305
|
Friday, May 24, 2013, 15:13 |
Aurelia Laxdal | CLT FEBIAD | | | | | | | CLT FEBIAD conditioning started | Purged the gas lines, turned on the HV and started the heaters for CLT FEBIAD: TGHT up to 580A and TBHT up to 230A. |
892
|
Thursday, August 05, 2021, 08:49 |
Fernando Maldonado | | | | | | | Problems/Solutions | CANBUS snooper set up to investigate random optics turnining off | Problem: Some devices turn off unexpectedly and sometimes without any obvious trigger. In the past, the only time this was an issue was during mass scans. Now with the automation of measurements, this is a major problem as it prevents longer parameter scans.
Thursday, August 05, 2021, 08:00: Kevin setup the CANBUS snooper by hooking it up on the magnet card loop port.
This device tracks the network so if any error happen it will be captured.
Thursday, August 05, 2021, 09:39: Test unsuccessful. No device turned off (I should be happy XD)
Thursday, August 05, 2021, 09:40: Will run the test another time
A PC was setup near the old magnet power supply (20210806_150334.jpg ). One of the software run smoothly but the other more useful one fails to connect to the usb adapter.
Friday, August 06, 2021, 14:52: Fixed issue with the usb adapter. With this, the CANBUS traffic can be store and inspected to catch any error on the communication (Annotation_2021-08-06_144737.png).
Friday, August 06, 2021, 14:53: Loggers are running.
Friday, August 13, 2021, 11:07: I forgot to input the feedback from Kevin:
"33 errors out of 10,300,00 transaction seems statistically insignificant to me. "
From the devices tripped,
"Most of the tripped supplies are located on the front side of the rack, the original test stand controllers"
So maybe the issues could be
"Compatibility issues with the old and new? The newer supplies are all daisy chained, should we upgrade these to the tap boards?
Should the old controllers (original test stand appear to be MK supplies) be upgraded (do we have enough)?" |
660
|
Tuesday, May 08, 2018, 10:36 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | C-seal Test | 2 C-Seals installed with SS springs on water blocks. The SS springs are also used in the module.
Long pkg seal (A):
T: 0.098" x 0.429" Diameter.
Installed on line FS#5 , Block L, Heat shield cooling block. (Top seal, bottom seal of 2 is still the rubber O-ring)
Short pkg seal (B):
T: 0.095" x 0.424" Diameter.
Installed on line FS#3 , Block G, Coil cooling block.
All the waterlines are purged and shut. Open individually and monitor for leaks.
Tuesday, May 08, 2018, 10:27: Roughing
Tuesday, May 08, 2018, 10:31: Both BV1A & BV1B are open.
Tuesday, May 08, 2018, 10:57: Turbo Pumps started.
Tuesday, May 08, 2018, 11:03: Ion gauge on.
Tuesday, May 08, 2018, 11:15: RGA started.
Tuesday, May 08, 2018, 13:30: Vacuum @ 3.14e-06T
Wednesday, May 09, 2018, 06:48: Vacuum 5.13E-07T. RGA ok.
Wednesday, May 09, 2018, 06:50: Hook up Leak Detector. Leak detector # 5 (DRY) from Vacuum Group. Startup
Baseline Reading:
TP pressure 0.0e-04
Leak rate: Below 0.0e-09 atm-cc/sec
Valve to chamber opened. LD connection clear.
LD: 1.3e-08 atm-cc/sec
He TEST:
Wednesday, May 09, 2018, 07:00: Purge both lines with He. Do not pressurize.
Vacuum @ 5.13e-07T. RGA status:
Water @ 3.22e-007
He:-1.93e-009
LD: 1.3e-08 atm-cc/sec
Wednesday, May 09, 2018, 07:15: Open line FS#5 to heat shield. Pressurize to 30 PSI.
Wednesday, May 09, 2018, 07:40: Vacuum @ 5.02e-07T. RGA status:
Water @ 3.13e-007
He:-1.67e-009
LD: 9.3e-08 atm-cc/sec. Purge and close FS#5.
Wednesday, May 09, 2018, 07:45: Open line FS#3 to Coil block. Pressurize to 30 PSI.
