  462   Monday, October 07, 2019, 09:18 Darwin Ortiz RosalesTaC TARGET BOATIn progressSintering TaC coating on endcaps and springs

Friday, October 04, 2019, 11:37

Each endcap is separated with a disc of graphite foil and rolled into packs of 5 within a foil envelope in a target boat.

There are also 3 coated springs, one in between endcaps and two on either end

The boat is wrapped with 2-layers of Ta heatshields.

Chamber pumping down

OMEGA slope = 0.99

Will Tap TGHT up manually to 40 A then autoramp to 400A at 1A/min.

Final desired temperature on OMEGA (tap)= 1800C


Monday, October 07, 2019, 09:08

Sunday night heating started at 1A/ min on TGHT to 54 A

heating paused for 1 hour to allow IGP1 to equillibrate.  Then restarted at 1A/min to 400A as planned. 

This morning IGP1 = 1.3e-06 Torr

TGHT = 401A, 4.2V

OMEGA = 1550 C


Monday, October 07, 2019, 09:36

manually tapping to 1800 C


Monday, October 07, 2019, 14:09

Temperature @ ~1800 for 3.5 hours

TGHT= 495.4, 9.2 V

IGP1= 1.1e-06 Torr Pressure Steady there begin cooling

Cooling @ -2A/min

 

 

 

  463   Tuesday, October 08, 2019, 14:16 Aaron SchmidtSiC HP-FEBIADIn progressTemp measurements.

Tuesday, October 08, 2019, 14:14: Remove Flex line HS. 

HS: 42752-1

Waterlines not open yet.

Tuesday, October 08, 2019, 14:15: roughing.

Tuesday, October 08, 2019, 14:24: Turbo pump on. 

Tuesday, October 08, 2019, 14:32: TP @ speed. 


Wednesday, October 09, 2019, 13:24 

The initial pressure was 3.25e-7 Torr

The current was manually increased to 25 A on both TBHT and TGHT  at a rate of 1 A each 30 s for both heaters.


Wednesday, October 09, 2019, 13:33

At 1 pm an additional ram was made to TGHT 350 A and TBHT 200 at same rate.

  464   Thursday, October 17, 2019, 13:53 Darwin Ortiz RosalesTaC44062-3LP-SISIn progressTaC coating/sintering

Thursday, October 17, 2019, 12:00

Ta tube was coated with TaC and wrapped with Ta heat-shields (3 layers)

Desired temperature= 1900 C (expected TGHT ~430 A), TBHT will be set fixed at 230A (max).

Evap 2 was pumped down on the previous night.

Good vacuum= 3.00 e-5 Torr

Bad vacuum = 5.00 e-5 Torr

Ramped TGHT and TBHT to 40A at 0.5A/min

Initial IGP1= 7.0 e-07 Torr


Thursday, October 17, 2019, 13:53

After pressure stabilization at 40A:

 Autoramp TGHT and TBHT at 1A/min to 400A and 230A respectively.


 Friday, October 18, 2019, 6:20

TGHT = 400A, 6.52V, TBHT= 233A, 4.1V

OMEGA = 1733C

Start autoramp to 430A on TGHT at 1A/min


Friday, October 18, 2019, 7:05

TGHT= 431A, 7.1V

TBHT= 233A, 4.1V

IGP1= 1.13e-06 Torr

OMEGA = 1828 C

Set autoramp to 465 at 1A/min


Friday, October 18, 2019, 11:13

TGHT = 465A, 7.8V, TBHT = 233A, 4.1V

OMEGA = 1865C

(Something is different with the heat dissipation on this target.  Will leave at this current and start cooling at 1200 noon to avoid container strain)


 Friday, October 18, 2019, 12:00

TGHT = 462.7A, 7.8V

TBHT= 233.4A, 4.1V

OMEGA = 1863C

IPG1= 1.02e-06 Torr

Commence cooling at -2A/min for TGHT and -1A/min for TBHT


 Monday, October 21, 2019, 09:11

Pump down and dismount.

 

  467   Thursday, November 21, 2019, 08:10 Aaron SchmidtSiC HP-FEBIADIn progressTemperature mapping.

 Thursday, November 21, 2019, 08:09: PS on. Leak issue resolved (Evap 2 Elog 466). Vacuum @ 4.10e-07T.

Thursday, November 21, 2019, 08:15: Auto-ramping TGHT / TBHT @ 2 A per min to 300 / 150 A. 

  468   Friday, November 22, 2019, 18:32 Fernando Maldonado & Marla Cervantes TaC HP-FEBIADIn progressTaC coating/sintering

 Friday, November 22, 2019, 18:18:

 

 

Friday, November 22, 2019, 18:18: Roughing

Friday, November 22, 2019, 18:23: Turbo on .

