835
|
Monday, December 21, 2020, 07:58 |
Aaron Schmidt | | | | | | | | Shutdown TS | Shutting down the ISAC TS for the planned
outage on Dec 22.
Monday, December 21, 2020, 07:50: |
|
836
|
Monday, January 04, 2021, 08:17 |
Aaron Schmidt | | | | | | | | Restart TS | Restarting TS after holidays & planned
power outage.
Monday, January 04, 2021, 08:17: |
|
842
|
Friday, January 29, 2021, 09:13 |
Aaron Schmidt | | LP-SIS | | | 44139-10 | 44378-2 | In progress | TS settings ok. | Friday, January 29, 2021, 09:11: CANBUS
controller was replaced. Quick systems check
ok. Sources, HV, & Optics all good. |
|
846
|
Monday, February 08, 2021, 09:20 |
Aaron Schmidt | | LP-SIS | | | 44139-10 | 44378-2 | Failed | Energy spread calibration with SIS. No PE | Re-salted. PE removed. EE Cleaned
Monday, February 08, 2021, 09:17:
Roughing. |
|
847
|
Tuesday, February 09, 2021, 14:02 |
Aaron Schmidt | | | | | | | Problems/Solutions | DI water loss | Tuesday, February 09, 2021, 13:43: DI water
flow completely stopped.
Control room contacted. DI water |
|
848
|
Wednesday, February 10, 2021, 09:49 |
Aaron Schmidt | | LP-SIS | | | 44691-8 | 44378-2 / 44378-3 | Failed | Energy spread calibration with SIS | Note* target has a ring on the TGHT - Right
leg. EE & PE placed. Target to HS OL
- OK. |
 |
852
|
Thursday, February 18, 2021, 10:47 |
Aaron Schmidt | | | | | | | | Optics loss / CANBUS failure. | Thursday, February 18, 2021, 10:45: TPS:Q3
& the TSB CBC CANBUS controllers had
failed yesterday, as well as a cable was |
|
853
|
Thursday, February 18, 2021, 11:03 |
Aaron Schmidt | | | | | | | Problems/Solutions | DI water pump configuration | https://elog.triumf.ca/TIS/Test-Stand/847
There was a previous DI CU-LCW
pump trip as per the above elog. The CU-LCW |
|
860
|
Tuesday, March 02, 2021, 11:42 |
Aaron Schmidt | | | | | | | | TS Tripped. | |
|
862
|
Wednesday, March 10, 2021, 14:28 |
Aaron Schmidt | | | | | | | In progress | RP2 swap. | Swapped RP2 out from a Varian SH-110 to
a Varian PTS06001.
Wednesday, March 10, 2021, 14:20: |
|
863
|
Wednesday, March 10, 2021, 14:57 |
Aaron Schmidt | | HP-FEBIAD | | | | 42752-5 | In progress | Emittance meter test with FEBIAD | Wednesday, March 10, 2021, 14:54: Roughing.
Wednesday, March 10, 2021, 14:57:
BV1A open. |
|
865
|
Thursday, March 25, 2021, 08:11 |
Aaron Schmidt | | | | | | | | Test Stand Tripped. (Water leak) | |
|
869
|
Tuesday, April 13, 2021, 13:27 |
Aaron Schmidt | | | | | | | | Indium gaskets installed FS#3 | Changed the gaskets from C-seals on FS#3
water blocks E, F,& H. G was already
done. |
|
873
|
Wednesday, May 19, 2021, 16:02 |
Aaron Schmidt | | | | | | | | P2N HS conditioning | Parasitic assemblies on the lid & end
plate included. Online HS.
Wednesday, May 19, 2021, 16:00: Roughing. |
|
874
|
Wednesday, May 26, 2021, 14:29 |
Aaron Schmidt | UC#33 (HS) | LP-SIS | ITW | TM2 | | 44378-3 | In progress | UC#33 HS conditioning | HS waterlines were very tight to line up.
Wednesday, May 26, 2021, 14:29: Roughing.
Wednesday, May 26, 2021, 15:09: TP1B |
|
875
|
Wednesday, June 02, 2021, 10:45 |
Aaron Schmidt | UC#34 HS | LP-SIS | | TM2 | 43044-13 | 44378-1 | In progress | UC#34 HS conditioning | Straight tube target / TGHT for outgassing.
Wednesday, June 02, 2021, 11:06:
Roughing. |
|
876
|
Monday, June 07, 2021, 13:45 |
Aaron Schmidt | Ta#62 | LP-SIS | ITE | TM4 | 44139-10 | 44378-4 | In progress | Ta#62 Conditioning | Monday, June 07, 2021, 13:44: Roughing.
Monday, June 07, 2021, 14:16: TP1B
on. (Tripped shortly after?) |
|
877
|
Monday, June 07, 2021, 14:40 |
Aaron Schmidt | | | | | | | Done | FC6 re-installed | Monday, June 07, 2021, 14:39: Roughing
beam line section.
Monday, June 07, 2021, 14:46: TMS:TP6 |
|
878
|
Wednesday, June 09, 2021, 11:51 |
Aaron Schmidt | | | | | | | Problems/Solutions | TPS:CB2 issue. | Tuesday, June 08, 2021, 08:25: IV4 open.
Optics set minus TPS:CB2. Shows as green
'on', set to 500V, however read back shows |
|
879
|
Wednesday, June 09, 2021, 14:31 |
Aaron Schmidt | Ta#62 | LP-SIS | ITE | TM4 | 44139-10 | 44378-4 | In progress | Install MB1 window & 9 pin for V test. | Installed a new window on MB1 as per Aurelia.
Connect modified 9 pin connector & voltage
meters for Ta#62 testing. |
|
|