08:10: Vacuum @ 4.9e-07T. RGA status:
Water @ 3.08e-007
He:-1.61e-009
LD: 1.5e-07 atm-cc/sec
Wednesday, May 09, 2018, 08:15: Depressurize lines. Connect HPA.
Wednesday, May 09, 2018, 08:20: Vacuum @ 4.76e-07T. RGA status:
Water @ 3.05e-007
He:-1.68e-009
LD: 1.7e-07 atm-cc/sec
08:25: LD: 1.7e-07 atm-cc/sec. Close Valve & disconnect LD
Water & Cycling TEST:
Wednesday, May 09, 2018, 08:45: Vacuum @ 4.67e-07T. RGA status:
Water: 3.02e-007
Open lines FS#2 and FS#4
Wednesday, May 09, 2018, 08:55: Vacuum @ 4.65e-07T. RGA status: Water @ 2.97e-007
Close lines FS#2 and FS#4. Water filled.
Open line FS#5 to heat shield. Vacuum and RGA ok.
09:00: Begin C-Seal (A) shock cycling. 20 cycles @ 5 min apart.
Close Supply/Return, Open Supply/Return to 'Shock'
TIME |
Vacuum (T) |
RGA (water) |
TIME |
Vacuum (T) |
RGA (Water) |
09:00 |
4.65e-07 |
2.94e-007 |
09:50 |
4.58e-07 |
2.87e-007 |
09:05 |
4.58e-07 |
2.93e-007 |
09:55 |
4.58e-07 |
2.88e-007 |
09:10 |
4.58e-07 |
2.93e-007 |
10:00 |
4.58e-07 |
2.87e-007 |
09:15 |
4.65e-07 |
2.92e-007 |
10:05 |
4.56e-07 |
2.87e-007 |
09:20 |
4.65e-07 |
2.92e-007 |
10:10 |
4.56e-07 |
2.85e-007 |
09:25 |
4.65e-07 |
2.90e-007 |
10:15 |
4.56e-07 |
2.86e-007 |
09:30 |
4.65e-07 |
2.89e-007 |
10:20 |
4.49e-07 |
2.83e-007 |
09:35 |
4.56e-07 |
2.89e-007 |
10:25 |
4.49e-07 |
2.84e-007 |
09:40 |
4.65e-07 |
2.89e-007 |
10:30 |
4.49e-07 |
2.84e-007 |
09:45 |
4.58e-07 |
2.89e-007 |
10:35 |
4.47e-07 |
2.83e-007 |
Wednesday, May 09, 2018, 10:40: Close line FS#5. Vacuum @ 4.49e-07T. RGA status: Water @ 2.84e-007
Open line FS#3 to Coil block. Vacuum and RGA ok
10:45: Begin C-Seal (B) shock cycling. 20 cycles @ 5 min apart
Close Supply/Return, Open Supply/Return to 'Shock'
TIME |
Vacuum (T) |
RGA (water) |
TIME |
Vacuum (T) |
RGA (Water) |
10:45 |
4.47e-07 |
2.80e-007 |
11:35 |
4.32e-07 |
2.77e-007 |
10:50 |
4.47e-07 |
2.80e-007 |
11:40 |
4.38e-07 |
2.75e-007 |
10:55 |
4.47e-07 |
2.81e-007 |
11:45 |
4.38e-07 |
2.75e-007 |
11:00 |
4.38e-07 |
2.80e-007 |
11:50 |
4.38e-07 |
2.75e-007 |
11:05 |
4.38e-07 |
2.78e-007 |
11:55 |
4.38e-07 |
2.75e-007 |
11:10 |
4.40-e07 |
2.79e-007 |
12:00 |
4.40e-07 |
2.75e-007 |
11:15 |
4.38e-07 |
2.77e-007 |
12:05 |
4.38e-07 |
2.73e-007 |
11:20 |
4.47e-07 |
2.77e-007 |
12:10 |
4.40e-07 |
2.73e-007 |
11:25 |
4.40e-07 |
2.78e-007 |
12:15 |
4.30e-07 |
2.71e-007 |
11:30 |
4.38e-07 |
2.76e-007 |
12:20 |
4.32e-07 |
2.73e-007 |
12:25: Open FS#5 and leave FS#3 open. Status Vacuum @ 4.32e-07T . RGA status: Water @ 2.70e-007
13:00: Status Vacuum @ 4.30e-07T . RGA status: Water @ 2.67e-007
Wednesday, May 09, 2018, 14:24: Status Vacuum @ 4.21e-07T . RGA status: Water @ 2.52e-007
Thursday, May 10, 2018, 07:41: Status Vacuum @ 3.24e-07T . RGA status: Water @ 1.76e-007.