Friday, November 22, 2019, 18:32: Turbo at speed 

 

  470   Monday, November 25, 2019, 11:35 Aaron Schmidt   In progressFlex - line HS installed

 Leak noted on previous TaC sintering on HP FEBIAD # 42464-3.

Swapped out gaskets on HS flex line a re-tightened.

Monday, November 25, 2019, 11:31: Roughing.

Monday, November 25, 2019, 11:42: Turbo pump on. 

Monday, November 25, 2019, 13:38: Vacuum @ 7.29e-06T. 

Monday, November 25, 2019, 13:42: Waterlines opened. Vacuum slowly climbed to 7.57e-06T. Waterlines closed / purged. 

Monday, November 25, 2019, 13:47: Vacuum @ 6.83e-06T.

Monday, November 25, 2019, 13:50: Waterlines opened. Vacuum gradually climbed again. Waterlines closed / purged.

Monday, November 25, 2019, 13:51: Turbo pump off. 

Monday, November 25, 2019, 14:41: Vent. Check seals (All on HS line).

Monday, November 25, 2019, 14:48: Roughing. 

Monday, November 25, 2019, 15:06: Vacuum @ 1.22e-04T. Waterlines opened. Vacuum continued to pump down steadily to 8.86e-05T and dropping.

Monday, November 25, 2019, 15:07: Turbo pump off. 

  474   Tuesday, December 03, 2019, 08:24 Aaron Schmidt  LP-FEBIADIn progressTemperature mapping.

Tuesday, December 03, 2019, 08:15: Waterlines opened. Vacuum ok @ 4.06e-07T

Tuesday, December 03, 2019, 08:23: Unable to start due to flow trip? PS off. 

Tuesday, December 03, 2019, 08:25: Turbo & Vac off. 

Tuesday, December 03, 2019, 08:51: Vented. Investigate. Install outer shields. Loose wire found on exterior paddle. Trip gone. Roughing. 

Tuesday, December 03, 2019, 09:03: Turbo pump on. 

Tuesday, December 03, 2019, 09:12: PS on. Vacuum @ 4.46e-05T and dropping. 


Wednesday, December 04, 2019, 10:21: Manually tapped up the TGHT / TBHT to 35 / 10 A.

Wednesday, December 04, 2019, 10:22: Auto-ramping TGHT / TBHT to 300 / 150 A @ 2 A per min. 

FM

Wednesday, December 04, 2019, 13:48:  Auto-ramping TGHT / TBHT to 350 / 175 A @ 2 A per min. 

Wednesday, December 04, 2019, 14:20: Auto-ramping TGHT / TBHT to 400/ 190 A @ 2 A per min.  


Thursday, December 05, 2019, 10:58: Checking the striptool, approximately 30 minutes ago there was an oscillatory behaviour on the TGHT power. It went down to 0 in a very short time.

Temperature measurements were recorded and indicate a 70C difference from before the event.

 Thursday, December 05, 2019, 15:08: Auto-ramping TGHT / TBHT to 450/ 230A @ 2 A per min.  

Thursday, December 05, 2019, 19:05: Checking the striptool, at around 6 pm the TGHT power supply trip and didn't come back.

Thursday, December 05, 2019, 19:06: Drop in temperature indicates the target stop glowing.

Thursday, December 05, 2019, 19:07> Turning off power supply on EPICS and setting the slider to 0A.

I will ramp up TGHT in the morning while in the lab. 


Friday, December 06, 2019, 14:55: Ramping down TBHT to 0A @ 2A/min 


Tuesday, December 10, 2019, 09:11: Manually tapped up the TGHT / TBHT to 35 / 10 A 

Tuesday, December 10, 2019, 09:12:  Auto-ramping TGHT / TBHT to 400/ 230A @ 2 A per min.  

Aborted

Attachment 1: TGHT_weird_behaviour.PNG
TGHT_weird_behaviour.PNG
Attachment 2: IEVAP-WFB1.PNG
IEVAP-WFB1.PNG
Attachment 3: 191205-GHT-trip-1800.PNG
191205-GHT-trip-1800.PNG
  486   Monday, June 01, 2020, 12:03 Aaron SchmidtTa44139-13LP-SISIn progressTa#60 Conditioning

 Ta#60 LP-SIS target description:

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm

Target density =  14.081 g/cm3

Target length = 3.33 cm

Total Mass =  46.891 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven=  445g w/ end caps)

Discs in target are arranged as follows: 1pack / 75singles / 1pack / 100singles / 2packs / 100singles / 1pack / 75singles / 1pack

End caps installed (Expanded). No Ta heat shield added.

https://elog.triumf.ca/TIS/Target+Production/98


Monday, June 01, 2020, 11:38: Roughing.

Monday, June 01, 2020, 12:03: Turbo pump on. 


TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 600A + at 2.0A/min.

Final desired temperature = 1900C.

OMEGA slope = 0.98.

Tuesday, June 02, 2020, 07:13: Omega slope set to 0.98. Power supplies / sources on. vacuum@ 5.13e-07T.

