The TGHT PS was found to be defective.
It was uninstalled w/ Joel S: I2020-02-28-2.
It was replaced with the conditioning station PS & connected. The chiller is not required and has been unplugged.
Wednesday, March 04, 2020, 14:00. Controls Involved (PS still locked out via main breaker)
Wednesday, March 04, 2020, 14:31: Water supplies opened. All ok except Chiller (Disconnected from PS, but not the supply/return, do not open Chiller lines)
Controls work ongoing.
Thursday, March 05, 2020 (Darwin)
Gelo finished installation of the other power supply S:_____________________.
It was tested and proved to be operational and epics controlled. Tested up to 60A
Chiller interlock was removed as it is no longer needed.
Will wait for Aaron to swap FEBIAD assembly in EVAP 2.
|