Purge all water from lines. Prep for He.
Hook up Leak Detector. Leak detector # 5 (DRY) from Vacuum Group. Startup
Thursday, May 10, 2018, 08:00: Baseline Reading:
TP pressure 0.0e-04
Leak rate: Below 0.0e-09 atm-cc/sec
Vacuum @ 3.15e-07T . RGA status: Water @ 1.65e-007.
Valve to chamber opened. LD connection clear.
Leak rate: 1.6e-08 atm-cc/sec
He TEST #2:
Thursday, May 10, 2018, 08:13: Purge both lines with He. Do not pressurize.
Vacuum @ 3.15e-07T. RGA status:
Water @ 1.76e-007
He: -1.51e-009
LD: 1.5e-08 atm-cc/sec
Thursday, May 10, 2018, 08:15: Open line FS#3 to Coil Block. Pressurize to 30 PSI.
Thursday, May 10, 2018, 08:40: Vacuum @ 3.22e-07T . RGA status:
Water @ 1.80e-007
He:-1.98e-009
LD: 7.1e-08 atm-cc/sec. Purge and close FS#3.
Thursday, May 10, 2018, 08:45: Open line FS#5 to Heat Shield. Pressurize to 30 PSI.
Thursday, May 10, 2018, 09:10: Vacuum @ 3.22e-07T. RGA status:
Water @ 1.79e-007
He:-1.39e-009
LD: 1.5e-07 atm-cc/sec
09:15: Depressurize lines. Connect HPA.
09:30: Vacuum @ 3.22e-07T . RGA status:
Water @ 1.78e-007
He:-1.56-009
LD: 1.7e-07 atm-cc/sec
Thursday, May 10, 2018, 09:32: Close Valve & disconnect LD
Thursday, May 10, 2018, 09:35: Opened all waterlines completely. Vacuum stable @3.22e-07T and no response on the RGA.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
24.8 |
2.83 |
TBHT |
24.7 |
3.09 |
COIL + EE |
24.7 |
5.08 |
TGHT |
24.9 |
5.77 |
Tuesday, May 15, 2018, 06:06: Auto ramping TGHT / TBHT to 580 / 270 A @ 2A per min.
Tuesday, May 15, 2018, 06:13: BIAS / EZL / EE @ 30 / 13 / 1.5 kV .
Tuesday, May 15, 2018, 06:17: Optics set. IV4 opened.
Tuesday, May 15, 2018, 08:35: RGA Restarted. Spikes noticed on BIAS current. Vacuum @ 2.57E-06T
Wednesday, May 16, 2018, 06:40: TMS:IG6 (between 3-4pm yesterday) and the RGA were both knocked out. Restarting both.
Wednesday, May 16, 2018, 06:48: Repeated attempts to reset/restart IG6 have failed. Closing IV4
Friday, May 18, 2018, 10:55: Auto-cooling @ 1A per min. IG6 still non-responsive. |
899
|
Tuesday, September 14, 2021, 17:12 |
Aaron Schmidt | C#3 | LP-SIS | ITW | TM2 | 44691-7 | 44378-11 | In progress | C#3 Conditioning | Tuesday, September 14, 2021, 17:00: Roughing
Tuesday, September 14, 2021, 17:37: TP1B on.
Tuesday, September 14, 2021, 17:47: TP1A on.
Tuesday, September 14, 2021, 17:55: IG1 on.
Wednesday, September 15, 2021, 06:51: Waterlines opened. Vacuum Stable @ 4.46e-06T.
Wednesday, September 15, 2021, 07:01: Power/sources/optics on - Set.
Wednesday, September 15, 2021, 07:02: IV4 opened.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
23.8 |
3.99 |
TBHT |
24.6 |
3.23
|
COIL + EE |
23.6 |
5.02 |
TGHT |
23.8 |
5.66 |
Wednesday, September 15, 2021, 07:05: Quick system check. TGHT / TBHT @ 10 / 10 A. OK.