Tuesday, June 02, 2020, 07:16: Manually tap up TGHT / TBHT to 40 / 5 A. Vacuum @ 5.08e-07T.

Tuesday, June 02, 2020, 07:19: Auto-ramping TGHT / TBHT @ 2 A per min to 350 / 150 A. 

Tuesday, June 02, 2020, 10:02: Auto-ramping TGHT / TBHT @ 2 / 1 A per min to 450 / 200 A. Vacuum @ 1.39e-06T. TGHT Voltage= 5.955V. Omega: 1288 deg C.

Tuesday, June 02, 2020, 11:54: Auto-ramping TGHT / TBHT @ 2 / 1 A per min to 500 / 230 A. Vacuum @ 1.85e-06T. TGHT Voltage= 7.998V. Omega: 1528 deg C.

Tuesday, June 02, 2020, 13:16: Auto-ramping TGHT @ 2 A per min to 550 A. Vacuum @ 2.51e-06T. TGHT Voltage= 9.060V. Omega: 1625 deg C. 

Tuesday, June 02, 2020, 13:58: Auto-ramping TGHT @ 2 A per min to 600 A. Vacuum @ 3.53e-06T. TGHT Voltage= 9.060V. Omega: 1728 deg C. 

Tuesday, June 02, 2020, 14:23: Auto-ramping TGHT @ 2 A per min to 625 A. Vacuum @ 5.56e-06T. TGHT Voltage= 11.236V. Omega: 1821 deg C.

Tuesday, June 02, 2020, 14:36: TGHT / TBHT 625 / 230 A. Vacuum @ 6.65e-06T. TGHT Voltage= 11.724V. Omega: 1865 deg C. 

Tap up TGHT manually.

Tuesday, June 02, 2020, 14:48: TGHT / TBHT 643 / 230 A. Vacuum @ 7.24e-06T. TGHT Voltage= 12.129V. Omega: 1901-1903 deg C.  

Desired temperature = 1900C reached.

Tuesday, June 02, 2020, 22:20: TGHT / TBHT 643 / 230 A. Vacuum @ 2.05e-06T. TGHT Voltage= 12.212V. Omega: 1901-1903 deg C. 

Tuesday, June 02, 2020, 22:22: Auto-Cooling @ 1 A per min. 


Wednesday, June 03, 2020, 06:08: TBHT @ 0. TGHT set for Auto-Cooling @ 2 A per min.

Wednesday, June 03, 2020, 11:38: PS off. Turbo pump off. 

Wednesday, June 03, 2020, 12:40: Venting. 

  492   Saturday, July 25, 2020, 08:58 Darwin Ortiz RosalesZrC44139-7-SK In progressZrC for Luca's experiments

Friday, July 24, 2020, 15:00

Ta tube cotaining 497 ZrC discs wrapped with Ta heat-shields (3 layers)

Desired temperature= 1800C (expected TGHT 410 A), TBHT will be set fixed at 230A (max).

good vacuum = 3.00 e-05 Torr

bad vacuum = 5.00 e-05 Torr

Evap 2 was left to pump down over night.


Saturday, July 25, 2020, 08:57

IGP1= 8.7 e-07 Torr

Start ramp at 0.25 A/min to 20 A on TGHT 


Saturday, July 25, 2020, 10:07

IGP1= 2.7e -06 Torr

Set ramp target to 30 A 


Wednesday, July 29, 2020, 13:11 

OMEGA reading 1700 C at 430 A during the night.  It was kept at this temperature for 3.5 hours.  The OMEGA slope was not changed from 0.990

when IGP1 = 1.2 e-06 Torr and stable, cooling was started at -3A/min at 9 am on this day.

IGP1= 2.2 e-07 Torr now at time of dismounting

 

  496   Tuesday, August 11, 2020, 10:17 Ferran Boix PamiesEmpty41882-1TARGET BOATIn progressContamination foils temperature test

The target was prepared and put under vacuum on 2020-08-10

 

2020-08-11 10:16am The pressure is 1e-6Torr. Leak checked performed, water on no problem. Starting to set target heating curve. 1A/10s up to 300A 

2020-08-11 11:23am target at 300A-1200degC Temperatures on exposed foil show to be higher than expected. 300degC already, 70degC on covered by foil thermocouple. Putting 50 more amps at 1A/10s 

2020-08-11 12:11pm target at 350A-1340degC. 350degC on exposed thermocouple. Ramping to 400A 1A/10s.

2020-08-11 12:28pm target at 400A-1420degC. 400degC on exposed thermocouple. Ramping to 450A 1A/10s.

  497   Wednesday, August 12, 2020, 08:58 Aaron Schmidt   In progressInstall Flex line HS

Flex line HS installed. New SS gaskets. 

Wednesday, August 12, 2020, 08:56: Roughing (Check).

