  102   Friday, October 17, 2014, 11:55 Laura LambertUC240282-5LP-SISIn progressConditioning UCx #11 Friday, October 17, 2014, 11:47
Target container was previously coated
with TaC spray and sintered.
  
  112   Tuesday, June 30, 2015, 13:31 Laura LambertUC240860-1LP-IG-LISIn progressConditioning UCx #13 Tuesday, June 30, 2015, 13:28
Target container was previously
  
  113   Thursday, July 02, 2015, 13:01 John WongUC240860-1LP-IG-LISIn progressConditioning UCx #13

    

       
            
  
  114   Friday, July 03, 2015, 13:45 Laura LambertUC240860-1LP-IG-LISIn progressConditioning UCx #13

    

       
            
 evap1_trip_off_july_3rd.JPG 
  116   Thursday, July 30, 2015, 17:19 John WongUO2/C40282-1TARGET BOATIn progressProcessing UC2_flk_07 Thursday, July 30, 2015, 17:10
The mixture of UO2/C was prepared
on July 13, 2015.  See screen shot for
 IMG_20150714_145857963.jpg 
  121   Thursday, October 15, 2015, 16:05 John WongUC241077-5LP-SISIn progressConditioning UCx#14Thursday, October 15, 2015, 15:52
Target container previously sintered
with TaC in Evap#2 - Target current at 440A,
  
  125   Thursday, February 18, 2016, 15:42 Laura LambertUC241077-1LP-SISIn progressConditioning UCx#15 Thursday, February 18, 2016, 15:34
Target container was previously
  
  126   Friday, February 26, 2016, 10:27 John WongUC241077-1LP-SISIn progressConditioning UCx#15

    

       
            
  
  135   Monday, September 12, 2016, 17:41 John Wong  TARGET BOATIn progressRUSH. Sintering end-caps Monday, September 12, 2016, 17:30
A bunch of end caps (12?) and a long
Ta-wire in spring sharp  were coated
  
  139   Monday, November 07, 2016, 13:34 Laura LambertUO2/C40282-1TARGET BOATIn progressProcessing UC2Flk_13 Monday, November 07, 2016, 13:29
UO2/C green was prepared Nov
 UCxFlk_13[4].jpgUCxFlk_13[1].jpg 
  140   Tuesday, November 15, 2016, 10:02 John WongUO2/C40282-1TARGET BOATIn progressProcessing UC2Flk_13

    

       
            
  
  147   Tuesday, May 23, 2017, 15:51 Laura LambertUO2/C40282-1TARGET BOATIn progressprocessing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS Tuesday, May 23, 2017, 14:42
UO2/C green was prepared May
 UCxFlk_16_temp_readout.jpg 
  150   Friday, May 26, 2017, 16:09 Laura LambertUO2/C40282-1TARGET BOATIn progressprocessing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS

    

       
            
  
  155   Wednesday, July 12, 2017, 17:07 Laura LambertUC242218-15LP-SISIn progressConditioning UCx#21 Wednesday, July 12, 2017, 17:06
Target container was previously
  
  159   Wednesday, July 19, 2017, 14:17 Laura LambertUC242218-15LP-SISIn progressConditioning UCx#21

    

       
            
  
  176   Wednesday, January 10, 2018, 14:44 Marla CervantesUO2/C40282-1TARGET BOATIn progressCarbonizing UO2/C discs for 1stepUCx in graphite sample container _#4 Wednesday, January 10, 2018, 14:44
Circles from cast 1 were used,
  
  177   Friday, January 12, 2018, 07:46 Laura LambertUO2/C TARGET BOATIn progressCarbonizing UO2/C discs for 1stepUCx in graphite sample container_#4

    

       
            
  
  180   Friday, January 19, 2018, 12:32 Marla CervantesUO2/C40282-2 TARGET BOATIn progressCarbonizing UO2/C discs for 1stepUCx in graphite sample container_#6 Friday, January 19, 2018, 12:29
Circles from cast 1 were used,
  
  184   Monday, January 29, 2018, 09:28 Marla CervantesUO2/C40282-2 TARGET BOATIn progressCarbonizing UO2/C discs for 1stepUCx in graphite sample container _#7 Monday, January 29, 2018, 09:26
35 circles of 14 mm diameter
  
  199   Wednesday, March 28, 2018, 11:46 Laura LambertUO2/C40282-2TARGET BOATIn progressCarbonizing first full length 1step UCx target Wednesday, March 28, 2018, 11:35