Wednesday, September 15, 2021, 07:06: BIAS / EE / EZL @ 1 / -0.5 / 1 kV. Not ok. BIAS short!!!* set to 1kV, zero read back. 0V & 0.230 mA.
Wednesday, September 15, 2021, 08:01: Hook was still in the cage. Removed*
Wednesday, September 15, 2021, 08:05: Quick system check. TGHT / TBHT @ 10 / 10 A. BIAS / EE / EZL @ 1 / -0.5 / 1 kV. All ok. Vacuum @ 4.02e-06T. Allow to stabilize.
Thursday, September 16, 2021, 04:38: Vacuum @ 2.13e-06T. Auto-ramping TGHT / TBHT to 350 A / 150 A @ 2 A per min.
Thursday, September 16, 2021, 04:44: BIAS / EE / EZL @ 20 / -1.0 / 10 kV.
Thursday, September 16, 2021, 08:58: Auto-ramping TGHT / TBHT to 580 A / 230 A @ 2 A per min.
Thursday, September 16, 2021, 13:20: Auto-ramp halted. Vacuum @ 3.12 e-06T. TGHT / TBHT @ 410 / 210. Adjusted good vacuum / increment limit t0 5.0e-06T & 7e-06T (Back off limit). Continue auto-ramping TGHT / TBHT to 580 A / 230 A @ 2 A per min.
Thursday, September 16, 2021, 16:30: BIAS / EE / EZL @ 30 / -1.5 / 13 kV. TGHT / TBHT @ 543+/ 230 A. TGHT still ramping on vac limit. Good wire scans so far.
Thursday, September 16, 2021, 16:36: Mass & wires scans proceeding.
Thursday, September 16, 2021, 17:16: Scans ok. TGHT @ 550 A. Vacuum @ 5.12e-06T.
Friday, September 17, 2021, 10:41: Mass & wire scans ok. BIAS / EE / EZL to 0 kV.
Sunday, September 19, 2021, 20:33: Auto-cooling @ 1 A per min.
Monday, September 20, 2021, 06:10: Power/sources off. IV4 off. Lock-out.
Monday, September 20, 2021, 06:13: IG1 off. Turbo pumps off.
Thursday, September 23, 2021, 05:04: Venting. |
379
|
Tuesday, May 20, 2014, 11:17 |
Anders Mjos | | | | | | | Problems/Solutions | Burnt off GND connection on Service Cap | The ground connection between B and F (ISK4523D Rev 6) was found burnt off. It will be switched out as per CATHODE BIAS configuration (ISK4563D Rev 3) by Ray D. |
737
|
Tuesday, June 25, 2019, 17:19 |
Fernando Maldonado | | | | | | | Problems/Solutions | Burnt cables on top of the test stand | Tuesday, June 25, 2019, 16:15: While inspecting the 9-pin connection with Ferran, it was noticed how two braided cables were burnt out pretty bad to the point they were separated in half (see attached pictures). Additionally the plastic insulator for the anode wire was melted.
Tuesday, June 25, 2019, 16:30: Braided cables need to be changed and anode wire redone.
Tuesday, June 25, 2019, 17:16: Wondering if this happened during TM4 source tray conditioning given the following entries in the elog (entry 725):
Monday, June 03, 2019, 09:51: BIAS down to 50 kV. Burnt plastic smell lingering. Wait*
Tuesday, June 04, 2019, 10:29: Note* Minute fluctuations of Anode current have ended after the spark. Also slight 'Burnt' smell noticed around the test stand area.
|
647
|
Monday, March 12, 2018, 10:44 |
Carla Babcock | | | | | | | | Bringing up HV with gas on | Pressure:
Previous HV tests done at 2e-7 pressure.
Current pressure 1.1e-6 (see previous entry for RGA stats) - first attachment shows source gas setup. Argon, neon and He leaks all on.
Ramping up:
- Second attachment - bias at 50kV
- Third attachment - bias at 60kV
- Fourth attachment - bias at 65kV
Pressure has been slowly falling since we started this test - now down to 8.7e-7
Spark after 10 mins, see attachment 5. Very slight vacuum jump (8.5e-7 -> 1.2e-6) and bias current jump (36uA -> 113uA). Tripped TP6 and the steerers, as usual. Bias current read back more erratic afterwards (see sixth attachment).