Wednesday, August 12, 2020, 09:17: Ready for turbo pump.

Wednesday, August 12, 2020, 09:20: BP1 Off. Venting. 

  512   Monday, September 28, 2020, 11:53 John Wongnp-SiC TARGET BOATIn progressnp-SiC carbonization

Monday, September 28, 2020, 11:49

6 discs of np-SiC were loaded to the target boat wrapped with 3 layers of heat shields.

Desired temperature at 1500 C, (As per e-log 414/416, TGHT = 450A/7.31V, 3.28kW) 

Omega slope set at 1.05 (for carbide)

Good vac = 3.0e-5 Torr,

Bad vac = 5.0e-5 Torr.

Pumping down in progress


 Monday, September 28, 2020, 21:44

Pressure at 1e-6 Torr.  Initiated autoramping at 0.2A/min to reach 300 A.  Monitor temp.


 Wednesday, September 30, 2020, 11:39

TGHT reached to 300 A/ 4.5V, temp at 1130 C.  No coating on windows.

Continue to ramp up 330A.  Monitor temp.


 Wednesday, September 30, 2020, 16:38

TGHT reached 330 A / 5.04 V, temp at 1190 C. 

Ramp up to 400 A. Current pressure at 9.8 e-7 Torr.


Thursday, October 01, 2020, 10:28

TGHT reached 400 A/ 6.3V, temp at 1320 C.  Continue to ramp up to 450 A.


 Thursday, October 01, 2020, 16:44

TGHT reached to 450 A/ 7.4 V.  TEmp at 1500 C. 

Pressure at 1.35 e-6 Torr and coming down.   Continue to hold TGHT at 1500 C for at least 24 hr.


 Sunday, October 04, 2020, 16:49

TGHT has been holding at 450 A/ 7.3 V for nearly 3 days; temp has gone up and stabilized at 1554 C; pressure at 2.13 e -7 Torr.

Initiated cooling down at -2A/min.


 Monday, October 05, 2020, 10:02

Chamber vented.


 

  513   Tuesday, October 06, 2020, 14:23 Aaron SchmidtTa44508-1LP-SISIn progressConditioning Ta#61

Ta#61 LP-SIS target description:

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm

Target density =  12.76 g/cm3

Target length = 3.4 cm

Total Mass = 43.388 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven=  464 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 100 singles / 1pack / 75 singles / 2packs / 75 singles / 1pack / 100 singles / 1pack

End caps installed (not yet expanded). No Ta foil heat shield added 


TBHT will be ramped up to 230A at 1.0A/min.

TGHT will be ramped up to 600A + at 2.0A/min.

Final desired temperature = 1900C.

OMEGA slope = 0.98.

Tuesday, October 06, 2020, 14:17: Roughing.

Tuesday, October 06, 2020, 14:36: Turbo pump on.

Tuesday, October 06, 2020, 14:43: Turbo pump not spinning up. Holding at 4 krpm. Will need to vent and Troubleshoot in the am.  


Attempted to run the turbo pump again. Only runs to 4 krpm. Shut down to avoid trip. Vent & remove Flex-line HS. Change all the SS gaskets. Re-install Flex-line HS w/ Ta#61.

Wednesday, October 07, 2020, 09:16: Roughing. 

Wednesday, October 07, 2020, 09:32: Turbo pump on. 

Wednesday, October 07, 2020, 10:05: Multiple attempts made to spin up the turbo pump. TP1 holds at 4 krpm, occasionally to 5 krpm, times out & trips. 

Wednesday, October 07, 2020, 10:08: Shut off TP1 & backing pump. 

Replaced TP1. https://elog.triumf.ca/TIS/Evaporator_2/514

Wednesday, October 07, 2020, 13:45: TP1 off. Soft start function off. Remote start configuration initiated. TP1 on @ 38krpm. OK. 

Wednesday, October 07, 2020, 13:47: Vacuum @ 1.31e-05T.

Wednesday, October 07, 2020, 13:49: Waterlines opened. Vacuum ok @ 1.27e-05T.

Wednesday, October 07, 2020, 13:50: PS switched on. 

Wednesday, October 07, 2020, 15:24: Slope set @ 0.98. Vacuum @ 3.30e-06T.

Wednesday, October 07, 2020, 15:26: TGHT / TBHT on. Manually tap up to 10 / 10 A.

Wednesday, October 07, 2020, 15:28: Auto-ramping TGHT / TBHT to 300 / 150 A @ 2 / 1 A per min. 


Thursday, October 08, 2020, 05:23: Vacuum @ 7.00e-07T. 

Thursday, October 08, 2020, 05:25: Auto-ramping TGHT / TBHT to 450 / 200 A @ 2 / 1 A per min. Temp @ 996 C

Thursday, October 08, 2020, 06:44: Auto-ramping TGHT / TBHT to 550 / 230 A @ 2 / 1 A per min. Temp @ 1426 C

Thursday, October 08, 2020, 07:43: Vacuum @ 3.88e-06T. Temp @ 1685 C. 

