Restarting TS after holidays & planned power outage.

Monday, January 04, 2021, 08:17: All epics controls in a 'white out' state.

Monday, January 04, 2021, 08:20: Rebooted PLC / IOC. Controls returned.

Monday, January 04, 2021, 08:22: Strip tools started / epics response ok.

Monday, January 04, 2021, 08:23: Switch on TMS:RP2 & TSG:RP1

Monday, January 04, 2021, 08:24: Open PV1 & PV2.

Monday, January 04, 2021, 08:26: Optics, steering, and archivers still in a non-responsive / 'white-out' state.


IOC rebooted on January 6. Controls returned to normal.