Entry  Mon Jun 20 05:58:21 2011, Jamie Brown, , , Run log run_log.xls
Attached is a spreadsheet summarizing all the run information from the experiment.
Entry  Tue Jun 21 02:58:31 2011, Jamie Brown, , , Run Books 13 and 14 tuda_book13_1-47.pdftuda_book13_48-95.pdftuda_book13_96-143.pdftuda_book13_144-191.pdftuda_book14.pdf
Attached. Book 13 is split into 4 sections as otherwise the file is too big for the elog to accept.
Entry  Wed Apr 13 03:43:42 2011, Jamie, , , Ni window leak tests 1 Screenshot.pngScreenshot-1.png
2um x 8 mm Ni windows leaked tested on TUDA gas cell. With window placed on the outside of the cell, cell was evacuated and pressure monitored with time,
i.e. 1atm differential air pressure. Comparison to leak rate with blank flange also do.
Tests were performed in order: Ni, 30 minuets pumping, Ni again, blank, Ni third time.
Entry  Wed Apr 13 03:55:21 2011, Jamie, , , Safety Report S1287-Revised_Safety_Report.pdfrevised.pdf
attached
 
note. s2 position in fig. 1 is wrong, should be 360mm.
Entry  Thu May 5 11:31:13 2011, JB, , , Tom's ToDo List 
 


Version 2 of ...

- re-test
chamber/coolant loop with vacuum cycle - done
- install MSL Type W preamp - done
- to adjust position of support ring, temporarily loosen
Entry  Fri May 6 15:08:00 2011, JB, , , New TUDA EPICS layout gas_handling-3.png
 
Entry  Sat May 7 17:29:13 2011, JB, , , Window leak tests on TUDA window2-leaktest.png
Attached plot shows rate of pressure increase in ~2l volume upstream of TUDA with Ni window #2 installed on reentrant flange. Comparison between
a)pumping out TUDA and 2l volume, and
b) filling TUDA with ~340mbar of He and pumping out 2l volume.
Entry  Wed May 11 17:59:12 2011, JB, , , Re-entrant flange alignment 
Alignments checks revealed that downstream end of TUDA was ~1mm off (can't remember which way).
Re-entrant flange (window end) found to be ~5mm too low and ~2mm to the left. Checked upstream end of chamber and was ok.
Removed bellows etc. and re-entrant flange, replaced with re-entrant flange bolts only figure tight. Tighten bolts from inside chamber whilst checking
Entry  Sun May 15 13:07:12 2011, JB, , , W detector V-I curve W_detector_V-I_curve.png
York W detector 2635-19
1037um
Entry  Thu May 26 00:15:18 2011, Hicham and Sarah, Routine, , End of run summary 
still running at 3.98 MeV/u
19:08
S2-1 had tripped off due to leakge current going above 8uA
Entry  Thu May 26 02:54:10 2011, Derek and Naomi, Routine, General, Thu 0-8am shift summary 
 
For run 123:
Beam outage for ~15 min but not stopping run.
Entry  Thu May 26 23:57:34 2011, Derek, Routine, General, Friday 00:00 - 08:00 Summary 
Sarah informed me that Jamie was performing the sorting and saving of spectra differently and didn't know what exactly to do so I will not be performing
any sorting.
 
Entry  Mon May 23 02:12:14 2011, Brian, Routine, , Start of Run summary 
Handover from last shift was...
1. Running at 4.11 MeV/u at about 15enA (5+)
2. Would like to take more beam but already at situation where deadtime about 50%.  They have been raising thresholds on the inner strips
Entry  Wed May 25 03:15:44 2011, Brian, Routine, General, Start of run summary and TDC problems 
Summary at start of run
Read through the runbook and end of run summar and the situation appears to be:
1. The check of the tune showed it was OK, although a bit of beam (or halo) clipping 4mm collimator
Entry  Wed May 25 07:09:17 2011, Brian, Routine, General, End of run summary (yes, a bit early, but done all I can think of!) 
Running status
Everything seems to be running OK.  ADC and TDC spectra look OK.  Chamber pressure has stabalised.  Detector leakages stabalised
Beam now up to 60pnA with trigger rate about 4,000/s and accepts about 3,000/s
Entry  Tue May 24 01:47:17 2011, Anonymous, , , Shift schedule, as of 1am Tuesday 24th Screenshot.png
 
Entry  Wed Feb 4 17:27:55 2015, Anonymous, , ,  
This is reachable and change-able via outside Internet
Entry  Wed May 18 09:09:02 2011, Alison Laird, , , Status update 
 Wednesday morning:
4 new windows were tested last night. 2 very good.
Now venting to install and test Faraday cup, install and test camera.
Entry  Fri May 27 23:13:01 2011, Alex Rojas, Routine, General, Shift summary 
No major problems presented, A pluser walk was performed at the begining of the shift run161 S2-1 front, run162 S2-2 front, run163 S2-1 back and run165
S2-2 back.
Runs 166, 168, 169 are void due to bad scaler reading
Entry  Wed May 18 08:54:08 2011, Alex Murphy, , , Photodiode data from target thickness measurements pdruns.xls