Thursday, October 08, 2020, 07:45: Auto-ramping TGHT to 600 A @ 2 A per min.

Thursday, October 08, 2020, 08:42: Auto-ramping TGHT to 630 A @ 2 A per min. Vacuum @ 4.01e-06T. Temp @ 1800 C. 

Thursday, October 08, 2020, 09:07: Auto-ramping TGHT to 645 A @ 2 A per min. Vacuum @ 4.91e-06T. Temp @ 1851 C.  

Thursday, October 08, 2020, 09:19: Auto-ramping TGHT to 655 A @ 2 A per min. Vacuum @ 5.37e-06T. Temp @ 1879 C.   

Thursday, October 08, 2020, 09:28: TGHT @ 650-657 A. Vacuum @ 5.70e-06T. Temp @ 1901 C. Desired temperature reached*

Thursday, October 08, 2020, 09:59: TGHT @ 650-657 A. Vacuum @ 4.64e-06T. Temp @ 1903 C.

Thursday, October 08, 2020, 10:01:  Auto-cooling TGHT / TBHT @ -3 / -2 A per min. 

Thursday, October 08, 2020, 13:57: TP1 / PS off.

Thursday, October 08, 2020, 14:08: Venting. 

Thursday, October 08, 2020, 14:15: Flex-Line HS removed w/ Ta#61. 

  514   Wednesday, October 07, 2020, 12:25 Aaron Schmidt   In progressIEVAP2:TP1 Swap out.

 Wednesday, October 07, 2020

TP1 was not spinning up past 4krpm. Stalling & tripping out. Examined with Vacuum group, appears to be starting to seize. Exchange turbo pump.

Serial# 500937

Wednesday, October 07, 2020, 12:25: TP1 Exchanged. 

Wednesday, October 07, 2020, 12:38: Roughing. 

Wednesday, October 07, 2020, 13:55: Soft start initiated. Steps up krpm every 5 min. 10 steps.

Wednesday, October 07, 2020, 13:22 @ 24 krpm.  

Wednesday, October 07, 2020, 13:42: TP1 at speed. 38 krpm. 

Wednesday, October 07, 2020, 13:45: TP1 off. Soft start function off. Remote start configuration initiated. TP1 on. OK. 

  518   Friday, October 16, 2020, 16:31 Luca EgoritiEmpty TARGET BOATIn progressHPOG annealing

Friday, October 16, 2020, 11:30

 Target mounted in EVAP2. Pump down started

Friday, October 16, 2020, 12:05

Pressure goes up. Checked with Ferran and he says that the valve IEVAP2:RV1 automatically closes sometimes. WEIRD, to be chacked.

Friday, October 16, 2020, 15:20

IGP2 bottoms at 0.2T, and doesn't increase recover if I close RV1 while it shouldn't (as shown before). --> Vented to restart from scratch

 

Friday, October 16, 2020, 15:45

 

Pumped down again, vacuum went down to 0.16 and then started raising until ~0.18. This time the valve was open indeed! opening and closing the valve had no effect on the vacuum as if the  booster pump was not effective

 

 

Friday, October 16, 2020, 16:27

Tried a THIRD time, this time effectively, to turn the turbo ON. I managed to, but the turbo makes weird spinning sounds every ~30 sec. Moreover, its pumping down plot seems quite weird  - see spike UP while pumping. Could it be related to a dysfunction of the backing pump?

 

  519   Wednesday, October 21, 2020, 14:39 Aaron SchmidtNb44508-2LP-SISIn progressConditioning Nb#9

 Nb#9 LP-SIS target description:

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm

Target density =  7.24 g/cm3

Target length = 3.5 cm

Total Mass = 25.343 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven=  425 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack

End caps installed (not yet expanded). No Ta foil heat shield added.


Final desired temperature = 1900C.

OMEGA slope = 0.98.

Wednesday, October 21, 2020, 14:09: Roughing. 

Wednesday, October 21, 2020, 14:32: Turbo pump on. 

Wednesday, October 21, 2020, 15:29: Waterlines opened. Vacuum ok @ 1.05E-05T. 

Wednesday, October 21, 2020, 15:30: TGHT / TBHT PS on. Slope Set.

Wednesday, October 21, 2020, 19:06: Auto-ramping TGHT / TBHT to 300 / 100 @ 1 A per min. Vacuum @ 1.85e-06T.


Thursday, October 22, 2020, 07:26: Auto-ramping TGHT / TBHT to 500 / 200 @ 2 A per min. Vacuum @ 7.61e-07T.

Thursday, October 22, 2020, 11:28: Auto-ramping TGHT / TBHT to 580 / 230 @ 2 A per min. Vacuum @ 1.53e-06T. The Omega IR2C is back. Temp @ 1576 deg C.

