  Evaporator_2, Page 11 of 25  Not logged in ELOG logo
Entry  Tuesday, March 10, 2020, 09:34, Darwin Ortiz Rosales, Empty, 42218-8, HP-SIS, Done, TaC coating/sintering SiC#40.PNG
Monday, March 9, 2020, 03:15
Container coated with TaC and wrapped with 3 Ta heat shields.
Desired temperature= 1900 C, Omega Slope set = 0.990, Auto TGHT at   0.2A/min to reach 400A, TGHT will be tapped up accordingly to reach   desired
Entry  Wednesday, March 04, 2020, 14:33, Aaron Schmidt, , , , Maintenance, PS swap out 
 The TGHT PS was found to be defective.
It was uninstalled w/ Joel S: I2020-02-28-2. 
Entry  Tuesday, December 03, 2019, 08:24, Aaron Schmidt, , , LP-FEBIAD, In progress, Temperature mapping. TGHT_weird_behaviour.PNGIEVAP-WFB1.PNG191205-GHT-trip-1800.PNG
Tuesday, December 03, 2019, 08:15: Waterlines opened. Vacuum ok @ 4.06e-07T
Tuesday, December 03, 2019, 08:23: Unable to start due to flow trip? PS off. 
Tuesday, December 03, 2019, 08:25: Turbo & Vac off. 
Entry  Tuesday, November 26, 2019, 15:21, Darwin Ortiz Rosales, SiC, 42464-3, HP-FEBIAD, Done, Conditioning of SiC discs (sintering) (RUSH) HPFIBIAD20191124-SinteringTaC.PNG
Tuesday, November 26, 2019, 14:53
Total number of foils: 504
Total length packed 17.4 cm
    Reply  Wednesday, November 27, 2019, 17:45, John Wong, SiC, 42464-3, HP-FEBIAD, Done, Conditioning of SiC discs (sintering) (RUSH) SiC_42464-3_RUSH_400A.JPG


    
        
            Darwin Ortiz Rosales wrote:
        
        
            
            Tuesday, November 26, 2019, 14:53
Entry  Tuesday, November 26, 2019, 15:43, Anders Mjos, SiC, 42464-3, HP-FEBIAD, Problems resolved, Water to vacuum leak on heat shield line 
This morning, the vacuum responded to shutting of the water of the heat shield circuit (leak rate without pumping leveling out). The vacuum chamber was
vented and the heat shield with flexible lines was replaced with another heat shield with fixed lines. The chamber was again pumped down and water opened
at ~150 mTorr to test the leak up rate without pumping. No leaks apparent, so continued pumping down with turbo pump. At a vacuum of about 1E-6 Torr the
Entry  Monday, November 25, 2019, 11:35, Aaron Schmidt, , , , In progress, Flex - line HS installed 
 Leak noted on previous TaC sintering on HP FEBIAD # 42464-3.
Swapped out gaskets on HS flex line a re-tightened.
Monday, November 25, 2019, 11:31: Roughing.
Entry  Saturday, November 23, 2019, 14:03, Darwin Ortiz Rosales, TaC, 42464-3, HP-FEBIAD, Done, TaC coating/sintering HPFIBIAD20191124.PNG
12.3
Saturday, November 23, 2019, 14:00
Container coated with TaC and wrapped with 3 Ta heat shields.
Entry  Friday, November 22, 2019, 18:32, Fernando Maldonado & Marla Cervantes , TaC, , HP-FEBIAD, In progress, TaC coating/sintering 
 Friday, November 22, 2019, 18:18:
 
