Entry  Monday, March 02, 2020, 14:42, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Full TS testing w/ HV using Ta#60 
Entry  Wednesday, March 04, 2020, 17:15, Fernando Maldonado, , , , , , , Problems/Solutions, Emittance rig communication 
Entry  Wednesday, March 11, 2020, 13:31, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Ta#60 w/ EE testing - 2 Ta#60_-_TS_Pre-condition_-_EE_Test_-_2.docx
Entry  Friday, March 27, 2020, 11:30, Aaron Schmidt, , , , , , , , Vacuum loss / spike / Shutdown Mar_27_-_2020_-_Vacuum_Trip.docx
   +  Reply  Tuesday, April 07, 2020, 10:53, Anders Mjos, , , , , , , , Vacuum loss / spike / Shutdown 
Entry  Tuesday, May 19, 2020, 06:01, Aaron Schmidt, , , , , , 42972-8, Problems/Solutions, Leak check / Troubleshoot May_19-20_Leak_check_-_FS#3.docxMess_inside_TS_-_1.jpgMess_inside_TS_-_2.jpgBlock_water_leak_visible.jpg
Entry  Monday, June 22, 2020, 07:07, Aaron Schmidt, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, In progress, Test FEBIAD (Fernando) FEBIAD_Testing_-_June_22_-_23.docxER-580-280-30kV-m28.txt
Entry  Thursday, June 25, 2020, 08:57, Fernando Maldonado, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, Done, FEBIAD development part 1/3 
Entry  Tuesday, June 30, 2020, 21:59, Fernando Maldonado, Test FEBIAD, HP-FEBIAD, , , 38295-8 , 42752-5 , Done, FEBIAD development part 2/3 
Entry  Monday, July 06, 2020, 05:28, Fernando Maldonado, Test FEBIAD , HP-FEBIAD, , , 38295-8 , 42752-5 , Done, FEBIAD development part 3/3 
Entry  Monday, July 13, 2020, 14:52, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 43515-2, , UCx HS conditioning.  
Entry  Monday, July 20, 2020, 11:40, Aaron Schmidt, (Empty-Test), , , , 44160-1, 43822-2, In progress, Conditioning Test P2N P2N_-_1_-_July-20-22-2020.docx
Entry  Tuesday, July 28, 2020, 13:27, Aaron Schmidt, , , , , , , Problems/Solutions, Water leak on magnet PS 
Entry  Tuesday, August 04, 2020, 15:07, Aaron Schmidt, UCx, LP-SIS, , , 44139-10, 43515-4, In progress, UCx HS conditioning with PEEK assembly UCx_-_HS_w-PEEK_Assy_-_43515-4.docx
Entry  Wednesday, August 05, 2020, 10:01, Aaron Schmidt, , , , , , , Problems/Solutions, Roughing pump swap out. 
Entry  Tuesday, August 11, 2020, 12:04, Aaron Schmidt, UCx, LP-SIS, , , 44139-10, 43515-4, In progress, UCx HS conditioning with PEEK assembly 
Entry  Tuesday, August 18, 2020, 10:00, Aaron Schmidt, , , , , , , , IDP15 Scroll pump installed - RP1 replaced 
Entry  Tuesday, August 18, 2020, 12:07, Aaron Schmidt, Test FEBIAD, HP-FEBIAD, , , 38295-8, 42752-5, In progress, RP check & Mass magnet check. 
Entry  Wednesday, August 19, 2020, 08:52, Aaron Schmidt, , , , , , , , Leak check / Troubleshoot Aug_19_-_2020_Leak_Check..docx
Entry  Tuesday, August 25, 2020, 07:23, Aaron Schmidt, , , , , , , Problems/Solutions, Beam line side vacuum trip 