Thursday, October 22, 2020, 12:22: Auto-ramping TGHT to 625 A @ 2 A per min. Vacuum @ 2.47e-06T. Temp @ 1734 C.  

Thursday, October 22, 2020, 12:48: Auto-ramping TGHT to 645 A @ 2 A per min. Vacuum @ 3.11e-06T. Temp @ 1815 C.   

Thursday, October 22, 2020, 13:10: Auto-ramping TGHT to 660 A @ 2 A per min. Vacuum @ 3.39e-06T. Temp @ 1851 C.  

Thursday, October 22, 2020, 13:25: Manually tap up TGHT until 1900 C. Vacuum @ 3.53e-06T.

Thursday, October 22, 2020, 13:30: TGHT @ 673 A. Temp @ 1903 C. Vacuum @  3.79e-06T.

Thursday, October 22, 2020, 14:00: Auto-cooling @ 1 A per min. 


Friday, October 23, 2020, 07:50: PS off. Turbo pump off. Purge waterline. 

Friday, October 23, 2020, 09:02: Venting. 

  546   Thursday, April 08, 2021, 08:25 Aaron SchmidtTa44139-10LP-SISIn progressConditioning Ta#62 & Flex - line HS installed

 Ta#62 LP-SIS target description:

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm

Target density = 13.96 g/cm3

Target length = 3.4 cm

Total Mass = 47.461 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven= 445 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack

End caps installed (expanded). No Ta foil heat shield added


TBHT will be ramped up to 230A 

TGHT will be ramped up to 600A +

Final desired temperature = 1900C.

OMEGA slope = 0.98.

Thursday, April 08, 2021, 08:24: Roughing.

Thursday, April 08, 2021, 09:06: Vent & check. Roughed to only 20 T. 

Thursday, April 08, 2021, 09:18: Roughing. Loose flange found. Left side wall / upper right. 

Thursday, April 08, 2021, 09:34: TP1 on. 

Thursday, April 08, 2021, 14:41: Vacuum @ 1.65e-06T. Waterline opened.

Thursday, April 08, 2021, 14:46: Vacuum ok. Power on. TGHT / TBHT to 20 / 15 A. Ok.

Thursday, April 08, 2021, 14:50: Auto-ramping TGHT / TBHT to 300 / 100 A @ 2 A per min.


Friday, April 09, 2021, 05:08: Vacuum @ 6.23e-07T. Temp @ 1195 C. Auto-ramping TGHT / TBHT to 400 / 150 A @ 2 A per min.

Friday, April 09, 2021, 06:01: Vacuum @ 9.64e-07T. Temp @ 1447 C. Auto-ramping TGHT / TBHT to 500 / 200 A @ 2 A per min.

Friday, April 09, 2021, 07:23: Vacuum @ 1.92e-06T. Temp @ 1671 C. Auto-ramping TGHT / TBHT to 600 / 230 A @ 2 / 1 A per min.  

Friday, April 09, 2021, 08:40: Vacuum @ 3.96e-06T. Temp @ 1877 C. Auto-ramping TGHT / TBHT to 620 A @ 1 A per min.   

Friday, April 09, 2021, 09:10: Vacuum @ 3.60e-06T. Temp @ 1915 C. Drop TGHT from 620 A to 610 A manually.

TGHT to 613 A manually.

Friday, April 09, 2021, 09:15: Vacuum @ 3.60e-06T. Temp @ 1902 C. TGHT / TBHT @ 613 A / 230 A. Desired temperature reached.

Friday, April 09, 2021, 12:08: Auto-cooling @ 1 A per min initiated. 


Monday, April 12, 2021, 07:23: PS / Turbo pump / roughing pump off. 

Monday, April 12, 2021, 08:03: Vented. 

  551   Wednesday, June 23, 2021, 17:48 Aaron SchmidtTa44691-4LP-SISIn progressConditioning Ta#62 (Replacement)

 Ta#62 LP-SIS target description: (REPLACEMENT FOR 44139-10)

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm

Target density = 14.29 g/cm3

Target length = 3.4 cm

Total Mass = 48.602 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven= 456 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack

End caps installed (Not expanded). No Ta foil heat shield added


Wednesday, June 23, 2021, 17:46: Roughing.

Wednesday, June 23, 2021, 18:03: TP1 on.

Wednesday, June 23, 2021, 18:09: TP1 @ speed. Vacuum @ 1.53e-04T & dropping.


TBHT will be ramped up to 230A 

TGHT will be ramped up to 600A +

Final desired temperature = 1900C.

OMEGA slope = 0.98.

Thursday, June 24, 2021, 07:38: PS on.  

Thursday, June 24, 2021, 07:45: TGHT / TBHT tapped up to 10 A. Slope @ 0.98

Thursday, June 24, 2021, 07:46: Auto Ramping TGHT / TBHT to 350 / 150 A @ @ A per min.