 
Entry  Thursday, November 21, 2019, 08:10, Aaron Schmidt, SiC, , HP-FEBIAD, In progress, Temperature mapping. 
 Thursday, November 21, 2019, 08:09: PS on. Leak issue resolved (Evap 2 Elog 466). Vacuum @ 4.10e-07T.
Thursday, November 21, 2019, 08:15: Auto-ramping TGHT / TBHT @ 2 A per min to 300 / 150 A. 
Entry  Friday, November 15, 2019, 13:26, Aaron Schmidt, SiC, , HP-FEBIAD, Problems resolved, Temp map testing - 1. (Leak issue) Test_FEBIAD_2019_-_Nov_-_Leak.docxEvap_2_cooling_-_1.jpgTest_FEBIAD_Left_HS_cooling_line_-_1.jpgTest_FEBIAD_Left_HS_cooling_line_-_2.jpg
 HS 42752-5 - Setup for Temperature mapping.
Friday, November 15, 2019, 13:26: Roughing. 
Friday, November 15, 2019, 13:36: Turbo pump on. 
Entry  Monday, November 04, 2019, 14:25, Darwin Ortiz Rosales, Endcaps, 40282-4, TARGET BOAT, Done,  Nov4CapCoating.PNG

Monday, November 04, 2019, 14:19 
Each endcap is separated with a disc of graphite foil and rolled into packs one pack of 4 and
one pack of 8 within a foil envelope in a target boat.
Entry  Thursday, October 17, 2019, 13:53, Darwin Ortiz Rosales, TaC, 44062-3, LP-SIS, In progress, TaC coating/sintering 
Thursday, October 17, 2019, 12:00
Ta tube was coated with TaC and wrapped with Ta heat-shields (3 layers)
Desired temperature= 1900 C (expected TGHT ~430 A), TBHT will be set fixed at 230A (max).
Entry  Tuesday, October 08, 2019, 14:16, Aaron Schmidt, SiC, , HP-FEBIAD, In progress, Temp measurements. 
Tuesday, October 08, 2019, 14:14: Remove Flex line HS. 
HS: 42752-1
Waterlines not open yet.
Entry  Monday, October 07, 2019, 09:18, Darwin Ortiz Rosales, TaC, , TARGET BOAT, In progress, Sintering TaC coating on endcaps and springs 
Friday, October 04, 2019, 11:37
Each endcap is separated with a disc of graphite foil and rolled into packs of 5 within a foil
envelope in a target boat.
Entry  Thursday, October 03, 2019, 09:26, Darwin Ortiz Rosales, TaC, 44062-6, LP-SIS, Done, TaC coating/sintering 
Thursday, October 03, 2019, 08:58
Ta tube was coated with TaC and wrapped with Ta heat-shields (3 layers)
Initial weight including heat-shields = 427 g
Entry  Friday, September 27, 2019, 18:18, Marla Cervantes, Nb, , TARGET BOAT, Done, Conditioning NB samples for Edward  Nb-finalTemp.JPGNb-arrangement.jpg
Wednesday, September 25, 2019, 18:06
Target boat with a layer of niobium foil on the bottom is used to heat up Nb samples to 1400 C for 4 hrs.
The niobium samples are wrapped in a Nb foil.
Entry  Thursday, September 26, 2019, 14:03, Aaron Schmidt, Nb, 41882-3, TARGET BOAT, In progress, HS swap & test Nb target 
 HS# 42752-7
Thursday, September 26, 2019, 13:46: Remove Flexible lines HS
Thursday, September 26, 2019, 14:03: Assy installed.
Entry  Tuesday, September 17, 2019, 13:25, Aaron Schmidt, , , LP-SIS, Problems resolved, Turbo pump / roughing troubleshoot. 
Swapped out VCRs on HS to tray connection. (Right one felt slightly off)
Tuesday, September 17, 2019, 13:23: roughing.
Tuesday, September 17, 2019, 13:32: Turbo pump on. 
Entry  Monday, September 16, 2019, 14:50, Aaron Schmidt, Ta, 44062-5, LP-SIS, In progress, Conditioning Ta#59 Ta#59_Evap_2_Conditioning..docx
 Ta#59 LP-SIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm
Entry  Wednesday, September 11, 2019, 15:16, Marla Cervantes, , 44062-4, LP-SIS, Done, TaC coated target container calibration/conditioning  A.JPGB.JPG
 Wednesday, September 11, 2019, 15:12
A target container coated with TaC elog 455 was loaded with an empty graphite
cartridge and set it in the EVAP2