Thursday, February 18, 2016, 15:42, Laura Lambert, UC2, 41077-1, LP-SIS, In progress, Conditioning UCx#15
|
Thursday, February 18, 2016, 15:34
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block - same method |
Friday, February 26, 2016, 10:27, John Wong, UC2, 41077-1, LP-SIS, In progress, Conditioning UCx#15
|
Laura Lambert wrote:
Thursday, February 18, 2016, 15:34 |
Monday, February 29, 2016, 16:16, Laura Lambert, UC2, 41077-1, LP-SIS, Done, Conditioning UCx#15
|
John Wong wrote:
|
Thursday, December 10, 2015, 10:59, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, 1stepUCx project - round2
|
Thursday, December 10, 2015, 08:54
Filled graphite tube with 34 UO2/C discs cast onto graphite.
34 discs = 4.10g |
Friday, December 04, 2015, 15:06, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, 1stepUCx project - round1
|
Wednesday, December 02, 2015, 14:08
UO2/C was cast onto a graphite sheet in the fume hood and let dry.
Initial UO2 powder used = 25.11g (Inventory R-00835A, UO2 + bottle = 243.44g before use) |
Thursday, October 15, 2015, 16:05, John Wong, UC2, 41077-5, LP-SIS, In progress, Conditioning UCx#14
|
Thursday, October 15, 2015, 15:52
Target container previously sintered with TaC in Evap#2 - Target current at 440A, temp measured at 1900C. A few tests on the temp measured
were done (see Evap#2 elog #251 & 252). |
Monday, October 26, 2015, 16:20, Laura Lambert, UC2, 41077-5, LP-SIS, Done, Conditioning UCx#14
|
John Wong wrote:
Thursday, October 15, 2015, 15:52 |
Monday, September 14, 2015, 15:31, John Wong, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_09
|
Monday, September 14, 2015, 15:28
Green cast dried UO2/C + organic mass = 61.31g
The green was rolled up and wrapped in a piece of graphite sheet. |
Saturday, August 29, 2015, 16:12, Anders Mjos, , , , Problems, Restarting vacuum after power outage
|
Saturday, August 29, 2015, 16:10: Roughing
Saturday, August 29, 2015, 16:10: Starting turbo
Saturday, August 29, 2015, 16:12: Turbo running. IG1 at 2.4E-4 T |
Wednesday, August 19, 2015, 11:44, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_08 8x
|
Wednesday, August 19, 2015, 11:02
UO2/C green was prepared Aug 11, 2015. The slurry was cast on a piece of glass coated with WD40
on Aug 12, 2015. |
Thursday, July 30, 2015, 17:19, John Wong, UO2/C, 40282-1, TARGET BOAT, In progress, Processing UC2_flk_07
|
Thursday, July 30, 2015, 17:10
The mixture of UO2/C was prepared on July 13, 2015. See screen shot for more info.
The material is loaded into a target boat and wrapped with 3 layers of Ta-heat shield. |
Tuesday, August 11, 2015, 10:23, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2_flk_07
|
John Wong wrote:
Thursday, July 30, 2015, 17:10 |
Tuesday, June 30, 2015, 13:31, Laura Lambert, UC2, 40860-1, LP-IG-LIS, In progress, Conditioning UCx #13
|
Tuesday, June 30, 2015, 13:28
Target container was previously coated with TaC spray and sintered.