Thursday, June 24, 2021, 10:47: TGHT / TBHT @ 350 / 150 A. Auto Ramping TGHT / TBHT to 580 / 230 A @ @ A per min. Temp @ 1120 C

Thursday, June 24, 2021, 12:59: TGHT / TBHT @ 580 / 230 A. Vacuum @ 8.24e-06T. Temp @ 1717 C. Auto-ramping TGHT to 600 A @ 2 A per min.   

Thursday, June 24, 2021, 13:10: Vacuum @ 8.83e-06T. Temp @ 1758 C. Auto-ramping TGHT to 620 A @ 2 A per min. 

Thursday, June 24, 2021, 13:21: Vacuum @ 1.0e-05T. Temp @ 1798 C. Auto-ramping TGHT to 645 A @ 2 A per min.  

Thursday, June 24, 2021, 13:37: Vacuum @ 1.15e-05T. Temp @ 1845 C. Tap up TGHT to 650 manually.

Thursday, June 24, 2021, 13:45: Vacuum @ 1.21e-05T. Temp @ 1875 C. Tap up TGHT to 665+ manually.

Thursday, June 24, 2021, 13:47: Vacuum @ 1.34e-05T. Temp @ 1901 C. Tapped up TGHT to 677 manually. Desired temperature reached.

Thursday, June 24, 2021, 13:51: Auto-cooling @ 2A per min 


Friday, June 25, 2021, 05:30: TP1 off. BP1 off.    

Friday, June 25, 2021, 07:36: Venting. 

Attachment 1: Ta#62_conditioning_-_Evap_2_-_44691-4.docx
  564   Wednesday, November 10, 2021, 18:07 Aaron SchmidtTa44691-11LP-SISIn progressConditioning Ta#63

Ta#63 LP-SIS target description: 

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.025mm

Target density = 15.38 g/cm3

Target length = 3.4 cm

Total Mass = 52.296 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven= 457 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack

End caps installed (Not expanded). No Ta foil heat shield added

https://elog.triumf.ca/TIS/Target+Production/114


TBHT will be ramped up to 230A 

TGHT will be ramped up to 600A +

Final desired temperature = 1900C.

OMEGA slope = 0.98.


Wednesday, November 10, 2021, 18:05: Roughing. 

Wednesday, November 10, 2021, 18:14: Omega Laser set. On end cap / ok. Slope = 0.980 

Wednesday, November 10, 2021, 18:24: Turbo pump on.

Wednesday, November 10, 2021, 18:25: RV1 valve hissing. Stop TP. Reset, open / close RV1 multiple times. Hissing stopped on its own. Won't affect the pump down, letting pressure out, not in. Will need to replace later.

Wednesday, November 10, 2021, 18:27: Turbo pump on. 

Wednesday, November 10, 2021, 18:32: TP ok. PS on. 


Thursday, November 11, 2021, 11:08: Vacuum @ 4.56e-07T. Auto ramping TGHT / TBHT to 580 / 230 A @ 2A per minute.

Thursday, November 11, 2021, 13:49: TGHT / TBHT @ 313 / 230 A. Vacuum @ 1.46e-06T. Temperature @ 1051 C. Auto ramp continues.

Thursday, November 11, 2021, 16:55: TGHT / TBHT @ 580 / 230 A. Vacuum @ 5.11e-06T. Temperature @ 1621 C. Auto ramp TGHT to 610 A @ 2 A per min.

Thursday, November 11, 2021, 17:13: TGHT / TBHT @ 610 / 230 A. Vacuum @ 6.54e-06T. Temperature @ 1670 C. Auto ramp TGHT to 630 A @ 2 A per min.

Thursday, November 11, 2021, 17:32: TGHT / TBHT @ 630 / 230 A. Vacuum @ 7.82e-06T. Temperature @ 1709 C. Auto ramp TGHT to 650 A @ 2 A per min. 

Thursday, November 11, 2021, 18:49: TGHT / TBHT @ 650 / 230 A. Vacuum @ 7.40e-06T. Temperature @ 1758 C. Auto ramp TGHT to 665 A @ 2 A per min. 

Thursday, November 11, 2021, 19:02: TGHT / TBHT @ 665 / 230 A. Vacuum @ 8.37e-06T. Temperature @ 1790 C. Auto ramp TGHT to 685 A @ 2 A per min. 

Thursday, November 11, 2021, 19:22: TGHT / TBHT @ 685 / 230 A. Vacuum @ 9.56e-06T. Temperature @ 1830 C. Auto ramp TGHT to 700 A @ 2 A per min. 