System has been stable for 20mins, though current on bias is still more erratic than before the spark. Increasing He leak rate from 7 to 7.06 to bring vacuum back up to 2e-6 (see attachment 7). No effect from increased pressure.
Tuesday, March 13, 2018, 05:52: Power off.
Tuesday, March 13, 2018, 05:56: Waterlines purged
Tuesday, March 13, 2018, 05:57: Ion gauge, Turbos off. |
741
|
Tuesday, July 02, 2019, 18:25 |
Fernando Maldonado | | | | | | | Done | Blank on FEBIAD gas line installed | Tuesday, July 02, 2019, 18:24: A blind is installed on the FEBIAD gas line (see attached picture) to rule out the possibility of gases entering the TIS. |
318
|
Thursday, July 11, 2013, 08:38 |
Anders Mjos | | | | | | | Problems/Solutions | Bias & EL P/S cleaned | The power supplies were "de-dusted" yesterday by Ray Dube and team. |
1013
|
Wednesday, July 24, 2024, 14:08 |
Dave Neilson | | | | | | | | Beam line window change - DUV installation | Wednesday, July 24, 2024, 14:07 Changed beamline window to DUV window (window at magnet for target source viewing) |
866
|
Friday, March 26, 2021, 17:04 |
Carla Babcock | | | | | | | | Beam line vented for emittance meter exchange | Vented beamline and removed ARIEL emittance meter. In the process of swapping components, beamline left vented until Monday when we will finish the job. |
810
|
Tuesday, August 25, 2020, 07:23 |
Aaron Schmidt | | | | | | | Problems/Solutions | Beam line side vacuum trip | Tuesday, August 25, 2020, 07:07: Beam line side of the TS appears to have tripped? Open BV6 & BV2.
Tuesday, August 25, 2020, 07:15: Beam line side TP6 & TP2 on.
Tuesday, August 25, 2020, 07:16: Venting Chamber side
Trip appears to have occurred at 6am on Saturday.
Contacted MCR. Power bump occurred.
|
209
|
Friday, September 21, 2012, 08:27 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A/B fluctuating | Backing pressures TSG:CG1A/B are fluctuating between 0.02 and 0.05 since Sept 17th at ~17h. Expected values <0.01. |
343
|
Tuesday, November 05, 2013, 15:50 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A and CG1B elevated | Pressure around 140 mTorr. The pressure started increasing early November 2nd. Will continue to monitor.
Tuesday, November 12, 2013, 09:51 UPDATE
Backing pressure further increased to ~ 350 mTorr over the weekend. Vacuum group has been informed and will replace the pump this week. |
345
|
Wednesday, November 20, 2013, 08:57 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A and CG1B elevated |
Anders Mjos wrote: |
Pressure around 140 mTorr. The pressure started increasing early November 2nd. Will continue to monitor.
Tuesday, November 12, 2013, 09:51 UPDATE
Backing pressure further increased to ~ 350 mTorr over the weekend. Vacuum group has been informed and will replace the pump this week.
|
The backing pump (TSG:RP1) was replaced yesterday by Anthony Ip. Backing pressure is down to 1 mTorr on TSG:CG1A |
437
|
Friday, April 24, 2015, 12:25 |
Anders Mjos | | | | | | | Problems/Solutions | Backing line pressure high | TSG:RP1 backing line pressure is >200 mT. An e-fault has been submitted to have the roughing pump replaced.
Friday, April 24, 2015, 13:13: Pump replaced by vacuum group. |
1021
|
Tuesday, September 10, 2024, 16:24 |
Dave Neilson | TiC #24D | HP-SIS | ITW | TM3 | 45447-27 | 45235-25 | | Back up target testing and conditioning | Tuesday, September 10, 2024, 16:21: Target installed in test stand by Brady
Tuesday, September 10, 2024, 16:21: roughed down and turbo pumps now on.
Tuesday, September 10, 2024, 20:27 Pressure at 4.9e-6, increasing TGHT TBHT to 580A/230A at 1A/30s
Wednesday, September 11, 2024, 10:00 The TGHT TBHT parameters were mistakenly reversed during heating. TBHT was dropped to 230A and TGHT increased to 580A at 1A/30s.
