | Flex line HS installed. New SS gaskets.
Wednesday, August 12, 2020, 08:56:
Roughing (Check). |
|
|
512
|
Monday, September 28, 2020, 11:53 |
John Wong | np-SiC | | TARGET BOAT | In progress | np-SiC carbonization | Monday, September 28, 2020, 11:49
6 discs of np-SiC were loaded to
the target boat wrapped with 3 layers of |
|
|
513
|
Tuesday, October 06, 2020, 14:23 |
Aaron Schmidt | Ta | 44508-1 | LP-SIS | In progress | Conditioning Ta#61 | Ta#61 LP-SIS target description:
Total Ta foils = 470 [6x20 packs |
|
|
514
|
Wednesday, October 07, 2020, 12:25 |
Aaron Schmidt | | | | In progress | IEVAP2:TP1 Swap out. | Wednesday, October 07, 2020
TP1 was not spinning up past 4krpm.
Stalling & tripping out. Examined with |
|
|
518
|
Friday, October 16, 2020, 16:31 |
Luca Egoriti | Empty | | TARGET BOAT | In progress | HPOG annealing | Friday, October 16, 2020, 11:30
Target mounted in EVAP2. Pump
down started |
|
|
519
|
Wednesday, October 21, 2020, 14:39 |
Aaron Schmidt | Nb | 44508-2 | LP-SIS | In progress | Conditioning Nb#9 | Nb#9 LP-SIS target description:
|
|
|
546
|
Thursday, April 08, 2021, 08:25 |
Aaron Schmidt | Ta | 44139-10 | LP-SIS | In progress | Conditioning Ta#62 & Flex - line HS installed | Ta#62 LP-SIS target
description: |
|
|
551
|
Wednesday, June 23, 2021, 17:48 |
Aaron Schmidt | Ta | 44691-4 | LP-SIS | In progress | Conditioning Ta#62 (Replacement) | Ta#62 LP-SIS target
description: (REPLACEMENT FOR 44139-10) |
|
|
564
|
Wednesday, November 10, 2021, 18:07 |
Aaron Schmidt | Ta | 44691-11 | LP-SIS | In progress | Conditioning Ta#63 | Ta#63 LP-SIS target description:
|
|
|
577
|
Thursday, June 02, 2022, 16:53 |
Aaron Schmidt | Ta | 44691-12 | LP-SIS | In progress | Conditioning Ta#64 | Ta#64 LP-SIS target