It's is wrapped with 3 layers of Ta-heat shield, including the center block. |
Thursday, July 02, 2015, 13:01, John Wong, UC2, 40860-1, LP-IG-LIS, In progress, Conditioning UCx #13
|
Laura Lambert wrote:
Tuesday, June 30, 2015, 13:28 |
Friday, July 03, 2015, 13:45, Laura Lambert, UC2, 40860-1, LP-IG-LIS, In progress, Conditioning UCx #13
|
John Wong wrote:
|
Wednesday, July 08, 2015, 10:52, John Wong, UC2, 40860-1, LP-IG-LIS, Done, Conditioning UCx #13
|
Laura Lambert wrote:
|
Monday, May 11, 2015, 11:49, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_06
|
Monday, May 11, 2015, 11:45
UO2/C green was prepared May 6, 2015. The slurry was cast on a piece of glass coated with WD40
on May 7, 2015. |
Tuesday, April 21, 2015, 11:28, Laura Lambert, , , , Maintenance, Ion Gauge replaced March 23rd 2015
|
|
Friday, March 20, 2015, 15:21, Laura Lambert, UC2, 41177-2, LP-SIS, Done, Conditioning UCx #12
|
Friday, March 20, 2015, 15:17
Target container was previously coated with TaC spray and sintered.
It's is wrapped with 3 layers of Ta-heat shield, including the center block. |
Monday, March 09, 2015, 16:58, Laura Lambert, Empty, , TARGET BOAT, Maintenance, Testing new software
|
Monday, March 09, 2015, 16:55
After upgrading IOC for CXML program, experienced some issues; therefore, switched to same software as EVAP2.
Testing new software. |
Monday, January 26, 2015, 11:28, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_05
|
Monday, January 26, 2015, 11:19
UO2/C green was prepared Jan 20, 2015. The slurry was cast on a piece of glass coated with WD40 on Jan 21, 2015.
The cast was let dry over the weekend and peeled off the glass nicely Jan 26, 2014. [see attached picture] |
Friday, January 23, 2015, 15:02, Laura Lambert, , , , Maintenance, water supply turned back on to EVAP1 and fume hoods
|
Friday, January 23, 2015, 15:02
water supply turned back on to EVAP1 and fume hoods
|
Thursday, December 11, 2014, 10:17, Laura Lambert, , , , Maintenance, water supply shut off for lab closure over holidays
|
Thursday, December 11, 2014, 10:16
water valve shut off for lab closure over the holidays.
|
Friday, October 17, 2014, 11:55, Laura Lambert, UC2, 40282-5, LP-SIS, In progress, Conditioning UCx #11
|
Friday, October 17, 2014, 11:47
Target container was previously coated with TaC spray and sintered.
It's is wrapped with 3 layers of Ta-heat shield, including the center block. |
Monday, October 20, 2014, 16:22, John Wong, UC2, 40282-5, LP-SIS, Done, Conditioning UCx #11
|
Laura Lambert wrote:
Friday, October 17, 2014, 11:47 |
Monday, November 10, 2014, 13:50, Laura Lambert, UC2, 40282-5, LP-SIS, Done, Conditioning UCx #11
|
John Wong wrote:
|
Tuesday, September 23, 2014, 15:00, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, In progress, Processing UC2Flk_04
|
Tuesday, September 23, 2014, 14:54
UO2/C green was prepared Sept 18, 2014. The slurry was cast on a piece of glass coated with WD40 on Sept 19, 2014.
The cast was let dry over the weekend and peeled off the glass nicely Sept 22, 2014. |
Friday, October 10, 2014, 14:00, John Wong, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_04
|
Laura Lambert wrote:
Tuesday, September 23, 2014, 14:54 |
Tuesday, August 26, 2014, 15:27, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_03
|
Tuesday, August 26, 2014, 11:54
UO2/C green was prepared Aug 20, 2014. The slurry was cast on a piece of glass coated with WD40 on Aug 21, 2014.
The cast peeled off the glass nicely Aug 22, 2014 and let dry until Aug 25, 2014. |
Thursday, August 14, 2014, 17:56, John Wong, ThO2, , LP-SIS, Done, Sintering ThO2#1
|
Thursday, August 14, 2014, 17:54
Target container consists of 240 discs of ThO2/Nb discs. The container is not required to be wrapped with Ta-heat shields.
One end cap is inserted on the left end (wrt to the ionizer pointing into the page). |
|