Wednesday, September 11, 2024, 13:50 TGHT TBHT at 580 230. Increasing BIAS/EE/EZL to 30/2.5/13 kV.
Wednesday, September 11, 2024, 14:36 At high voltage, on FC0 there is an output beam current of 1.85e-7 A.
Wednesday, September 11, 2024, 14:49 Mass scan recorded. 2024-09-11 HPTiC-24D - scan 1.txt ... FC6 problem with recording background level data persists
Wednesday, September 11, 2024, 15:53 increasing BIAS and EZL to condition high voltage
Wednesday, September 11, 2024, 16:32 at 37kV (EZL 22kV), TGHT timed out and cut the current to the target. I elected to leave it cold rather than suddenly reheating it, and am cooling down TBHT at -1A/30s, while continuing to increase BIAS for conditioning.
there have been no sparks at all and I'm unsure of what precipitated this event. None of the 'trip indicators' on the TGHT panel lit up during this event. I will bring this up with Keiko/Roberto tomorrow Sept 12.
Wednesday, September 11, 2024, 17:06 one spark occurred at 49kV
Wednesday, September 11, 2024, 17:15 now at 50kV, EZL at 33kV. Over 30 minutes there was just one spark at the HV bias.
Wednesday, September 11, 2024, 17:50 decreasing high voltage elements to 0 0 0. |
657
|
Friday, April 20, 2018, 13:20 |
Carla Babcock | | | | | | | Done | BIAS* fan sounds like it is dying | The fan in the EZL power supply is making a terrible noise - keep an eye on it, it sounds like it might give up soon.
Monday, April 23, 2018, 10:47: The back panel was opened. Original entry stated EZL power supply issue. Corrected to BIAS PS. High voltage group notified. Fan replacement required.
Monday, May 14, 2018, 13:20: BIAS fans, external an internal were replaced. Re-installed @ TS.
Monday, May 14, 2018, 13:26: BIAS ramped up to 10 kV. Response ok on epics and locally on the PS. No odd noise on the fans either. The issue appears to be fixed. |
629
|
Wednesday, February 07, 2018, 08:46 |
Aaron Schmidt | | | | | | | | BIAS Power supply installation | Wednesday, February 07, 2018, 08:40: A 75 kV Glassman power supply was installed in the rack for use in further HV testing.
-The 75kV power supply is linked into the keyed interlock system. The key & switch labelled BIAS/EZL will unlock it.
-The PS is currently not connected to the epics controls and can only be adjusted manually.
-The old Glassman supply is disconnected and removed from the cage. |
715
|
Wednesday, March 27, 2019, 11:01 |
Aaron Schmidt | | | | | | | Problems/Solutions | BIAS PS replaced. Test | Wednesday, March 27, 2019, 10:25: BIAS @ 1 kV
952V - 548uA on controls readback - Scaling req'd
964V direct from the PS - 25 uA
Wednesday, March 27, 2019, 10:28:
2.75 kV
2725V - 1515uA on controls readback
2696V direct from the PS - 65.8 uA - Scaling req'd
Wednesday, March 27, 2019, 10:31:
5.5kV
5465V - 3022uA on controls readback
5.478kV direct from the PS - 137.5uA - Scaling req'd
Wednesday, March 27, 2019, 11:00: PS runs ok. Longer connection cable req'd to link to TS source. Contact controls over scaling.
Wednesday, March 27, 2019, 14:25: Sources on. BIAS connected.
Wednesday, March 27, 2019, 14:34: BIAS / EZL @ 5.5 / 1 kV. No spark.
Wednesday, March 27, 2019, 14:51: BIAS / EZL @ 10 / 5 kV. No spark.
Wednesday, March 27, 2019, 14:57: BIAS / EZL @ 20 / 10 kV. No spark.
Scaling done IOC Restarted.
Thursday, April 04, 2019, 10:33: BIAS / EZL @ 20 / 10 kV. No spark.
Thursday, April 04, 2019, 10:35: BIAS / EZL / EE @ 30 / 13 / -1.5 kV. Anode at 200 V. No spark.
Thursday, April 04, 2019, 10:49: Sources brought to 0. No spark & scaling appears complete. |
|