  Test-Stand, Page 5 of 53  Not logged in ELOG logo
Entry  Wednesday, September 28, 2011, 16:33, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, HV conditioning 
Started the HV conditioning: TSG:BIAS=30kV
Entry  Thursday, September 29, 2011, 09:27, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, Heaters conditioning 
Started the heaters conditioning: TGHT up to 580A and TBHT up to 230A.
Entry  Friday, September 30, 2011, 18:03, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Finished testing SiC#26 at the Test Stand 
Today, did a did a mass scan: plotdump-local-clean.txt Sep30 11 12-20-08.txt
Optimized a bit the tune with Friedhelm, then started the Target Cooldown.
Entry  Monday, October 03, 2011, 10:53, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target is ready to be removed.  
Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum and the water is still on.
    Reply  Monday, October 03, 2011, 13:56, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Venting 


    
        
            Aurelia Laxdal wrote:
        
        
            
            Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum
    Reply  Monday, October 03, 2011, 14:46, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target stored under vacuum 


    
        
            Anders Mjos wrote:
        
        
            
            
            
              
    Reply  Wednesday, October 12, 2011, 13:14, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target removed 


    
        
            Anders Mjos wrote:
        
        
            
            
            
Entry  Monday, May 14, 2012, 16:57, Aurelia Laxdal, , , ITE, TM4, , , , SiC#27-HP-SIS installed in the Test Stand 
Rick and John installed the ITE-TM4-SiC#27-HP-SIS-May2012 in the Test Stand. Pumping down.
Entry  Tuesday, May 15, 2012, 07:39, Rick Maharaj, Sic #27, HP-SIS, ITE, TM4, , , In progress, Water on at test stand 
The vacuum on TSGIG1 reads 2.85e-07. Turing on water on teststand and observing any changes in vacuum pressure.
    Reply  Tuesday, May 15, 2012, 10:14, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , In progress, target ready to be heated and biased 
 Tuesday, May 15, 2012, 10:13: Turbo pumps at speed. Vacuum at 1.4E-5.
Tuesday, May 15, 2012, 12:03: Cooling lines opened. Vacuum stable at 1.6E-6
Tuesday, May 15, 2012, 12:17: Target ready to be heated and biased.
Entry  Tuesday, May 15, 2012, 16:18, Aurelia Laxdal, SiC#27, HP-SIS, ITE, TM4, , , In progress, Target/Ion source conditioning 
Did the HV conditioning up to 30kV and started to ramp up the heaters to 580A and 230A.
Entry  Wednesday, May 16, 2012, 18:10, Aurelia Laxdal, , , ITE, TM4, , , , SiC#27 cooling down 
Today: did a mass scan at 580A on TGHT and 230A on TBHT at 30kV. Found some A/q units discrepancies on the mass scan page. It may be a hall probe problem: 
under investigations.
Uploaded the testing file on Docushare: http://documents.triumf.ca/docushare/dsweb/View/Collection-8539/Document-56575
    Reply  Thursday, May 17, 2012, 08:36, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , Done, Target removed 
Thursday, May 17, 2012, 08:36: Turbo pumps switched off in preparation of target removal.
Thursday, May 17, 2012, 08:51: Purging cooling lines.
Thursday, May 17, 2012, 08:55: Venting.
    Reply  Thursday, May 17, 2012, 12:19, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , Problems/Solutions, Loose chip of insulator material detected Chipped_insulator_stand-off.pdf


    
        
            Anders Mjos wrote:
        
        
            
             A chip of insulator material was detected below the lower target insulator stand-off (attachment
Entry  Thursday, May 17, 2012, 13:24, John Wong, SiC#27, HP-SIS, ITE, TM4, 38817-3, , Problems/Solutions, Solid residues found on EE SiC#27_after_teststand.pdfSiC#27_clean_EE.pdf
 Thursday, May 17, 2012, 13:15
After the test-stand, the EE was removed for inspection.  It was discovered that there were some solid residues coated on the extraction electrode
and the common plate, but the ionizer tube was clean (see attachment#1).  Some samples were collected and will try to do some analysis.  This
Entry  Thursday, August 23, 2012, 11:39, Anders Mjos, NiO#1, HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 installed 
Thursday, August 23, 2012, 11:38: NiO#1 installed.
Thursday, August 23, 2012, 11:38: Started roughing. Both roughing pumps timed out.
Thursday, August 23, 2012, 11:54: Roughing.
    Reply  Friday, August 24, 2012, 08:28, Anders Mjos, NiO#1, HP-FEBIAD, ITE, TM4, , , Done, NiO#1 installed 


    
        
            Anders Mjos wrote:
        
        
            
            Thursday, August 23, 2012, 11:38: NiO#1 installed.
Entry  Monday, August 27, 2012, 13:21, Aurelia Laxdal, NiO#1, HP-FEBIAD, ITE, TM4, , , In progress, HV conditioning at Test Stand  
Did HV conditioning up to TSG:BIAS=30kV, TSH=EE=-600V
Turned off the HV for Kazuya to check the connection/output of the TSG:TGHT Xantrex power supply.
Entry  Tuesday, August 28, 2012, 16:57, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, Updates for NiO#1 at Test Stand 
Tested the power supplies and locked up the HV cage.
Turned on the HV: 30kV.
Tomorrow we'll start up the heaters: 580A for the target and 280-300A for the tube.
Entry  Wednesday, August 29, 2012, 11:34, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 heating startup & few checks 
Friedhelm checked the voltage across R4 from ISK4563D-rev2.pdf. It shows 50 kOhms with the power supplies off and everything connected according to the
drawing. With the Anode PS On and set at 20V, we could see the same readback on EPICS and on the meter.
Then started the heater ramping: auto ramp 2A/min.