Thursday, November 11, 2021, 19:41: TGHT / TBHT @ 700 / 230 A. Vacuum @ 1.18e-05T. Temperature @ 1870 C. Manually tap up to 705 A

Thursday, November 11, 2021, 19:43: TGHT / TBHT @ 705 / 230 A. Vacuum @ 1.25e-05T. Temperature @ 1885 C. Manually tap up to 710 A

Thursday, November 11, 2021, 19:44: TGHT / TBHT @ 710 / 230 A. Vacuum @ 1.34e-05T. Temperature @ 1890 C. Manually tap up to 715 A 

Thursday, November 11, 2021, 19:46: TGHT / TBHT @ 715 / 230 A. Vacuum @ 1.75e-05T. Temperature @ 1898 C. Manually tap up to 717 A

Thursday, November 11, 2021, 19:46: TGHT @ 717 A. Temperature @ 1901 C. Temperature reached.

Thursday, November 11, 2021, 19:48: Begin auto-cooling @ 2 A per min.


Friday, November 12, 2021, 06:13: PS off. TP1 off. 

  577   Thursday, June 02, 2022, 16:53 Aaron SchmidtTa44691-12LP-SISIn progressConditioning Ta#64

 Ta#64 LP-SIS target description: 

Total Ta foils = 470 [6x20 packs + 350 single discs]

Foil Thickness = 0.0254mm (0.0010") Measured.

Target density = 12.005 g/cm3

Target length = 3.35 cm

Total Mass = 40.2166 g [Incl foils + Ta wire on 6 packs]

Total mass w/ Target oven= 446 g (w/ end caps)

Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack

End caps installed (Not expanded). No Ta foil heat shield added


Final desired temperature = 1900C.

Thursday, June 02, 2022, 16:49: Roughing 

Thursday, June 02, 2022, 17:02: OMEGA slope = 0.98. 

Thursday, June 02, 2022, 17:10: TP1 on.

Thursday, June 02, 2022, 17:21: TP1 is up to speed. PS on. 


Friday, June 03, 2022, 05:22: Auto-ramping TGHT / TBHT to 500 / 200 A @ 2 A per min. Vacuum @ 1.78e-06T.

Friday, June 03, 2022, 08:59: TGHT / TBHT @ 424 / 200 A. Vacuum @ 3.42e-06T. Temperature @ 1318 C. Auto ramp ongoing.

Friday, June 03, 2022, 09:40: TGHT / TBHT @ 500 / 200 A. Vacuum @ 4.47e-06T. Temperature @ 1469 C. Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min

Friday, June 03, 2022, 10:47: TGHT / TBHT @ 580 / 230 A. Vacuum @ 6.26e-06T. Temperature @ 1620 C. Auto-ramping TGHT to 600 @ 2 A per min 

Friday, June 03, 2022, 11:08: TGHT / TBHT @ 600 / 230 A. Vacuum @ 6.54e-06T. Temperature @ 1655 C. Auto-ramping TGHT to 630 @ 2 A per min  

Friday, June 03, 2022, 11:30: TGHT / TBHT @ 630 / 230 A. Vacuum @ 7.73e-06T. Temperature @ 1708 C. Auto-ramping TGHT to 650 @ 2 A per min

Friday, June 03, 2022, 11:45: TGHT / TBHT @ 650 / 230 A. Vacuum @ 8.32e-06T. Temperature @ 1748 C. Auto-ramping TGHT to 660 @ 2 A per min

Friday, June 03, 2022, 11:53: TGHT / TBHT @ 660 / 230 A. Vacuum @ 8.83e-06T. Temperature @ 1755 C. Auto-ramping TGHT to 670 @ 2 A per min

Friday, June 03, 2022, 12:05: TGHT / TBHT @ 670 / 230 A. Vacuum @ 9.03e-06T. Temperature @ 1780 C. Auto-ramping TGHT to 680 @ 2 A per min

Friday, June 03, 2022, 12:11: TGHT / TBHT @ 680 / 230 A. Vacuum @ 9.14e-06T. Temperature @ 1795 C. Auto-ramping TGHT to 700 @ 2 A per min 

Friday, June 03, 2022, 12:23: TGHT / TBHT @ 700 / 230 A. Vacuum @ 9.50e-06T. Temperature @ 1822 C. Auto-ramping TGHT to 720 @ 2 A per min

Friday, June 03, 2022, 12:29: TGHT / TBHT @ 720 / 230 A. Vacuum @ 1.00e-05T. Temperature @ 1853 C. Auto-ramping TGHT to 730 @ 2 A per min

Friday, June 03, 2022, 12:36: TGHT / TBHT @ 725 / 230 A. Vacuum @ 1.04e-05T. Temperature @ 1860 C. Manually tap up TGHT to reach desired temperature

Friday, June 03, 2022, 13:04: TGHT / TBHT @ 760 / 230 A. Vacuum @ 1.07e-05T. Temperature @ 1901 C. Desired temperature reached

 

Friday, June 03, 2022, 13:13: Auto-cooling at 2 A per min. 

 


Monday, June 06, 2022, 07:07: PS off. BV1 closed & TP1 off.

Monday, June 06, 2022, 08:47: Venting. 